law requires a generator of hazardous waste to complete, sign, and provide to certain persons a manifest containing specific information under certain circumstances when hazardous waste is to be transported and, with certain exceptions, imposes a fee on the use of the hazardous waste manifest.
This bill would, on and after January 1, 2014, eliminate the fee on the use of the manifest.
(7)Existing law requires the State Board of Equalization to provide to the Legislature quarterly
reports on various hazardous waste fees collected.
This bill would make conforming changes with regard to those reports.
(8)Existing law requires the Department of Toxic Substances Control (DTSC) to suspend the permit of a facility for nonpayment of facility fees if the State Board of Equalization certifies in writing specified facts.
This bill would additionally authorize DTSC to certify in writing those facts.
(9)Existing law exempts from the hazardous waste facility fee a treatment facility engaged in treatment to accomplish a removal or remedial action or a corrective action in accordance with an order issued by the United States Environmental Protection Agency.
This bill would, on and after January 1, 2014, exempt from the hazardous waste facility fee a treatment facility engaged in removal or remedial actions pursuant to a removal action work plan or a remedial action plan that meets specific requirements and is authorized to operate by DTSC.
(10)Existing law establishes a base rate for the 1997 reporting period for a hazardous waste facility fee at $19,761 and requires for each reporting period thereafter that the State Board of Equalization adjust the base rate annually to reflect changes in the cost of living during the prior fiscal year.
This bill would, instead, establish the base rate for the 2013 reporting period for that fee at $30,005, and would require the State Board of Equalization to adjust the base rate and other specified rates related to hazardous waste annually to reflect increases or decreases in the cost of living during the prior fiscal year.
(11)Existing law requires a person who disposes of hazardous waste to pay a disposal fee. Existing law assesses a hazardous waste generator fee with a base rate of $2,748.
This bill would revise and recast these provisions to eliminate the disposal fee, and instead the bill would assess, on and after January 1, 2014, a generation and handling fee of $31.52 per ton of hazardous waste generated, except as specified. The bill would require the State Board of Equalization to adjust the fee schedule to reflect changes in the cost of living during the prior fiscal year.
(12)Existing law provides a hazardous waste generator with a credit toward the generator fee if the generator pays an inspection fee to a Certified Unified Program Agency with jurisdiction over the facility or transfers hazardous materials offsite for recycling.
This bill would, on and after January 1, 2014, repeal those credits.
(13)Existing law provides a person who applies for, or requests, specified permits, variances, or waste classification determinations with the option of paying a flat fee or entering into a reimbursement agreement to reimburse DTSC for costs
incurred in processing the application or response to the request.
This bill would eliminate the flat fee option. The bill would additionally require the reimbursement agreement to provide for the reimbursement of the costs incurred by DTSC in reviewing and overseeing corrective action.
(14)Existing law imposes an annual verification fee upon generators, transporters, and facility operators with more than 50 employees that possess a valid identification number issued by DTSC or the United States Environmental Protection Agency.
This bill would, on and after January 1, 2014, eliminate that fee.
(15)Existing law exempts from certain reimbursement requirements an application to modify a permit for a facility’s allowable capacity for treatment or storage of hazardous waste. Existing law exempts, from fees assessed on used oil, used oil removed from a motor vehicle that is subsequently recycled by a permitted recycler.
This bill would eliminate those exemptions. Because a failure to pay this fee is a crime, this bill would impose a state-mandated local program.
(16)Existing law exempts from the hazardous waste generator fee a person transporting, importing, or receiving certain hazardous waste imported into the state.
This bill would, on and after January 1, 2014, eliminate this exemption. Because a failure to pay this fee is a crime, this bill would impose a state-mandated local program.
(17)This bill would make conforming changes and delete obsolete provisions pertaining
to the state’s hazardous waste programs.
(18)
(19)
(20)
(21)
(22)
(23)
(24)
(25)
(26)
(27)
(28)
(29)
(30)
(31)
(32)
(33)
(34)
(35)
(36)
(37)
(38)
(39)
(40)
(41)
(42)
(43)
(44)
(45)
(46)
(47)
(48)
(49)
(50)
(51)
(52)
(53)
(54)
(a)For purposes of this chapter, the following definitions apply:
(1)“Manifest” means a shipping document originated and signed by a generator of hazardous waste that contains all of the information required by the department and that complies with all applicable federal and state regulations.
(2)“California Uniform Hazardous Waste Manifest” means either of the following:
(A)A manifest document printed and supplied by the state for a shipment initiated on or before September 4, 2006.
(B)The Uniform Hazardous Waste Manifest printed by a source registered with the United States Environmental Protection Agency for a shipment initiated on or after September 5, 2006.
(3)For purposes of this section and Section 25205.15, a shipment is initiated on the date when the manifest is signed by the first transporter and the hazardous waste leaves the site where it is generated.
(b)(1)Except as provided in Section 25160.2 or 25160.8, or as otherwise authorized by a variance issued by the department, a person generating hazardous waste that is transported, or submitted for transportation, for offsite handling, treatment, storage, disposal, or any combination thereof, shall complete a manifest prior to the time the waste is transported or offered for
transportation, and shall designate on that manifest the facility to which the waste is to be shipped for the handling, treatment, storage, disposal, or combination thereof. The manifest shall be completed as required by the department. The generator shall provide the manifest to the person who will transport the hazardous waste, who is the driver, if the hazardous waste will be transported by vehicle, or the person designated by the railroad corporation or vessel operator, if the hazardous waste will be transported by rail or vessel.
(A)The generator shall use the standard California Uniform Hazardous Waste Manifest supplied by the department for all shipments of hazardous waste initiated on and before September 4, 2006, for which a manifest is required, except as provided in paragraph (2).
(B)The generator shall use the Uniform Hazardous Waste Manifest printed by a source registered with the United States Environmental Protection Agency for all shipments of hazardous waste initiated on and after September 5, 2006, for which a manifest is required.
(C) A manifest shall only be used for the purposes specified in this chapter, including, but not limited to, identifying materials that the person completing the manifest reasonably believes are hazardous waste.
(D)Within 30 days from the date of transport, or submission for transport, of hazardous waste, each generator of that hazardous waste shall submit to the department a legible copy of each manifest used. The copy submitted to the department shall contain the signatures of the generator and the transporter.
(E)In lieu of submitting a copy of each manifest used, a generator may submit an electronic report to the department meeting the requirements of Section 25160.3.
(2)Except as provided in Section 25160.2 or 25160.8 or as otherwise authorized by a variance issued by the department, a person generating hazardous waste that is transported, or submitted for transportation, for offsite handling, treatment, storage, disposal, or any combination thereof, outside of the state, shall complete, whether or not the waste is determined to be hazardous by the importing country or state, a manifest in accordance with the following conditions:
(A)The generator shall use the standard California Uniform Hazardous Waste Manifest or the manifest required by the receiving state for all shipments of hazardous waste initiated on and before September 4, 2006, for which a manifest is required.
(B)The generator shall use the Uniform Hazardous Waste Manifest printed by a source registered with the United States Environmental Protection Agency for all shipments of hazardous waste initiated on and after September 5, 2006, for which a manifest is required.
(C)The generator shall submit a copy of the manifest specified in subparagraph (A) or (B), as applicable, to the department within 30 days from the date of the transport, or submission for transport, of the hazardous waste. In lieu of submitting a copy of each manifest used, a generator may submit an electronic report to the department meeting the requirements of Section 25160.3.
(3)Within 30 days from the date of transport, or submission for transport, of hazardous waste out of state, each generator of that hazardous waste shall submit to the department a legible copy of each manifest used. The copy submitted to the department shall contain the signatures of the generator, all transporters, excepting intermediate rail transporters, and the out-of-state facility operator. If within 35 days from the date of the initial shipment, or for exports by water to foreign countries 60 days after the initial shipment, the generator has not received a copy of the manifest signed by all transporters and the facility operator, the generator shall contact the owner or operator of the designated facility to determine the status of the hazardous waste and to request that the owner or operator immediately provide a signed copy of the manifest to the generator. Except as provided otherwise in paragraph (2) of subdivision (h) of Section 25123.3, if within 45 days from the date of the initial shipment or, for exports by water to foreign countries, 90 days from the date of the initial shipment, the generator has not received a copy of the signed manifest from the facility owner or operator, the generator shall submit an exception report to the department.
(4)For shipments of waste that do not require a manifest pursuant to Title 40 of the Code of Federal Regulations, the department, by regulation, may establish manifest requirements that differ from the requirements of this section. The requirements for an alternative form of manifest shall ensure that the hazardous waste is transported by a registered hazardous waste transporter, that the hazardous waste is tracked, and that human health and safety and the environment are protected.
(5)(A)Notwithstanding any other provision of this section, except as provided in subparagraph (B), the generator copy of the manifest is not required to be submitted to the department for any waste transported in compliance with the consolidated manifest procedures in Section 25160.2 or with the procedures specified in Section 25160.8, or when the transporter is operating pursuant to a variance issued by the department pursuant to Section 25143 authorizing the use of a consolidated manifest for waste not listed in Section 25160.2, if the generator, transporter, and facility are all identified as the same company on the hazardous waste manifest. If multiple identification numbers are used by a single company, all of the company’s identification numbers shall be included in its annual transporter registration application, if those numbers will be used with the consolidated manifest procedure. Nothing in this paragraph affects the obligation of a facility operator to submit to the department a copy of a manifest pursuant to this section.
(B)If the waste subject to subparagraph (A) is transported out of state, the generator shall either ensure that the facility operator submits to the department a copy of the manifest or the generator shall submit a copy to the department that contains the signatures of the generator, all transporters, excepting intermediate rail transporters, and the out-of-state facility operator pursuant to paragraph (3).
(c)(1)The department
shall determine the form and manner in which a manifest shall be completed and the information that the manifest shall contain. The information requested on the manifest shall serve as the data dictionary for purposes of the developing of an electronic reporting format pursuant to Section 71062 of the Public Resources Code. The form of each manifest and the information requested on each manifest shall be the same for all hazardous wastes, regardless of whether the hazardous wastes are also regulated pursuant to the federal act or by regulations adopted by the United States Department of Transportation. However, the form of the manifest and the information required shall be consistent with federal regulations.
(2)Pursuant to federal regulations, the department may require information on the manifest in addition to the information required by federal regulations.
(d)(1)A person who transports hazardous waste in a vehicle shall have a manifest in his or her possession while transporting the hazardous waste. The manifest shall be shown upon demand to any representative of the department, any officer of the Department of the California Highway Patrol, any local health officer, any certified unified program agency, or any local public officer designated by the director. If the hazardous waste is transported by rail or vessel, the railroad corporation or vessel operator shall comply with Subchapter C (commencing with Section 171.1) of Chapter 1 of Subtitle B of Title 49 of the Code of Federal Regulations and shall also enter on the shipping papers any information concerning the hazardous waste that the department may require.
(2)Any person who transports a waste, as defined by Section 25124, and who is provided with a manifest for that waste shall, while transporting that waste, comply with all requirements of this chapter, and the regulations adopted pursuant thereto, concerning the transportation of hazardous waste.
(3)A person who transports hazardous waste shall transfer a copy of the manifest to the facility operator at the time of delivery, or to the person who will subsequently transport the hazardous waste in a vehicle. A person who transports hazardous waste and then transfers custody of that hazardous waste to a person who will subsequently transport that waste by rail or vessel shall transfer a copy of the manifest to the person designated by the railroad corporation or vessel operator, as specified by Subchapter C (commencing with Section 171.1) of Chapter 1 of Subtitle B of Title 49 of the Code of Federal Regulations.
(4)A person transporting hazardous waste by motor vehicle, rail, or water shall certify to the department, at the time of initial registration and at the time of renewal of that registration pursuant to this article, that the transporter is familiar with the requirements of this section, the department regulations, and federal laws and regulations governing the use of manifests.
