Amended
IN
Senate
March 18, 2024 |
Introduced by Senator Stern |
February 15, 2024 |
Existing law, the Public Utilities Act, directs the Public Utilities Commission to require each load-serving entity, defined to include electrical corporations, electric service providers, and community choice aggregators, to maintain physical generating capacity and electrical demand response adequate to meet their load requirements as part of their resource adequacy requirements.
This bill would require each load-serving entity to procure from virtual power plants, defined as actively coordinated aggregations of behind-the-meter distributed energy resources that can perform certain functions, sufficient capacity to meet specified minimum capacity requirements by certain dates, as provided. The bill would require capacity procured from a virtual power plant by a load-serving entity pursuant to these provisions to be used to meet the resource
adequacy requirements established for the load-serving entity. The bill would authorize the commission to postpone, in one-year increments, the deadlines for compliance with these requirements for a particular load-serving entity if the commission makes certain findings. The bill would require, on or before January 30, 2026, and each year thereafter, each load-serving entity to submit a report to the commission showing the load-serving entity’s progress toward complying with the virtual power plant capacity requirements.
(1)“Load-serving entity” has the same meaning as defined in Section 380.
(2)
(3)
(B)
(C)
(b)Each load-serving entity shall procure from virtual power plants sufficient capacity to meet the following capacity and timeline requirements:
(1)On or before January 1, 2028, a capacity of not less than 2.5 percent of the load-serving entity’s monthly system resource adequacy obligation.
(2)On or before January 1, 2030, a capacity of not less than 5 percent of the load-serving entity’s monthly system resource adequacy obligation.
(3)On or before January 1, 2031, a capacity of not less than 7.5 percent of the load-serving entity’s monthly system resource adequacy obligation.
(4)On or before January 1, 2032, a capacity of not less than 10 percent of the load-serving entity’s monthly system resource adequacy obligation.
(5)On or before January 1, 2033, a capacity of not less than 12.5 percent of the load-serving entity’s monthly system resource adequacy obligation.
(6)On or before January 1, 2035, a capacity of not less than 15 percent of the load-serving entity’s monthly system resource adequacy obligation.
(c)Capacity procured from a virtual power plant by a load-serving entity pursuant to this section shall be used to meet the resource adequacy requirements established for the load-serving entity pursuant to Section 380.
(d)The commission may postpone, in one-year increments, the deadlines specified for compliance with the capacity requirements in subdivision (b) for a particular load-serving entity. The commission shall only approve delayed compliance if the commission finds both of the following:
(1)The load-serving entity has fully explored all reasonable methods to comply with its procurement requirements.
(2)A one-year delay is warranted because compliance would not be cost effective, after considering all lifetime avoided costs of virtual power plants, including environmental costs, and all of the purposes served by virtual power plants.
(e)On or before January 30, 2026, and each year thereafter, each load-serving entity shall submit a report to the commission showing the load-serving entity’s progress toward complying with the virtual power plant capacity targets established pursuant to subdivision (b).