AB-3005 Leroy Anderson Dam and Reservoir: permitting, environmental review, and public contracting.(2019-2020)

Senate
Assembly
Int
1st
Cmt
2nd
3rd
Pass
1st
Cmt
2nd
Cmt
2nd
3rd
2nd
3rd
Pass
Pass
Veto
Senate
Assembly
Int
1st
Cmt
2nd
3rd
Pass
1st
Cmt
2nd
Cmt
2nd
3rd
2nd
3rd
Pass
Pass
Veto

Bill Status
AB-3005
Robert Rivas (A)
-
Beall (S) , Berman (A) , Caballero (S) , Chu (A) , Gallagher (A) , Hill (S) , Kalra (A) , Monning (S) , Nielsen (S)
Leroy Anderson Dam and Reservoir: permitting, environmental review, and public contracting.
03/23/20
An act to add Section 1602.5 to the Fish and Game Code, to add Section 21163 to the Public Contract Code, to add Chapter 6.8 (commencing with Section 21189.60) to Division 13 of the Public Resources Code, and to add Section 13160.2 to, and to add Part 4 (commencing with Section 6700) to Division 3 of, the Water Code, relating to the Leroy Anderson Dam and Reservoir, and declaring the urgency thereof, to take effect immediately.
Assembly
09/04/20
08/24/20

Type of Measure
Inactive Bill - Vetoed
Two Thirds Vote Required
Non-Appropriation
Fiscal Committee
State-Mandated Local Program
Urgency
Non-Tax levy
Last 5 History Actions
Date Action
09/29/20 Vetoed by Governor.
09/15/20 Enrolled and presented to the Governor at 3 p.m.
08/31/20 Senate amendments concurred in. To Engrossing and Enrolling. (Ayes 75. Noes 1. Page 5443.).
08/30/20 In Assembly. Concurrence in Senate amendments pending.
08/30/20 Read third time. Urgency clause adopted. Passed. Ordered to the Assembly. (Ayes 39. Noes 0. Page 4500.).
Governor's Message
To the Members of the California State Assembly:

I am returning Assembly Bill 3005 without my signature.

This bill would modify contracting requirements and prescribe expedited California Environmental Quality Act (CEQA) review and regulatory processes for various state agencies to facilitate projects for the Leroy Anderson Dam and Reservoir.

Notwithstanding the importance of completing projects at the Anderson Dam, the bill sets unrealistic timelines for state entities to expedite deliverables. This will require staff to be diverted away from other critical projects throughout the state that are going through the CEQA process. Although the Anderson Dam projects are a key element of dam safety, it is problematic to set a precedent for a special process and timeline for one project that may undermine the quality of review by departments.

Furthermore, a public works project of this magnitude will have significant environmental impacts, and therefore, review through the full CEQA process is necessary.

For these reasons, I am returning Assembly Bill 3005 without my signature.

Sincerely,





Gavin Newsom