(e)(1)A facility operator in the state who receives hazardous waste for handling, treatment, storage, disposal, or any combination thereof, which was transported with a manifest pursuant to this section, shall submit a copy of the manifest to the
department within 30 days from the date of receipt of the hazardous waste. The copy submitted to the department shall contain the signatures of the generator, all transporters, excepting intermediate rail transporters, and the facility operator. In instances in which the generator or transporter is not required by the generator’s state or federal law to sign the manifest, the facility operator shall require the generator and all transporters, excepting intermediate rail transporters, to sign the manifest before receiving the waste at any facility in this state. In lieu of submitting a copy of each manifest used, a facility operator may submit an electronic report to the department meeting the requirements of Section 25160.3.
(2)Any treatment, storage, or disposal facility receiving hazardous waste generated outside this state may only accept the hazardous waste for treatment, storage, disposal, or any combination thereof, if the hazardous waste is accompanied by a completed standard California Uniform Hazardous Waste Manifest.
(3)A facility operator may accept hazardous waste generated offsite that is not accompanied by a properly completed and signed standard California Uniform Hazardous Waste Manifest if the facility operator meets both of the following conditions:
(A)The facility operator is authorized to accept the hazardous waste pursuant to a hazardous waste facilities permit or other grant of authorization from the department.
(B)The facility operator is in compliance with the regulations adopted by the department specifying the conditions and procedures applicable to the receipt of hazardous waste under these circumstances.
(4)This subdivision applies only to shipments of hazardous waste for which a manifest is required pursuant to this section and the regulations adopted pursuant to this section.
(f)A generator, transporter, or facility operator may comply with the requirements of Sections 66262.40, 66263.22, 66264.71, and 66265.71 of Title 22 of the California Code of Regulations by storing manifest information electronically. A generator, transporter, or facility operator who stores manifest information electronically shall use the standardized electronic format and protocol for the exchange of electronic data established by the Secretary for Environmental Protection pursuant to Part 2 (commencing with Section 71050) of Division
34 of the Public Resources Code and the stored information shall include all the information required to be retained by the department, including all signatures required by this section.
(g)The department shall make available for review, by any interested party, the department’s plans for revising and enhancing its system for tracking hazardous waste for the purposes of protecting human health and the environment, enforcing laws, collecting revenue, and generating necessary reports.
(h)This section shall remain in effect only until January 1, 2014, and as of that date is repealed, unless a later enacted statute, that is enacted before January 1, 2014, deletes or extends that date.
(a)For purposes of this chapter, the following definitions apply:
(1)“Manifest” means a shipping document originated and signed by a generator of hazardous waste that contains all of the information required by the department and that complies with all applicable federal and state regulations.
(2)“California Uniform Hazardous Waste Manifest” means either of the following:
(A)A manifest document printed and supplied by the state for a shipment initiated on or before September 4, 2006.
(B)The Uniform Hazardous Waste Manifest printed by a source registered with the United States Environmental Protection Agency for a shipment initiated on or after September 5, 2006.
(3)For purposes of this section, a shipment is initiated on the date when the manifest is signed by the first transporter and the hazardous waste leaves the site where it is generated.
(b)(1)Except as provided in Section 25160.2 or 25160.8, or as otherwise authorized by a variance issued by the department, a person generating hazardous waste that is transported, or submitted for transportation, for offsite handling, treatment, storage, disposal, or any combination thereof, shall complete a manifest prior to the time the waste is transported or offered for transportation, and shall designate on that manifest the facility to which
the waste is to be shipped for the handling, treatment, storage, disposal, or combination thereof. The manifest shall be completed as required by the department. The generator shall provide the manifest to the person who will transport the hazardous waste, who is the driver, if the hazardous waste will be transported by vehicle, or the person designated by the railroad corporation or vessel operator, if the hazardous waste will be transported by rail or vessel.
(A)The generator shall use the standard California Uniform Hazardous Waste Manifest supplied by the department for all shipments of hazardous waste initiated on and before September 4, 2006, for which a manifest is required, except as provided in paragraph (2).
(B)The generator shall use the Uniform Hazardous Waste Manifest printed by a source registered with the United States Environmental Protection Agency for all shipments of hazardous waste initiated on and after September 5, 2006, for which a manifest is required.
(C)A manifest shall only be used for the purposes specified in this chapter, including, but not limited to, identifying materials that the person completing the manifest reasonably believes are hazardous waste.
(D)Within 30 days from the date of transport, or submission for transport, of hazardous waste, each generator of that hazardous waste shall submit to the department a legible copy of each manifest used. The copy submitted to the department shall contain the signatures of the generator and the transporter.
(E)In lieu of submitting a copy of each manifest used, a generator may submit an electronic report to the department meeting the requirements of Section 25160.3.
(2)Except as provided in Section 25160.2 or 25160.8 or as otherwise authorized by a variance issued by the department, a person generating hazardous waste that is transported, or submitted for transportation, for offsite handling, treatment, storage, disposal, or any combination thereof, outside of the state, shall complete, whether or not the waste is determined to be hazardous by the importing country or state, a manifest in accordance with the following conditions:
(A)The generator shall use the standard California Uniform Hazardous Waste Manifest or the manifest required by the receiving state for all shipments of hazardous waste initiated on and before September 4, 2006, for which a manifest is required.
(B)The generator shall use the Uniform Hazardous Waste Manifest printed by a source registered with the United States Environmental Protection Agency for all shipments of hazardous waste initiated on and after September 5, 2006, for which a manifest is required.
(C)The generator shall submit a copy of the manifest specified in subparagraph (A) or (B), as applicable, to the department within 30 days from the date of the transport, or submission for transport, of the hazardous waste. In lieu of submitting a copy of each manifest used, a generator may submit an electronic report to the department meeting the requirements of Section 25160.3.
(3)Within 30 days from the date of transport, or submission for transport, of hazardous waste out of state, each generator of that hazardous waste shall submit to the department a legible copy of each manifest used. The copy submitted to the department shall contain the signatures of the generator, all transporters, excepting intermediate rail transporters, and the out-of-state facility operator. If within 35 days from the date of the initial shipment, or for exports by water to foreign countries 60 days after the initial shipment, the generator has not received a copy of the manifest signed by all transporters and the facility operator, the generator shall contact the owner or operator of the designated facility to determine the status of the hazardous waste and to request that the owner or operator immediately provide a signed copy of the manifest to the generator. Except as provided otherwise in paragraph (2) of subdivision (h) of Section 25123.3, if within 45 days from the date of the initial shipment or, for exports by water to foreign countries, 90 days from the date of the initial shipment, the generator has not received a copy of the signed manifest from the facility owner or operator, the generator shall submit an exception report to the department.
(4)For shipments of waste that do not require a manifest pursuant to Title 40 of the Code of Federal Regulations, the department, by regulation, may establish manifest requirements that differ from the requirements of this section. The requirements for an alternative form of manifest shall ensure that the hazardous waste is transported by a registered hazardous waste transporter, that the hazardous waste is tracked, and that human health and safety and the environment are protected.
(5)(A)Notwithstanding any other provision of this section, except as provided in subparagraph (B), the generator copy of the manifest is not required to be submitted to the department for any waste transported in compliance with the consolidated manifest procedures in Section 25160.2 or with the procedures specified in Section 25160.8, or when the transporter is operating pursuant to a variance issued by the department pursuant to Section 25143 authorizing the use of a consolidated manifest for waste not listed in Section 25160.2, if the generator, transporter, and facility are all identified as the same company on the hazardous waste manifest. If multiple identification numbers are used by a single company, all of the company’s identification numbers shall be included in its annual transporter registration application, if those numbers will be used with the consolidated manifest procedure. Nothing in this paragraph affects the obligation of a facility operator to submit to the department a copy of a manifest pursuant to this section.
(B)If the waste subject to subparagraph (A) is transported out of state, the generator shall either ensure that the facility operator submits to the department a copy of the manifest or the generator shall submit a copy to the department that contains the signatures of the generator, all transporters, excepting intermediate rail transporters, and the out-of-state facility operator pursuant to paragraph (3).
(c)(1)The department shall determine the form and manner in which a manifest shall be completed and the
information that the manifest shall contain. The information requested on the manifest shall serve as the data dictionary for purposes of the developing of an electronic reporting format pursuant to Section 71062 of the Public Resources Code. The form of each manifest and the information requested on each manifest shall be the same for all hazardous wastes, regardless of whether the hazardous wastes are also regulated pursuant to the federal act or by regulations adopted by the United States Department of Transportation. However, the form of the manifest and the information required shall be consistent with federal regulations.
(2)Pursuant to federal regulations, the department may require information on the manifest in addition to the information required by federal regulations.
(d)(1)A person who transports hazardous waste in a vehicle shall have a manifest in his or her possession while transporting the hazardous waste. The manifest shall be shown upon demand to any representative of the department, any officer of the Department of the California Highway Patrol, any local health officer, any certified unified program agency, or any local public officer designated by the director. If the hazardous waste is transported by rail or vessel, the railroad corporation or vessel operator shall comply with Subchapter C (commencing with Section 171.1) of Chapter 1 of Subtitle B of Title 49 of the Code of Federal Regulations and shall also enter on the shipping papers any information concerning the hazardous waste that the department may require.
(2)Any person who transports a waste, as defined by Section 25124, and who is provided with a manifest for that waste shall, while transporting that waste, comply with all requirements of this chapter, and the regulations adopted pursuant thereto, concerning the transportation of hazardous waste.
(3)A person who transports hazardous waste shall transfer a copy of the manifest to the facility operator at the time of delivery, or to the person who will subsequently transport the hazardous waste in a vehicle. A person who transports hazardous waste and then transfers custody of that hazardous waste to a person who will subsequently transport that waste by rail or vessel shall transfer a copy of the manifest to the person designated by the railroad corporation or vessel operator, as specified by Subchapter C (commencing with Section 171.1) of Chapter 1 of Subtitle B of Title 49 of the Code of Federal Regulations.
(4)A person transporting hazardous waste by motor vehicle, rail, or water shall certify to the department, at the time of initial registration and at the time of renewal of that registration pursuant to this article, that the transporter is familiar with the requirements of this section, the department regulations, and federal laws and regulations governing the use of manifests.
(e)(1)A facility operator in the state who receives hazardous waste for handling, treatment, storage, disposal, or any combination thereof, which was transported with a manifest pursuant to this section, shall submit a copy of the manifest to the department within 30 days from the date of receipt of the hazardous waste. The copy submitted to the
department shall contain the signatures of the generator, all transporters, excepting intermediate rail transporters, and the facility operator. In instances in which the generator or transporter is not required by the generator’s state or federal law to sign the manifest, the facility operator shall require the generator and all transporters, excepting intermediate rail transporters, to sign the manifest before receiving the waste at any facility in this state. In lieu of submitting a copy of each manifest used, a facility operator may submit an electronic report to the department meeting the requirements of Section 25160.3.
(2)Any treatment, storage, or disposal facility receiving hazardous waste generated outside this state may only accept the hazardous waste for treatment, storage, disposal, or any combination thereof, if the hazardous waste is accompanied by a completed standard California Uniform Hazardous Waste Manifest.
(3)A facility operator may accept hazardous waste generated offsite that is not accompanied by a properly completed and signed standard California Uniform Hazardous Waste Manifest if the facility operator meets both of the following conditions:
(A)The facility operator is authorized to accept the hazardous waste pursuant to a hazardous waste facilities permit or other grant of authorization from the department.
(B)The facility operator is in compliance with the regulations adopted by the department specifying the conditions and procedures applicable to the receipt of hazardous waste under these circumstances.
(4)This subdivision applies only to shipments of hazardous waste for which a manifest is required pursuant to this section and the regulations adopted pursuant to this section.
(f)A generator, transporter, or facility operator may comply with the requirements of Sections 66262.40, 66263.22, 66264.71, and 66265.71 of Title 22 of the California Code of Regulations by storing manifest information electronically. A generator, transporter, or facility operator who stores manifest information electronically shall use the standardized electronic format and protocol for the exchange of electronic data established by the Secretary for Environmental Protection pursuant to Part 2 (commencing with Section 71050) of Division 34 of the Public Resources Code and the stored information
shall include all the information required to be retained by the department, including all signatures required by this section.
(g)The department shall make available for review, by any interested party, the department’s plans for revising and enhancing its system for tracking hazardous waste for the purposes of protecting human health and the environment, enforcing laws, collecting revenue, and generating necessary reports.
(h)This section shall become operative on January 1, 2014, and shall apply to the fees due for the 2014 reporting period and thereafter, including the prepayments due during the reporting period and the final reconciliation fee due and payable following the reporting period.
(a)There is in the General Fund the Hazardous Waste Control Account, which shall be administered by the director. In addition to any other money that may be deposited in the Hazardous Waste Control Account, pursuant to statute, all of the following amounts shall be deposited in the account:
(1)The fees collected pursuant to Sections 25174.1, 25205.2, 25205.5, 25205.14, 25205.15, and 25205.16.
(2)The fees collected pursuant to Section 25187.2, to the extent that those fees are for the oversight of corrective action taken under this chapter.
(3)Any interest earned upon the money deposited in the Hazardous Waste Control Account.
(4)Any money received from the federal government pursuant to the federal act.
(5)Any reimbursements for funds expended from the Hazardous Waste Control Account for services provided by the department pursuant to this chapter, including, but not limited to, the reimbursements required pursuant to Sections 25201.9 and 25205.7.
(b)The funds deposited in the Hazardous Waste Control Account may be appropriated by the Legislature, for expenditure as follows:
(1)To the department for the administration and implementation of this chapter.
(2)To the department for allocation to the State Board of Equalization to pay refunds of fees collected pursuant to Sections 43051 and 43053 of the Revenue and Taxation Code and for the administration and collection of the fees imposed pursuant to Article 9.1 (commencing with Section 25205.1) that are deposited into the Hazardous Waste Control Account.
(3)To the department for the costs of performance or review of analyses of past, present, or potential environmental public health effects related to toxic substances, including extremely hazardous waste, as defined in Section 25115, and hazardous waste, as defined in Section 25117.
(4)(A)To the department for allocation to the office of the Attorney General for the support of the Toxic Substance Enforcement Program in the office of the Attorney General, in carrying out the purposes of this chapter.
(B)On or before October 1 of each year, the Attorney General shall report to the Legislature on the expenditure of any funds allocated to the office of the Attorney General for the preceding fiscal year pursuant to this paragraph and paragraph (14) of subdivision (b) of Section 25173.6. The report shall include all of the following:
(i)A description of cases resolved by the office of the Attorney General through settlement or court order, including the monetary benefit to the department and the state.
(ii)A description of injunctions or other court orders benefiting the people of the state.
(iii)A description of any cases in which the Attorney General’s Toxic Substance Enforcement Program is representing the department or the state against claims by defendants or responsible parties.
(iv)A description of other pending litigation handled by the Attorney General’s Toxic Substance Enforcement Program.
(C)Nothing in subparagraph (C) shall require the Attorney General to report on any confidential or investigatory matter.
(5)To the department for administration and implementation of Chapter 6.11 (commencing with Section 25404).
(c)(1)Expenditures from the Hazardous
Waste Control Account for support of state agencies other than the department shall, upon appropriation by the Legislature to the department, be subject to an interagency agreement or similar mechanism between the department and the state agency receiving the support.
(2)The department shall, at the time of the release of the annual Governor’s Budget, describe the budgetary amounts proposed to be allocated to the State Board of Equalization, as specified in paragraph (2) of subdivision (b) and in paragraph (3) of subdivision (b) of Section 25173.6, for the upcoming fiscal year.
(3)It is the intent of the Legislature that moneys appropriated in the annual Budget Act each year for the purpose of reimbursing the State Board of Equalization, a private party, or other public agency, for the administration and collection of the fees imposed pursuant to Article 9.1 (commencing with Section 25205.1) and deposited in the Hazardous Waste Control Account, shall not exceed the costs incurred by the State Board of Equalization, the private party, or other public agency, for the administration and collection of those fees.
(d)With respect to expenditures for the purposes of paragraphs (1) and (3) of subdivision (b) and paragraphs (1) and (2) of subdivision (b) of Section 25173.6, the department shall, at the time of the release of the annual Governor’s Budget, also make available the budgetary amounts and allocations of staff resources of the department proposed for the following activities:
(1)The department shall identify, by permit type, the projected allocations of budgets and staff resources for hazardous waste facilities permits, including standardized permits, closure plans, and postclosure permits.
(2)The department shall identify, with regard to surveillance and enforcement activities, the projected allocations of budgets and staff resources for the following types of regulated facilities and activities:
(A)Hazardous waste facilities operating under a permit or grant of interim status issued by the department, and generator activities conducted at those facilities. This information shall be reported by permit type.
(B)Transporters.
(C)Response to complaints.
(3)The department shall identify the projected allocations of budgets and staff resources for both of the following activities:
(A)The registration of hazardous waste transporters.
(B)The operation and maintenance of the hazardous waste manifest system.
(4)The department shall identify, with regard to site mitigation and corrective action, the projected allocations of budgets and staff resources for the oversight and implementation of the following activities:
(A)Investigations and removal and remedial actions at military bases.
(B)Voluntary investigations and removal and remedial actions.
(C)State match and operation and maintenance costs, by site, at joint state and federally funded National Priority List Sites.
(D)Investigation, removal and remedial actions, and operation and maintenance at the Stringfellow Hazardous Waste Site.
(E)Investigation, removal and remedial actions, and operation and maintenance at the Casmalia Hazardous Waste Site.
(F)Investigations and removal and remedial actions at nonmilitary, responsible party lead National Priority List Sites.
(G)Preremedial activities under the federal Comprehensive Environmental Response, Compensation, and Liability Act of 1980 (42 U.S.C. Sec. 9601 et seq.).
(H)Investigations, removal and remedial actions, and operation and maintenance at state-only orphan sites.
(I)Investigations and removal and remedial actions at nonmilitary, non-National Priority List responsible party lead sites.
(J)Investigations, removal and remedial actions, and operation and maintenance at Expedited Remedial Action Program sites pursuant to former Chapter 6.85 (commencing with Section 25396).
(K)Corrective actions at hazardous waste facilities.
(5)The department shall identify, with regard to the regulation of hazardous waste, the projected allocation of budgets and staff resources for the following activities:
(A)Determinations pertaining to the classification of hazardous wastes.
(B)Determinations for variances made pursuant to Section 25143.
(C)Other determinations and responses to public inquiries made by the department regarding the regulation of hazardous waste and hazardous substances.
(6)The department shall identify projected allocations of budgets and staff resources needed to do all of the following:
(A)Identify, remove, store, and dispose of, suspected hazardous substances or hazardous materials associated with the investigation of clandestine drug laboratories.
(B)Respond to emergencies pursuant to Section 25354.
(C)Create, support, maintain, and implement the railroad accident prevention and immediate deployment plan developed pursuant to Section 7718 of the Public Utilities Code.
(7)The department shall identify projected allocations of budgets and staff resources for the administration and implementation of the unified hazardous waste and hazardous materials regulatory program established pursuant to Chapter 6.11 (commencing with Section 25404).
(8)The department shall identify the total cumulative expenditures of the Regulatory Structure Update and Site Mitigation Update projects since their inception, and shall identify the total projected allocations of budgets and staff resources that are needed to continue these projects.
(9)The department shall identify the total projected allocations of budgets and staff resources that are necessary for all other activities proposed to be conducted by the department.
(e)Notwithstanding this chapter, or Part 22 (commencing with Section 43001) of Division 2 of the Revenue and Taxation Code, for any fees, surcharges, fines, penalties, and funds that are required to be deposited into the Hazardous Waste Control Account or the Toxic Substances Control Account, the department, with the approval of the Secretary for Environmental Protection, may take any of the following actions:
(1)Assume responsibility for, or enter into a contract with a private party or with another public agency, other than the State Board of Equalization, for the collection of any fees, surcharges, fines, penalties and funds described in subdivision (a) or otherwise described in this chapter or Chapter 6.8 (commencing with Section 25300), for deposit into the Hazardous Waste Control Account or the Toxic Substances Control Account.
(2)Administer, or by mutual agreement, contract with a private party or another public agency, for the making of those determinations and the performance of functions that would otherwise be the responsibility of the State Board of Equalization pursuant to this chapter, Chapter 6.8 (commencing with Section 25300), or Part 22 (commencing with Section 43001) of Division 2 of the Revenue and Taxation Code, if those activities and functions for which the State Board of Equalization would otherwise be responsible become the responsibility of the department or, by mutual agreement, the contractor selected by the department.
(f)If, pursuant to subdivision (e), the department, or a private party or another public agency, pursuant to a contract with the department, performs the determinations and functions that would otherwise be the responsibility of the State Board of Equalization, the department shall be responsible for ensuring that persons who are subject to the fees specified in subdivision (e) have equivalent rights to public notice and comment, and procedural and substantive rights of appeal, as afforded by the procedures of the State Board of Equalization pursuant to Part 22 (commencing
with Section 43001) of Division 2 of the Revenue and Taxation Code. Final responsibility for the administrative adjustment of fee rates and the administrative appeal of any fees or penalty assessments made pursuant to this section may only be assigned by the department to a public agency.
(g)If, pursuant to subdivision (e), the department, or a private party or another public agency, pursuant to a contract with the department, performs the determinations and functions that would otherwise be the responsibility of the State Board of Equalization, the department shall have equivalent authority to make collections and enforce judgments as provided to the State Board of Equalization pursuant to Part 22 (commencing with Section 43001) of Division 2 of the Revenue and Taxation Code. Unpaid amounts, including penalties and interest, shall
be a perfected and enforceable state tax lien in accordance with Section 43413 of the Revenue and Taxation Code.
(h)The department, with the concurrence of the Secretary for Environmental Protection, shall determine which administrative functions should be retained by the State Board of Equalization, administered by the department, or assigned to another public agency or private party pursuant to subdivisions (e), (f), and (g).
(i)The department may adopt regulations to implement subdivisions (e) to (h), inclusive.
(j)The Director of Finance, upon request of the director, may make a loan from the General Fund to the Hazardous Waste Control Account to meet cash needs. The loan shall be subject to the
repayment provisions of Section 16351 of the Government Code and the interest provisions of Section 16314 of the Government Code.
(k)The department shall establish, within the Hazardous Waste Control Account, a reserve of at least one million dollars ($1,000,000) each year to ensure that all programs funded by the Hazardous Waste Control Account will not be adversely affected by any revenue shortfalls.
(l)This section shall remain in effect only until January 1, 2014, and as of that date is repealed, unless a later enacted statute, that is enacted before January 1, 2014, deletes or extends that date.
(a)There is in the General Fund the Hazardous Waste Control Account, which shall be administered by the director. In addition to any other money that may be deposited in the Hazardous Waste Control Account, pursuant to statute, all of the following amounts shall be deposited in the account:
(1)The fees collected pursuant to Sections 25205.2, 25205.5, and 25205.14.
(2)The fees collected pursuant to Section 25187.2, to the extent that those fees are for the oversight of corrective action taken under this chapter.
(3)Any interest earned upon the money deposited in the Hazardous Waste Control Account.
(4)Any money received from the federal government pursuant to the federal act.
(5)Any reimbursements for funds expended from the Hazardous Waste Control Account for services provided by the department pursuant to this chapter, including, but not limited to, the reimbursements required pursuant to Sections 25201.9 and 25205.7.
(b)The funds deposited in the Hazardous Waste Control Account may be appropriated by the Legislature, for expenditure as follows:
(1)To the department for the administration and implementation of this chapter.
(2)To the department for allocation to the State Board of Equalization to pay refunds of fees collected pursuant to Sections 43051 and 43053 of the Revenue and Taxation Code and for the administration and collection of the fees imposed pursuant to Article 9.1 (commencing with Section 25205.1) that are deposited into the Hazardous Waste Control Account.
(3)To the department for the costs of performance or review of analyses of past, present, or potential environmental public health effects related to toxic substances, including extremely hazardous waste, as defined in Section 25115, and hazardous waste, as defined in Section 25117.
(4)(A)To the department for allocation to the office of the Attorney General for the support of the Toxic Substance Enforcement Program in the office of the Attorney General, in carrying out the purposes of this chapter.
(B)On or before October 1 of each year, the Attorney General shall report to the Legislature on the expenditure of any funds allocated to the office of the Attorney General for the preceding fiscal year pursuant to this paragraph and paragraph (14) of subdivision (b) of Section 25173.6. The report shall include all of the following:
(i)A description of cases resolved by the office of the Attorney General through settlement or court order, including the monetary benefit to the department and the state.
(ii)A description of injunctions or other court orders benefiting the people of the state.
(iii)A description of any cases in which the Attorney General’s Toxic Substance Enforcement Program is representing the department or the state against claims by defendants or responsible parties.
(iv)A description of other pending litigation handled by the Attorney General’s Toxic Substance Enforcement Program.
(C)Nothing in subparagraph (C) shall require the Attorney General to report on any confidential or investigatory matter.
(5)To the department for administration and implementation of Chapter 6.11 (commencing with Section 25404).
(c)(1)Expenditures from the Hazardous Waste Control Account for support of state agencies other than the department shall, upon appropriation by the Legislature to the department, be subject to an interagency agreement or similar mechanism between the department and the state agency receiving the support.
(2)The department shall, at the time of the release of the annual Governor’s Budget, describe the budgetary amounts proposed to be allocated to the State Board of Equalization, as specified in paragraph (2) of subdivision (b) and in paragraph (3) of subdivision (b) of Section 25173.6, for the upcoming fiscal year.
(3)It is the intent of the Legislature that moneys appropriated in the annual Budget Act each year for the purpose of reimbursing the State Board of Equalization, a private party, or other public agency, for the administration and collection of the fees imposed pursuant to Article 9.1 (commencing with Section 25205.1) and deposited in the Hazardous Waste Control Account, shall not exceed the costs incurred by the State Board of Equalization, the private party, or other public agency, for the administration and collection of those fees.
(d)With respect to expenditures for the purposes of paragraphs (1) and (3) of subdivision (b) and paragraphs (1) and (2) of subdivision (b) of Section 25173.6, the department shall, at the time of the release of the annual Governor’s Budget, also make available the budgetary amounts and allocations of staff resources of the department proposed for the following activities:
(1)The department shall identify, by permit type, the projected allocations of budgets and staff resources for hazardous waste facilities permits, including standardized permits, closure plans, and postclosure permits.
(2)The department shall identify, with regard to surveillance and enforcement activities, the projected allocations of budgets and staff resources for the following types of regulated facilities and activities:
(A)Hazardous waste facilities operating under a permit or grant of interim status issued by the department, and generator activities conducted at those facilities. This information shall be reported by permit type.
(B)Transporters.
(C)Response to complaints.
(3)The department shall identify the projected allocations of budgets and staff resources for both of the following activities:
(A)The registration of hazardous waste transporters.
(B)The operation and maintenance of the hazardous waste manifest system.
(4)The department shall identify, with regard to site mitigation and corrective action, the projected allocations of budgets and staff resources for the oversight and implementation of the following activities:
(A)Investigations and removal and remedial actions at military bases.
(B)Voluntary investigations and removal and remedial actions.
(C)State match and operation and maintenance costs, by site, at joint state and federally funded National Priority List Sites.
(D)Investigation, removal and remedial actions, and operation and maintenance at the Stringfellow Hazardous Waste Site.
(E)Investigation, removal and remedial actions, and operation and maintenance at the Casmalia Hazardous Waste Site.
(F)Investigations and removal and remedial actions at nonmilitary, responsible party lead National Priority List Sites.
(G)Preremedial activities under the federal Comprehensive Environmental Response, Compensation, and Liability Act of 1980 (42 U.S.C. Sec. 9601 et seq.).
(H)Investigations, removal and remedial actions, and operation and maintenance at state-only orphan sites.
(I)Investigations and removal and remedial actions at nonmilitary, non-National Priority List responsible party lead sites.
(J)Investigations, removal and remedial actions, and operation and maintenance at Expedited Remedial Action Program sites pursuant to former Chapter 6.85 (commencing with Section 25396).
(K)Corrective actions at hazardous waste facilities.
(5)The department shall identify, with regard to the regulation of hazardous waste, the projected allocation of budgets and staff resources for the following activities:
(A)Determinations pertaining to the classification of hazardous wastes.
(B)Determinations for variances made pursuant to Section 25143.
(C)Other determinations and responses to public inquiries made by the department regarding the regulation of hazardous waste and hazardous substances.
(6)The department shall identify projected allocations of budgets and staff resources needed to do all of the following:
(A)Identify, remove, store, and dispose of, suspected hazardous substances or hazardous materials associated with the investigation of clandestine drug laboratories.
(B)Respond to emergencies pursuant to Section 25354.
(C)Create, support, maintain, and implement the railroad accident prevention and immediate deployment plan developed pursuant to Section 7718 of the Public Utilities Code.
(7)The department shall identify projected allocations of budgets and staff resources for the administration and implementation of the unified hazardous waste and hazardous materials regulatory program established pursuant to Chapter 6.11 (commencing with Section 25404).
(8)The department shall identify the total cumulative expenditures of the Regulatory Structure Update and Site Mitigation Update projects since their inception, and shall identify the total projected allocations of budgets and staff resources that are needed to continue these projects.
(9)The department shall identify the total projected allocations of budgets and staff resources that are necessary for all other activities proposed to be conducted by the department.
(e)Notwithstanding this chapter, or Part 22 (commencing with Section 43001) of Division 2 of the Revenue and Taxation Code, for any fees, surcharges, fines, penalties, and
funds that are required to be deposited into the Hazardous Waste Control Account or the Toxic Substances Control Account, the department, with the approval of the Secretary for Environmental Protection, may take any of the following actions:
(1)Assume responsibility for, or enter into a contract with a private party or with another public agency, other than the State Board of Equalization, for the collection of any fees, surcharges, fines, penalties and funds described in subdivision (a) or otherwise described in this chapter or Chapter 6.8 (commencing with Section 25300), for deposit into the Hazardous Waste Control Account or the Toxic Substances Control Account.
(2)Administer, or by mutual agreement, contract with a private party or another public agency, for the making of those determinations and the performance of functions that would otherwise be the responsibility of the State Board of Equalization pursuant to this chapter, Chapter 6.8 (commencing with Section 25300), or Part 22 (commencing with Section 43001) of Division 2 of the Revenue and Taxation Code, if those activities and functions for which the State Board of Equalization would otherwise be responsible become the responsibility of the department or, by mutual agreement, the contractor selected by the department.
(f)If, pursuant to subdivision (e), the department, or a private party or another public agency, pursuant to a contract with the department, performs the determinations and functions that would otherwise be the responsibility of the State Board of Equalization, the department shall be responsible for ensuring that persons who are
subject to the fees specified in subdivision (e) have equivalent rights to public notice and comment, and procedural and substantive rights of appeal, as afforded by the procedures of the State Board of Equalization pursuant to Part 22 (commencing with Section 43001) of Division 2 of the Revenue and Taxation Code. Final responsibility for the administrative adjustment of fee rates and the administrative appeal of any fees or penalty assessments made pursuant to this section may only be assigned by the department to a public agency.
(g)If, pursuant to subdivision (e), the department, or a private party or another public agency, pursuant to a contract with the department, performs the determinations and functions that would otherwise be the responsibility of the State Board of Equalization, the department shall have equivalent authority to make
collections and enforce judgments as provided to the State Board of Equalization pursuant to Part 22 (commencing with Section 43001) of Division 2 of the Revenue and Taxation Code. Unpaid amounts, including penalties and interest, shall be a perfected and enforceable state tax lien in accordance with Section 43413 of the Revenue and Taxation Code.
(h)The department, with the concurrence of the Secretary for Environmental Protection, shall determine which administrative functions should be retained by the State Board of Equalization, administered by the department, or assigned to another public agency or private party pursuant to subdivisions (e), (f), and (g).
(i)The department may adopt regulations to implement subdivisions (e) to (h), inclusive.
(j)The Director of Finance, upon request of the director, may make a loan from the General Fund to the Hazardous Waste Control Account to meet cash needs. The loan shall be subject to the repayment provisions of Section 16351 of the Government Code and the interest provisions of Section 16314 of the Government Code.
(k)The department shall establish, within the Hazardous Waste Control Account, a reserve of at least one million dollars ($1,000,000) each year to ensure that all programs funded by the Hazardous Waste Control Account will not be adversely affected by any revenue shortfalls.
(l)This section shall become operative on January 1, 2014.
(a)A person who disposes of hazardous waste in this state shall pay a fee for the disposal of hazardous waste to land, based on the type of waste placed in a disposal site, in accordance with this section and Section 25174.6.
(b)“Disposal fee” means the fee imposed by this section.
(c)For purposes of this section, “dispose” and “disposal” include “disposal,” as defined in Section 25113, including, but not limited to, “land treatment,” as defined in subdivision (n) of Section 25205.1.
(d)An operator of an authorized hazardous
waste facility, at which hazardous wastes are disposed, shall collect a fee from any person submitting hazardous waste for disposal and shall transmit the fees to the State Board of Equalization for the disposal of those wastes. The operator shall be considered the taxpayer for purposes of Section 43151 of the Revenue and Taxation Code. The facility operator is not required to collect and transmit the fee for a hazardous waste if the operator maintains written evidence that the hazardous waste is eligible for the exemption provided by Section 25174.7 or otherwise exempted from the fees pursuant to this chapter. The written evidence may be provided by the operator or by the person submitting the hazardous waste for disposal, and shall be maintained by the operator at the facility for a minimum of three years from the date that the waste is submitted for disposal. If the operator submits the
hazardous waste for disposal, the operator shall pay the same fee as would any other person.
(e)Notwithstanding subdivision (d), the disposal facility shall not be liable for the underpayment of any disposal fees for hazardous waste submitted for disposal by a person other than the operator, if the person submitting the hazardous waste to the disposal facility has done either of the following:
(1)Mischaracterized the hazardous waste.
(2)Misrepresented any exemptions pursuant to Section 25174.7 or any other exemption from the disposal fee provided pursuant to this chapter.
(f)(1)Any additional payment of disposal fees that are due to the
State Board of Equalization as a result of a mischaracterization of a hazardous waste, a misrepresentation of an exemption, or any other error, shall be the responsibility of the person making the mischaracterization, misrepresentation, or error.
(2)In the event of a dispute regarding the responsibility for a mischaracterization, misrepresentation, or other error, for which additional payment of disposal fees are due, the State Board of Equalization shall assign responsibility for payment of the fee to that person, or those persons, it determines responsible for the mischaracterization, misrepresentation, or other error, provided that the person, or persons, has the right to a public hearing and comment, and the procedural and substantive rights of appeal pursuant to Part 22 (commencing with Section 43001) of Division 2 of the Revenue and Taxation Code.
(3)Any generator, transporter, or owner or operator of a disposal facility shall report to the department and the State Board of Equalization any information regarding the mischaracterization, misrepresentation, or error, which could affect the disposal fee, within 30 days of that information first becoming known to that person.
(g)The State Board of Equalization shall deposit the fees collected pursuant to this section in the Hazardous Waste Control Account, for expenditure by the department, upon appropriation by the Legislature.
(h)The operator of the facility that disposes of the hazardous waste to land shall provide to every person who submits hazardous waste for disposal at the facility a
statement showing the amount of hazardous waste fees payable pursuant to this section.
(i)Any person who disposes of hazardous waste at any site that is not an authorized hazardous waste facility shall be responsible for payment of fees pursuant to this section and shall be the taxpayer for purposes of Section 43151 of the Revenue and Taxation Code.
(j)This section applies only to fees due for the 2013 and earlier reporting periods.
(k)This section shall remain in effect only until January 1, 2014, and as of that date is repealed, unless a later enacted statute, that is enacted before January 1, 2014, deletes or extends that date.
(a)The base rate for the hazardous wastes specified in Section 25174.6 that are disposed of or submitted for disposal in the state is eighty-five dollars and twenty-four cents ($85.24) per ton for disposal of hazardous waste to land.
(b)The base rate specified in subdivision (a) is the base rate for the period of January 1, 1997, to December 31, 1997. Beginning with calendar year 1998, and for each year thereafter, the State Board of Equalization shall adjust the base rate annually to reflect increases or decreases in the cost of living during the prior fiscal year, as measured by the Consumer Price Index issued by the Department of Industrial
Relations or a successor agency.
(c)This section applies only to fees due for the 2013 and earlier reporting periods.
(d)This section shall remain in effect only until January 1, 2014, and as of that date is repealed, unless a later enacted statute, that is enacted before January 1, 2014, deletes or extends that date.
(a)The fee provided pursuant to Section 25174.1 shall be determined as a percentage of the base rate, as adjusted by the State Board of Equalization, pursuant to Section 25174.2, or as otherwise provided by this section. The procedure for determining these fees is as follows:
(1)The following fees shall be paid for each ton, or fraction of a ton for up to the first 5,000 tons of the following hazardous wastes disposed of, or submitted for disposal, in the state at each specific offsite facility by each producer, or at each specific onsite facility, per month, if the hazardous wastes are not otherwise subject to the fee specified in paragraph (3) or (4) and are not otherwise exempt from the fees imposed pursuant to this article:
(A)For non-RCRA hazardous waste, excluding asbestos, generated in a remedial action, a removal action, or a corrective action taken pursuant to this chapter, Chapter 6.7 (commencing with Section 25280), Chapter 6.75 (commencing with Section 25299.10), or Chapter 6.8 (commencing with Section 25300), or generated in any other required or voluntary cleanup, removal, or remediation of a hazardous substance or non-RCRA hazardous waste, a fee of five dollars and seventy-two cents ($5.72) per ton.
(B)For all other non-RCRA hazardous waste, a fee of 16.31 percent of the base rate for each ton.
(2)Thirteen percent of the base rate for each ton, or fraction of a ton, shall be paid for up to the first 5,000 tons of hazardous waste disposed of, or submitted for disposal, in the state, at each specific offsite facility by each producer, or at each specific onsite facility, per month, which result from the extraction, beneficiation, and processing of ores and minerals, including phosphate rock and the overburden from the mining of uranium ore and that is not otherwise subject to the fee specified in paragraph (3) or (4).
(3)Two hundred percent of the base rate shall be paid for each ton, or fraction of a ton, of extremely hazardous waste disposed of, or submitted for disposal, in the state.
(4)Two hundred percent of the base rate shall be paid for each ton, or fraction of a ton, of restricted hazardous wastes listed in subdivision (b) of Section 25122.7 disposed of, or submitted for disposal, in the state.
(5)Forty and four-tenths percent of the base rate shall be paid for each ton, or fraction thereof, of hazardous waste disposed of, or submitted for disposal, in the state that is not otherwise subject to the fees specified in paragraph (1), (2), (3), (4), or (6).
(6)Five percent of the base rate shall be paid for each ton, or fraction of a ton, of hazardous waste disposed of, or submitted for disposal, in the state that is a solid hazardous waste residue resulting from incineration or dechlorination. Fees shall not be imposed pursuant to this paragraph on a solid hazardous waste residue resulting from incineration or dechlorination that is disposed of, or submitted for disposal, outside of the state.
(7)Fifty percent of the fee that would otherwise be paid for each ton, or fraction of a ton, of hazardous waste disposed of in the state that is a solid hazardous waste residue resulting from treatment of a treatable waste by means of a designated treatment technology, as defined in Section 25179.2. Fees shall not be imposed pursuant to this paragraph on a solid hazardous waste residue resulting from treatment of a treatable waste by means of a designated treatment technology that is not a hazardous waste or that is disposed of, or submitted for disposal, outside of the state.
(b)The amount of fees payable to the State Board of Equalization pursuant to this section shall be calculated using the total wet weight, measured in tons or fractions of a ton, of the hazardous waste in the form in which the hazardous waste existed at the time of disposal, submission for disposal, or application to land using a land disposal method, as defined in Section 66260.10 of Title 22 of the California Code of Regulations, if all of the following apply:
(1)The weight of any nonhazardous reagents or treatment additives added to the waste, after it has been submitted for disposal, for purposes of rendering the waste less hazardous, shall not be included in those calculations.
(2)Except as provided by paragraph (7) of subdivision (a), any RCRA hazardous waste received, treated, and disposed at the disposal facility shall be subject to a disposal fee pursuant to this section as if it were a non-RCRA hazardous waste, if the waste, due to treatment, is no longer a RCRA hazardous waste at the time of disposal.
(c)All fees imposed by this section shall be paid in accordance with Part 22 (commencing with Section 43001) of Division 2 of the Revenue and Taxation Code.
(d)This section applies only to fees due for the 2013 and earlier reporting periods.
(e)This section shall remain in effect only until January 1, 2014, and as of that date is repealed, unless a later enacted statute, that is enacted before January 1, 2014, deletes or extends that date.
(a)The fees provided for in Sections 25174.1 and 25205.5 do not apply to any of the following:
(1)Hazardous wastes that result when a government agency, or its contractor, removes or remedies a release of hazardous waste in the state caused by another person.
(2)Hazardous wastes generated or disposed of by a public agency operating a household hazardous waste collection facility in the state pursuant to Article 10.8 (commencing with Section 25218), including, but not limited to, hazardous waste received from conditionally exempt small quantity commercial generators, authorized pursuant to Section 25218.3.
(3)Hazardous wastes generated or disposed of by local vector control agencies that have entered into a cooperative agreement pursuant to Section 116180 or by county agricultural commissioners, if the hazardous wastes result from their control or regulatory activities and if they comply with the requirements of this chapter and regulations adopted pursuant this chapter.
(4)Hazardous waste disposed of, or submitted for disposal or treatment, by any person, which is discovered and separated from solid waste as part of a load checking program.
(b)Notwithstanding paragraph (1) of subdivision (a), any person responsible for a release of hazardous waste, that has been removed or remedied by a
government agency, or its contractor, shall pay the fee pursuant to Section 25174.1.
(c)Any person who acquires land for the sole purpose of owner-occupied single-family residential use, and who acquires that land without actual or constructive notice or knowledge that there is a tank containing hazardous waste on or under that property, is exempt from the fees imposed pursuant to Sections 25174.1 and 25205.5, in connection with the removal of the tank.
(d)This section applies only to fees due for the 2013 and earlier reporting periods.
(e)This section shall remain in effect only until January 1, 2014, and as of that date is repealed, unless a later enacted statute, that is enacted before January
1, 2014, deletes or extends that date.
(a)(1)The department shall prepare and adopt, by regulation, a list, and on or before January 1, 2002, and when appropriate thereafter, shall revise, by regulation, that list, of specified hazardous wastes that the department finds are economically and technologically feasible to recycle either onsite or at an offsite commercial hazardous waste recycling facility in the state, taking into consideration various factors that shall include, but are not limited to, the quantities of, concentrations of, and potential contaminants in, these hazardous wastes, the number and location of recycling facilities, and the proximity of these facilities to hazardous waste generators.
(2)Whenever any hazardous waste on the list adopted or revised pursuant to paragraph (1) is transported offsite for disposal, the department may request, in writing, by certified mail with return receipt requested, and the generator of that waste shall supply the department with, a formal, complete, and detailed statement justifying why the waste was not recycled. The generator shall supply the statement in writing, by certified mail with return receipt requested, within 30 calendar days of receipt of the department’s request. This statement shall include the generator’s assessment of the economic and technological feasibility of recycling the wastes and may include, but need not to be limited to, the generator’s good faith determination that sending the hazardous waste to any recycling facility where it is feasible to recycle that hazardous waste would constitute an unacceptable environmental or business risk. This determination by the generator shall be based upon an environmental audit or other reasonably diligent investigation of the environmental and other relevant business practices of the recycling facility or facilities where it would otherwise be feasible to recycle the waste. If the request is made of any entity listed in Section 25118 other than an individual, the statement shall be issued by the responsible management of that entity. The department shall keep confidential any trade secrets contained in that statement.
(3)On or before January 1, 2002, the department shall establish a procedure for the department to independently verify whether any hazardous waste identified in the list adopted pursuant to paragraph (1) is disposed of, rather than recycled. The department shall, on or before January 1, 2002, prepare and adopt those regulations that the department finds necessary to ensure that it can fully perform its duties pursuant to subdivisions (k) and (l) of Section 25170 to encourage the exchange of hazardous waste and to establish and maintain an information clearinghouse of hazardous wastes that may be recyclable.
(4)On or before July 1, 2000, the department shall establish an advisory committee to advise the department on the development of the regulations required or authorized by this section and on the department’s implementation of this section. The advisory committee shall consist of representatives of generators, hazardous waste facility operators, environmental organizations, the Legislature, and other interested parties.
(5)In determining to which generators the department will send the request specified in paragraph (2), the department shall give priority to notifying generators transporting offsite for disposal more than 1000 pounds per year of the type of hazardous waste that would be the subject of the request, to the extent this prioritization is feasible within the information management capabilities of the department.
(b)(1)If, after the department receives a statement from a generator pursuant to paragraph (2) of subdivision (a), the department finds the recycling of a hazardous waste to be economically and technologically feasible, the department shall inform the generator, in writing, by certified mail, return receipt requested, that 30 days after the date the generator receives notice of the department’s
finding, any of the generators’ hazardous waste transported offsite to which the department’s finding applies shall, after that date, be recycled. The department may establish procedures for rescinding or modifying any finding made by the department pursuant to this paragraph if there is a pertinent change in circumstances related to that finding.
(2)Notwithstanding paragraph (1), the department shall not find the recycling of a hazardous waste to be economically and technologically feasible if a generator includes a good faith determination in the statement submitted pursuant to paragraph (2) of subdivision (a) that sending its hazardous waste to any recycling facility where it is otherwise feasible to recycle the hazardous waste constitutes an unacceptable environmental or business risk.
(c)A generator who does not recycle a hazardous waste after the generator receives a notice of the departments’ findings pursuant to subdivision (b) that the hazardous waste is economically and technologically feasible to recycle is subject to five times the disposal fee that would otherwise apply to the disposal of that hazardous waste pursuant to Section 25174.1.
(d)For purposes of this section, “recycle” and “recycling” shall have the same meaning as set forth in subdivision (a) of Section 25121.1.
(e)This section applies only to fees due for the 2013 and earlier reporting periods.
(f)This section shall remain in effect only until January 1, 2014, and as of that date is repealed, unless a
later enacted statute, that is enacted before January 1, 2014, deletes or extends that date.
(a)(1)The department shall prepare and adopt, by regulation, a list, and when appropriate, shall revise, by regulation, that list, of specified hazardous wastes that the department finds are economically and technologically feasible to recycle either onsite or at an offsite commercial hazardous waste recycling facility in the state, taking into consideration various factors that shall include, but are not limited to, the quantities of, concentrations of, and potential contaminants in, these hazardous wastes, the number and location of recycling facilities, and the proximity of these facilities to hazardous waste generators.
(2)Whenever any hazardous waste on the list adopted or revised pursuant to paragraph (1) is transported offsite for disposal, the department may request, in writing, by certified mail with return receipt requested, and the generator of that waste shall supply the department with a formal, complete, and detailed statement justifying why the waste was not recycled. The generator shall supply the statement in writing, by certified mail with return receipt requested, within 30 calendar days of receipt of the department’s request. This statement shall include the generator’s assessment of the economic and technological feasibility of recycling the wastes and may include, but need not to be limited to, the generator’s good faith determination that sending the hazardous waste to any recycling facility where it is feasible to recycle that hazardous waste would constitute an unacceptable environmental or business risk. This determination by the generator shall be based upon an environmental audit or other reasonably diligent investigation of the environmental and other relevant business practices of the recycling facility or facilities where it would otherwise be feasible to recycle the waste. If the request is made of any entity listed in Section 25118 other than an individual, the statement shall be issued by the responsible management of that entity. The department shall keep confidential any trade secrets contained in that statement.
(3)The department shall establish a procedure for the department to independently verify whether any hazardous waste identified in the list adopted pursuant to paragraph (1) is disposed of, rather than recycled. The department shall prepare and adopt those regulations that the department finds necessary to ensure that it can fully perform its duties pursuant to subdivisions (k) and (l) of Section 25170 to encourage the exchange of hazardous waste and to establish and maintain an information clearinghouse of hazardous wastes that may be recyclable.
(4)The department shall establish an advisory committee to advise the department on the development of the regulations required or authorized by this section and on the department’s implementation of this section. The advisory committee shall consist of representatives of generators, hazardous waste facility operators, environmental organizations, the Legislature, and other interested parties.
(5)In determining to which generators the department will send the request specified in paragraph (2), the department shall give priority to notifying generators transporting offsite for disposal more than 1000 pounds per year of the type of hazardous waste that would be the subject of the request, to the extent this prioritization is feasible within the information management capabilities of the department.
(b)(1)If, after the department receives a statement from a generator pursuant to paragraph (2) of subdivision (a), the department finds the recycling of a hazardous waste to be economically and technologically feasible, the department shall inform the generator, in writing, by certified mail, return receipt requested, that 30 days after the date the generator receives notice of the department’s finding, any of the generators’ hazardous waste transported offsite to which the department’s finding applies shall, after that date, be recycled. The department
may establish procedures for rescinding or modifying any finding made by the department pursuant to this paragraph if there is a pertinent change in circumstances related to that finding.
(2)Notwithstanding paragraph (1), the department shall not find the recycling of a hazardous waste to be economically and technologically feasible if a generator includes a good faith determination in the statement submitted pursuant to paragraph (2) of subdivision (a) that sending its hazardous waste to any recycling facility where it is otherwise feasible to recycle the hazardous waste constitutes an unacceptable environmental or business risk.
(c)A generator who does not recycle a hazardous waste after the generator receives a notice of the departments’ findings pursuant to
subdivision (b) that the hazardous waste is economically and technologically feasible to recycle is subject to five times the generation and handling fee that would otherwise apply to of that hazardous waste pursuant to Section 25205.5.
(d)For purposes of this section, “recycle” and “recycling” shall have the same meaning as set forth in subdivision (a) of Section 25121.1.
(e)This section shall become operative on January 1, 2014, and shall apply to the fees due for the 2014 reporting period and thereafter, including the prepayments due following the reporting period and the final reconciliation fee due and payable following the reporting period.
(a)The State Board of Equalization shall provide quarterly reports to the Legislature on the fees collected pursuant to Sections 25205.2 and 25205.5. The reports shall be due on the 15th day of the second month following each quarter.
(b)The report submitted pursuant to this subdivision shall be submitted in compliance with Section 9795 of the Government Code.
(a)For purposes of this section, the term “permit” means a hazardous waste facilities permit, interim status authorization, or standardized permit.
(b)The department shall suspend the permit of any facility for nonpayment of any facility fee assessed pursuant to Section 25205.2 or activity fee assessed pursuant to Section 25205.7, if the operator of the facility is subject to the fee, and if the department or the State Board of Equalization has certified in writing to all of the following:
(1)The facility’s operator is delinquent in the payment of the fee for one or more reporting periods.
(2)The department or the State Board of Equalization has notified the facility’s operator of the delinquency.
(3)For a facility operator that exercised the option to pay the flat activity fee rate under subdivision (d) of Section 25205.7 as that section read on January 1, 2013, the operator has exhausted his or her administrative rights of appeal provided by Chapter 3 (commencing with Section 43151) of Part 22 of Division 2 of the Revenue and Taxation Code, and the State Board of Equalization has determined that the operator is liable for the fee, or that the operator has failed to assert those rights.
(c)(1)The department shall suspend the permit of any facility for nonpayment of a penalty assessed upon the owner or operator for failure to comply with this chapter or the regulations adopted pursuant to this chapter, if the penalty has been imposed by a trial court judge or by an administrative hearing officer if the person has agreed to pay the penalty pursuant to a written
agreement resolving a lawsuit or an administrative order or if the penalty has become final due to the person’s failure to respond to the lawsuit or order.
(2)The department may suspend a permit pursuant to this subdivision only if the owner or operator is delinquent in the payment of the penalty and the department has notified the owner or operator of the delinquency pursuant to subdivision (d).
(d)Before suspending a permit pursuant to this section, the department shall notify the owner or operator of its intent to do so, and shall allow the owner or operator a minimum of 30 days in which to cure the delinquency.
(e)The department may deny a new permit or refuse to renew a permit on the same grounds
for which the department is required to suspend a permit under this section, subject to the same requirements and conditions.
(f)(1)The department shall reinstate a permit that is suspended pursuant to this section upon payment of the amount due if the permit has not otherwise been revoked or suspended pursuant to any other provision of this chapter or regulation. Until the department reinstates a permit suspended pursuant to this section, if the facility stores, treats, disposes of, or recycles hazardous wastes, the facility shall be in violation of this chapter. If the operator of the facility subsequently pays the amount due, the period of time for which the operator shall have been in violation of this chapter shall be from the date of the activity that is in violation until the day after the owner or operator
submits the payment to the department.
(2)Except as otherwise provided in this section, the department is not required to take any other statutory or regulatory procedures governing the suspension of the permit before suspending a permit in compliance with the procedures of this section.
(g)(1)A suspension under this section shall be stayed while an authorized appeal of the fee or penalty is pending before a court or an administrative agency.
(2)For purposes of this subdivision, “an authorized appeal” means any appeal allowed pursuant to an applicable regulation or statute.
(h)The department may suspend a permit under this section based
on a failure to pay the required fee or penalty that commenced prior to January 1, 2002, if the failure to pay has been ongoing for at least 30 days following that date.
(i)Notwithstanding Section 43651 of the Revenue and Taxation Code, the suspension of a permit pursuant to this section, the reason for the suspension, and any documentation supporting the suspension, shall be a matter of public record.
(j)(1)This section does not authorize the department to suspend a permit held by a government agency if the agency does not dispute the payment but nonetheless is unable to process the payment in a timely manner.
(2)This section does not apply to a site owned or operated by a federal agency if the department has entered into an agreement with that federal agency regarding the remediation of that site.
(k)This section does not limit or supersede Section 25186.
(a)Except as provided in subdivisions (c) and (h), in addition to the fees specified in Section 25174.1, each operator of a facility shall pay a facility fee for each reporting period, or any portion thereof, to the board based on the size and type of the facility, as specified in Section 25205.4. On or before January 31 of each calendar year, the department annually shall notify the board of all known facility operators by facility type and size. The department shall also notify the board of any operator who is issued a permit or grant of interim status within 30 days from the date that a permit or grant of interim status is issued to the operator. The fee specified in this section does not apply to
facilities exempted pursuant to Section 25205.12.
(b)The board shall deposit all fees collected pursuant to subdivision (a) in the Hazardous Waste Control Account in the General Fund. The fees so deposited may be expended by the department, upon appropriation by the Legislature, for the purposes specified in subdivision (b) of Section 25174.
(c)Notwithstanding subdivision (a), a person who is issued a variance by the department from the requirement of obtaining a hazardous waste facilities permit or grant of interim status is not subject to the fee, for any reporting period following the reporting period in which the variance was granted by the department.
(d)Operators subject to facility fee liability pursuant to this section
shall pay the following amounts:
(1)The operator shall pay the applicable facility fee for each reporting period in which the facility actually engaged in the treatment, storage, or disposal of hazardous waste.
(2)The operator shall pay the applicable facility fee for one additional reporting period immediately following the final reporting period in which the facility actually engaged in that treatment or storage. For the 1994 reporting period and thereafter, the facility’s size for that additional reporting period shall be deemed to be the largest size at which the facility has ever been subject to the fee. If the department previously approved a unit or portion of the facility for a variance, closure, or permit-by-rule, the facility’s size for that reporting period shall be deemed to be its largest size since the department granted the approval.
(3)The operator of a disposal facility shall pay twice the applicable facility fee for one additional reporting period immediately following the final reporting period in which the facility actually engaged in disposal of hazardous waste.
(4)For the 1994 reporting period and thereafter, a facility shall not be deemed to have stopped treating, storing, or disposing of hazardous waste unless it has actually ceased that activity and has notified the department of its intent to close.
(5)If the reporting period which immediately followed the final reporting period in which a facility actually engaged in the treatment, storage, or disposal of the hazardous waste was the six-month period from July 1, 1991, through December 31, 1991, the operator shall be subject to twice the fee otherwise applicable to that operator for that reporting period under paragraphs (2) and (3).
(e)No facility shall be subject to a facility fee for treatment, storage, or disposal, if that activity ceased before July 1, 1986, and if the fee for the activity was not paid prior to January 1, 1994.
(f)Notwithstanding any other provision of this section, a person who ceased actual treatment, storage, or disposal of hazardous waste, whether generated onsite or received from offsite, before July 1, 1986, and who paid facility fees for any reporting period after that date pursuant to a decision of the State Board of Equalization, and who filed a claim for refund
of those fees on or before January 1, 1994, shall be entitled to a refund of those amounts.
(g)Facility operators who treated, stored, or disposed of hazardous waste on or after July 1, 1986, shall be subject to the provisions of this section which were in effect prior to January 1, 1994, as to payments which their operators made prior to January 1, 1994. The operators shall be subject to subdivision (d) as to any other liability for the facility fee.
(h)A treatment facility is not subject to the facility fee established pursuant to this section, if the facility engages in treatment exclusively to accomplish a removal or remedial action or a corrective action in accordance with an order issued by the Environmental Protection Agency pursuant to the federal act or in
accordance with an order issued by the department pursuant to Section 25187, if the facility was put in operation solely for purposes of complying with that order. The department shall instead assess a fee for that facility for the actual time spent by the department for the inspection and oversight of that facility. The department shall base the fee on the department’s work standards and shall assess the fee on an hourly basis.
(i)Notwithstanding subdivision (a), a facility operating pursuant to a standardized permit or grant of interim status, as specified in Section 25201.6, shall receive a credit for the annual facility fee imposed by this section for a period of time equal to the number of years that the facility lawfully operated prior to September 21, 1993, pursuant to a hazardous waste facilities permit or other grant of authorization
and paid facility fees for the operation of the facility pursuant to this section.
(j)This section applies only to fees due for the 2013 and earlier reporting periods, including the prepayments due during each reporting period and the final reconciliation fee due and payable by February 28 of the year following each reporting period.
(k)This section shall remain in effect only until January 1, 2014, and as of that date is repealed, unless a later enacted statute, that is enacted before January 1, 2014, deletes or extends that date.
(a)Except as provided in subdivisions (c) and (e), each operator of a facility shall pay a facility fee for each reporting period, or any portion of the reporting period, to the board based on the size and type of the facility, as specified in Section 25205.4. On or before January 31 of each calendar year, the department annually shall notify the board of all known facility operators by facility type and size. The department shall also notify the board of any operator who is issued a permit or grant of interim status within 30 days from the date that a permit or grant of interim status is issued to the operator. The fee specified in this section does not apply to facilities exempted pursuant to Section 25205.12.
(b)The board shall deposit all fees collected pursuant to subdivision (a) in the Hazardous Waste Control Account in the General Fund. The fees so deposited may be expended by the department, upon appropriation by the Legislature, for the purposes specified in subdivision (b) of Section 25174.
(c)Notwithstanding subdivision (a), a person who is issued a variance by the department from the requirement of obtaining a hazardous waste facilities permit or grant of interim status is not subject to the fee for any reporting period following the reporting period in which the variance was granted by the department.
(d)Operators subject to facility fee liability pursuant to this section shall pay the following amounts:
(1)The operator shall pay the applicable facility fee for each reporting period in which the facility actually engaged in the treatment, storage, or disposal of hazardous waste.
(2)The operator shall pay the applicable facility fee for one additional reporting period immediately following the final reporting period in which the facility actually engaged in that treatment or storage. The facility’s size for the additional reporting period shall be deemed to be the largest size at which the facility has ever been subject to the fee. If the department previously approved a unit or portion of the facility for a variance, closure, or permit-by-rule, the facility’s size for that reporting period shall be deemed to be its largest size since the department granted the approval.
(3)The operator of a disposal facility shall pay twice the applicable facility fee for one additional reporting period immediately following the final reporting period in which the facility actually engaged in disposal of hazardous waste.
(4)A facility shall not be deemed to have stopped treating, storing, or disposing of hazardous waste unless it has actually ceased that activity and has notified the department of its intent to close.
(e)A treatment facility is not subject to the facility fee established pursuant to this section if the facility engages in treatment exclusively to accomplish a removal or remedial action or a corrective action in accordance with an order issued by the United States Environmental Protection Agency pursuant to the federal act or in accordance with an order issued by the department pursuant to Section 25187, or if the removal or remedial action is carried out pursuant to
a removal action work plan or a remedial action plan prepared pursuant to Section 25356.1 and that treatment facility is authorized to operate pursuant to Section 25358.9, if the facility was put in operation
solely for purposes of complying with that order. The department shall instead assess a fee for that facility for the actual time spent by the department for the inspection and oversight of that facility. The department shall base the fee on the department’s work standards and shall assess the fee on an hourly basis.
(f)This section shall become operative on January 1, 2014 and shall apply to the annual facility fees due for the 2014 reporting period and thereafter, including the prepayments due during the reporting period and the final reconciliation fee due and payable by February 28 of the year following the reporting period.
The following facilities are exempt from the fees imposed by this article:
(a)Any household hazardous waste collection facility operated pursuant to Article 10.8 (commencing with Section 25218).
(b)Any facility operated by a local government agency, or by any person operating a hazardous waste collection program under an agreement with a public agency, which is used for wastes which meet the requirements of paragraph (3) of subdivision (a) of Section 25174.7.
(c)That portion of a solid waste facility permitted pursuant to Chapter 3
(commencing with Section 44001) of Part 4 of Division 30 of the Public Resources Code, which is used for the segregation, handling, and storage of hazardous waste separated from solid waste loads received by the facility, pursuant to a load checking program.
(d)A facility used solely for the treatment, storage, disposal, or recycling of hazardous waste which results when a public agency or its contractor investigates, removes, or remedies a release of hazardous waste caused by another person.
(e)(1)For purposes of fees assessed in any reporting period beginning July 1, 1990, or subsequently, a facility which has been issued a permit for the purpose of storing hazardous waste onsite, and whose permit has expired, if all of the following has occurred:
(A)The facility has received no waste from offsite since the permit expired.
(B)The owner or operator gave the department timely notification of intent to close the facility, pursuant to regulations adopted by the department.
(C)At least 90 days have elapsed since the owner or operator gave the department that notification.
(D)The department did not complete its review of the closure plan within 90 days of receiving the notification.
(2)This exclusion shall take effect the reporting period following the reporting period in which the facility first satisfied the requirements of paragraph (1) and did not accumulate waste onsite for more than 90 consecutive days.
(f)This section applies only to fees due for the 2013 and earlier reporting periods.
(g)This section shall remain in effect only until January 1, 2014, and as of that date is repealed, unless a later enacted statute, that is enacted before January 1, 2014, deletes or extends that date.
The following facilities are exempt from the fees imposed by this article:
(a)Any household hazardous waste collection facility operated pursuant to Article 10.8 (commencing with Section 25218).
(b)Any facility operated by a local government agency or by any person operating a hazardous waste collection program under an agreement with a public agency that is used for wastes that meet the requirements of paragraph (3) of subdivision (a) of Section 25205.5.2.
(c)That portion of a solid waste facility permitted pursuant to Chapter 3 (commencing with Section
44001) of Part 4 of Division 30 of the Public Resources Code, which is used for the segregation, handling, and storage of hazardous waste separated from solid waste loads received by the facility, pursuant to a load checking program.
(d)A facility used solely for the treatment, storage, disposal, or recycling of hazardous waste that results when a public agency or its contractor investigates, removes, or remedies a release of hazardous waste caused by another person.
(e)(1)A facility that has been issued a permit for the purpose of storing hazardous waste onsite and whose permit has expired, if all of the following has occurred:
(A)The facility has received no waste from offsite since the permit expired.
(B)The owner or operator gave the department timely notification of intent to close the facility, pursuant to regulations adopted by the department.
(C)At least 90 days have elapsed since the owner or operator gave the department that notification.
(D)The department did not complete its review of the closure plan within 90 days of receiving the notification.
(2)This exclusion shall take effect the reporting period following the reporting period in which the facility first satisfied the requirements of paragraph (1) and did not accumulate waste onsite for more than 90 consecutive days.
(f)This section shall become operative on January 1, 2014, and shall apply to the fees due for the 2014 reporting period and thereafter. This includes the prepayments due during the reporting period and the final reconciliation fee due and payable following the reporting period.
(a)The base rate for the 2013 reporting period for the fee imposed by Section 25205.2 is thirty thousand five dollars ($30,005). Commencing with the 2014 reporting period, and for each reporting period thereafter, the board shall adjust the base rate annually to reflect increases or decreases in the cost of living during the prior fiscal year, as measured by the Consumer Price Index issued by the Department of Industrial Relations or by a successor agency.
(b)The determination of the facility fee pursuant to this section, including the redetermination of the base rate, is exempt from Chapter 3.5 (commencing with Section 11340) of Part 1
of Division 3 of Title 2 of the Government Code.
(c)Except as provided in subdivision (e), in computing the facility fees pursuant to this section, all of the following shall apply:
(1)The fee to be paid by a ministorage facility shall equal 25 percent of the base facility rate.
(2)The fee to be paid by a small storage facility shall equal the base facility rate.
(3)The fee to be paid by a large storage facility shall equal twice the base facility rate.
(4)The fee to be paid by a minitreatment facility shall equal 50 percent of the base facility rate.
(5)The fee to be paid by a small treatment facility shall equal twice the base facility rate.
(6)The fee to be paid by a large onsite treatment facility shall equal three times the base facility rate.
(7)The fee to be paid by a large offsite treatment facility shall be three times the base facility rate.
(8)The fee to be paid by a disposal facility shall equal 10 times the base facility rate.
(9)(A)The fee to be paid by a facility with a postclosure permit shall be five thousand seven hundred twenty-five dollars ($5,725) annually for a small facility, eleven thousand four hundred fifty dollars ($11,450) annually for a medium facility, and seventeen thousand one hundred seventy-five dollars ($17,175) for a large facility during the first five years of the postclosure period. The fee to be paid by a facility with a postclosure permit during the remaining years of the postclosure care period shall be three thousand fifty dollars ($3,050) annually for a small facility, six thousand one hundred dollars ($6,100) annually for a medium facility, and ten thousand three hundred dollars ($10,300) annually for a large facility.
(B)The fees required by subparagraph (A) shall be reduced by 50 percent for any facility for which an agency, other than the department, is the lead agency pursuant to paragraph (1) of subdivision (b) of Section 25204.6.
(d)If a facility falls into more than one category listed in either subdivision (c) or (e), or any combination thereof, or multiple operations under a single hazardous waste facilities permit or grant of interim status fall into more than one category listed in subdivision (c) or (e), or any combination thereof, the facility operator shall pay only the rate for the facility category which is the highest rate.
(e)Notwithstanding subdivision (c), the facility fee for a facility that has been issued a standardized permit shall be as follows:
(1)The fee to be paid for a facility that has been issued a Series A standardized permit shall be eleven thousand seven hundred thirty dollars ($11,730).
(2)The fee to be paid for a facility that has been issued a Series B standardized permit shall be five thousand four hundred ninety-seven dollars ($5,497).
(3)Except as specified in paragraph (4), the fee to be paid for a facility that has been issued a Series C standardized permit shall be four thousand six hundred seventeen dollars ($4,617).
(4)The fee for a facility that has been issued a Series C standardized permit is two thousand three hundred eight dollars ($2,308) if the facility meets all of the following conditions:
(A)The facility treats not more than 1,500 gallons of liquid hazardous waste and not more than 3,000 pounds of solid hazardous waste in any calendar month.
(B)The total facility storage capacity does not exceed 15,000 gallons of liquid hazardous waste and 30,000 pounds of solid hazardous waste.
(C)If the facility both treats and stores hazardous waste, the facility does not exceed the volume limitations specified in subparagraphs (A) and (B) for each individual activity.
(f)The fee imposed pursuant to this section shall be paid in accordance with Part 22 (commencing with Section 43001) of Division 2 of the Revenue and Taxation Code.
(a)In addition to the fee imposed pursuant to Section 25174.1, every generator of hazardous waste, in the amounts specified in subdivision (c), shall pay the board a generator fee for each generator site for each calendar year, or portion thereof, unless the generator has paid a facility fee or received a credit, as specified in Section 25205.2, for each specific site, for the calendar year for which the generator fee is due.
(b)The base fee rate for the fee imposed pursuant to subdivision (a) is two thousand seven hundred forty-eight dollars ($2,748).
(c)(1)Each
generator who generates an amount equal to, or more than, five tons, but less than 25 tons, of hazardous waste during the prior calendar year shall pay 5 percent of the base rate.
(2)Each generator who generates an amount equal to, or more than, 25 tons, but less than 50 tons, of hazardous waste during the prior calendar year shall pay 40 percent of the base rate.
(3)Each generator who generates an amount equal to, or more than, 50 tons, but less than 250 tons, of hazardous waste during the prior calendar year shall pay the base rate.
(4)Each generator who generates an amount equal to, or more than, 250 tons, but less than 500 tons, of hazardous waste during the prior calendar year shall pay five times the base rate.
(5)Each generator who generates an amount equal to, or more than, 500 tons, but less than 1,000 tons, of hazardous waste during the prior calendar year shall pay 10 times the base rate.
(6)Each generator who generates an amount equal to, or more than, 1,000 tons, but less than 2,000 tons, of hazardous waste during the prior calendar year shall pay 15 times the base rate.
(7)Each generator who generates an amount equal to, or more than, 2,000 tons of hazardous waste during the prior calendar year shall pay 20 times the base rate.
(d)The base rate established pursuant to subdivision (b) was the base rate for the 1997 calendar year and the board shall adjust the
base rate annually to reflect increases or decreases in the cost of living, during the prior fiscal year, as measured by the Consumer Price Index issued by the Department of Industrial Relations or by a successor agency.
(e)The establishment of the annual operating fee pursuant to this section is exempt from Chapter 3.5 (commencing with Section 11340) of Part 1 of Division 3 of Title 2 of the Government Code.
(f)The following materials are not hazardous wastes for purposes of this section:
(1)Hazardous materials which are recycled, and used onsite, and are not transferred offsite.
(2)Aqueous waste treated in a treatment unit operating, or which subsequently operates, pursuant to a permit-by-rule, or pursuant to Section 25200.3 or 25201.5. However, hazardous waste generated by a treatment unit treating waste pursuant to a permit-by-rule, by a unit which subsequently obtains a permit-by-rule, or other authorization pursuant to Section 25200.3 or 25201.5 is hazardous waste for purposes of this section.
(g)The fee imposed pursuant to this section shall be paid in accordance with Part 22 (commencing with Section 43001) of Division 2 of the Revenue and Taxation Code.
(h)(1)A generator who pays a hazardous waste generator inspection fee to a certified unified program agency, which is imposed as part of a single fee system and fee accountability program that are both in compliance with the requirements of Section
25404.5, shall be eligible for a refund of all, or part of, the generator fee paid pursuant to subdivision (a) if both of the following conditions apply:
(A)The generator received a credit pursuant to Section 43152.7 or 43152.11 of the Revenue and Taxation Code for fees paid for hazardous waste generated in 1996.
(B)The department certifies, pursuant to subdivision (b) of Section 25205.9, that funds are available to pay all or part of the refund.
(2)A generator who is eligible for a refund pursuant to paragraph (1) shall submit an application for that refund to the board by September 30 following the fiscal year during which the generator paid the generator fee pursuant to subdivision (a). An application for a refund postmarked after September 30 is void, shall not be processed by the board, and shall be returned to the applicant.
(i)(1)A generator who transfers hazardous materials to an offsite facility for recycling at that offsite facility or another offsite facility shall be eligible for a refund of all, or part of, the generator fee paid pursuant to subdivision (a) if all of the following
conditions apply:
(A)The offsite facility to which the hazardous materials are manifested pays a facility fee pursuant to Section 25205.2.
(B)The amount of hazardous materials transferred to the offsite facility and recycled there, when deducted from the total tonnage of hazardous waste generated at the generator’s site, results in the generator becoming eligible for a generator fee that is lower than the fee paid pursuant to subdivision (a).
(C)The hazardous materials transferred to the offsite facility are not burned in a boiler, industrial furnace, or an incinerator, as those terms are defined in Section 260.10 of Title 40 of the Code of Federal Regulations, used in a manner constituting disposal, or used to produce products that are applied to land.
(D)The department certifies, pursuant to subdivision (b) of Section 25205.9, that funds are available to pay all or part of the refund.
(2)A generator who is eligible for a refund pursuant to paragraph (1) shall submit an application for that refund to the board by September 30 following the fiscal year during which the generator paid the generator fee pursuant to subdivision (a). An application for a refund postmarked after September 30 is void, shall not be processed by the board, and shall be returned to the applicant.
(j)(1)The amendment of this section made by Chapter 1125 of the Statutes of 1991 does not constitute a change in, but is declaratory
of, existing law.
(2)The amendment of subdivision (a) of this section made by Chapter 259 of the Statutes of 1996 does not constitute a change in, but is declaratory of, existing law.
(k)This section applies only to fees due for the 2013 and earlier reporting periods, including the prepayments due during each reporting period and the final reconciliation fee due and payable by February 28 of the year following each reporting period.
(l)This section shall remain in effect only until January 1, 2014, and as of that date is repealed, unless a later enacted statute, that is enacted before January 1, 2014, deletes or extends that date.
(a)(1)Except as otherwise provided in this section, each generator, as defined in subdivision (e) of Section 25205.1, of hazardous waste that generates an amount equal to, or greater than, five tons of hazardous waste shall pay the board for each generator site for each calendar year, or portion of the calendar year, a generation and handling fee of thirty-one dollars and fifty-two cents ($31.52) per ton of hazardous waste generated.
(2)A generator that is issued a hazardous waste facilities permit from the department and that pays an annual facility fee, as specified in Section 25205.2, may deduct, from the amount of hazardous waste otherwise subject to this subdivision that is generated per calendar year, the amount of hazardous waste that is solely stored, bulked, or transferred through the location of the permitted hazardous waste facility and that is in route to another facility that is authorized to do any of the following:
(A)Manage the hazardous waste for reclamation and recovery, including fuel blending prior to energy recovery at another site.
(B)Manage the hazardous waste through destruction methods or treatment prior to disposal at another site.
(C)Manage the hazardous waste by any form of treatment.
(D)Dispose of the hazardous waste.
(b)Generators of more than five tons of hazardous waste in the prior calendar year are subject to the prepayment due during each reporting period and the final reconciliation fee due and payable by February 28 of the year following each reporting period.
(c)Notwithstanding subdivision (a), a generator of used oil shall pay a generation and handling fee of twenty-seven dollars and eighty-six cents ($27.86) per ton of used oil generated.
(d)The base rates established pursuant to subdivisions (a) and (c) are the rates for the 2014 reporting period and the board shall adjust the base rates annually to reflect increases or decreases in the cost of living, during the prior fiscal year, as measured
by the Consumer Price Index issued by the Department of Industrial Relations or by a successor agency.
(e)The following materials are not hazardous wastes for purposes of this section:
(1)Hazardous materials that are recycled and used onsite, and that are not transferred offsite.
(2)Aqueous waste treated in a treatment unit operating, or which subsequently operates, pursuant to a permit-by-rule, or pursuant to Section 25200.3 or 25201.5. However, hazardous waste generated by a treatment unit treating waste pursuant to a permit-by-rule, by a unit that subsequently obtains a permit-by-rule, or by other authorization pursuant to Section 25200.3 or 25201.5 is hazardous waste for purposes of this section.
(f)The fee imposed pursuant to this section shall be paid in accordance with Part 22 (commencing with Section 43001) of Division 2 of the Revenue and Taxation Code.
(g)This section shall become operative on January 1, 2014, and shall apply to the annual generation and handling fees due for the 2014 reporting period and thereafter. This includes the prepayments due during the reporting period and the final reconciliation fee due and payable by February 28 of the year following the reporting
period.
Notwithstanding Sections 25174.1 and 25205.5, the department may adopt regulations exempting victims of disasters from the hazardous waste disposal fee imposed pursuant to Section 25174.1 and the generator fee imposed pursuant to Section 25205.5. The regulations may allow that exemption if all of the following apply:
(a)The hazardous waste is generated in a geographical area identified in a state of emergency proclamation by the Governor pursuant to Section 8625 of the Government Code because of fire, flood, storm, earthquake, riot, or civil unrest.
(b)The hazardous waste is generated when property owned
or controlled by the victim is damaged or destroyed as a result of the
disaster.
(c)The hazardous waste is not hazardous waste that is routinely produced as part of a manufacturing or commercial business or that is managed by a hazardous waste facility or a facility operated by a generator of hazardous waste who files a hazardous waste notification statement with the department pursuant to subdivision (a) of Section 25158.
(d)The victim meets any other condition or limitation on eligibility specified by the department.
(e)This section shall remain in effect only until January 1, 2014, and as of that date is repealed, unless a later enacted statute, that is enacted before January 1, 2014, deletes or extends that date.
Notwithstanding Section 25205.5, the department may adopt regulations exempting victims of disasters from the generation and handling fee imposed pursuant to Section 25205.5. The regulations may allow that exemption if all of the following apply:
(a)The hazardous waste is generated in a geographical area identified in a state of emergency proclamation by the Governor pursuant to Section 8625 of the Government Code because of fire, flood, storm, earthquake, riot, or civil unrest.
(b)The hazardous waste is generated when property owned or controlled by the victim is damaged or destroyed as a result of the disaster.
(c)The hazardous waste is not hazardous waste that is routinely produced as part of a manufacturing or commercial business or that is managed by a hazardous waste facility or a facility operated by a generator of hazardous waste who files a hazardous waste notification statement with the department pursuant to subdivision (a) of Section 25158.
(d)The victim meets any other condition or limitation on eligibility specified by the department.
(e)This section shall become operative on January 1, 2014, and shall apply to the fees due for the 2014 reporting period and thereafter, including the prepayments due following the reporting period and the final reconciliation fee due and payable following the reporting
period.
(a)The fees provided for in Section 25205.5 do not apply to any of the following:
(1)Hazardous wastes that result when a government agency, or its contractor, removes or remedies a release of hazardous waste in the state caused by another person.
(2)Hazardous waste generated or disposed of by a public agency operating a household hazardous waste collection facility in the state pursuant to Article 10.8 (commencing with Section 25218), including, but not limited to, hazardous waste received from conditionally exempt small quantity commercial generators, authorized pursuant to Section 25218.3.
(3)Hazardous waste generated by a local vector control agency that has entered into a cooperative agreement pursuant to Section 116180 or by a county agricultural commissioner, if the hazardous wastes result from the agency’s or commissioner’s control or regulatory activities and if the agency or commissioner complies with the requirements of this chapter and regulations adopted pursuant to this chapter.
(4)Hazardous waste generated by any person, which is discovered and separated from solid waste as part of a load checking program.
(5)Hazardous waste used oil generated by a used oil collection center certified by the Department of Resources Recycling and Recovery pursuant to Section 48660 of the Public Resources Code for the collection of used oil from the public.
(b)Notwithstanding paragraph (1) of subdivision (a), any person responsible for a release of hazardous waste, which has been removed or remedied by a government agency, or its contractor, shall pay the fee pursuant to Section 25205.5.
(c)Any person who acquires land for the sole purpose of owner-occupied single-family residential use, and who acquires that land without actual or constructive notice or knowledge that there is a tank containing hazardous waste on or under that property, is exempt from the fees imposed pursuant to Section 25205.5 in connection with the removal of the tank.
(d)This section shall become operative on January 1, 2014, and shall apply to
the fees due for the 2014 reporting period and thereafter, including the prepayments due during the reporting period and the final reconciliation fee due and payable following the reporting period.
(a)(1)A person who applies for, or requests, any of the following shall enter into a written agreement with the department pursuant to which that person shall reimburse the department, pursuant to Article 9.2 (commencing with Section 25206.1), for the costs incurred by the department in processing the application or responding to the request, including the costs of reviewing and overseeing corrective action as set forth in subdivision (b):
(A)A new hazardous waste facilities permit, including a standardized permit.
(B)A hazardous waste facilities permit for postclosure.
(C)A renewal of an existing hazardous waste facilities permit, including a standardized permit or postclosure permit.
(D)A class 2 or class 3 modification of an existing hazardous waste facilities permit or grant of interim status, including a standardized permit or grant of interim status or a postclosure permit.
(E)A variance.
(F)A waste classification determination.
(2)Any agreement required pursuant to paragraph (1) shall provide for at least 25 percent of the reimbursement to be made in advance of the processing of the application or the response to the request.
(3)Any agreement entered into pursuant to this section shall, if applicable, include costs of reviewing and overseeing corrective action as set forth in subdivision (b).
(b)An applicant pursuant to paragraph (1) of subdivision (a) shall pay the department’s costs in reviewing and overseeing any corrective action program described in the application for a standardized permit pursuant to subparagraph (C) of paragraph (2) of subdivision (c) of Section 25201.6 or required pursuant to subdivision (b) of Section 25200.10, and in reviewing and overseeing any corrective action work undertaken at the facility pursuant to that corrective action program.
(c)(1)An applicant pursuant to paragraph (1) of
subdivision (a) shall, pursuant to Section 21089 of the Public Resources Code, pay all costs incurred by the department for purposes of complying with the California Environmental Quality Act (Division 13 (commencing with Section 21000) of the Public Resources Code) in conjunction with an application or request, including any activities associated with corrective action for any of the activities identified in subdivision (a).
(2)Paragraph (1) does not apply to projects that are exempt from the California Environmental Quality Act (Division 13 (commencing with Section 21000) of the Public Resources Code).
(d)Any reimbursements received pursuant to this section shall be placed in the Hazardous Waste Control Account for appropriation in accordance with Section 25174.
(e)Subdivision (a) does not apply to any variance granted pursuant to Article 4 (commencing with Section 66263.40) of Chapter 13 of Division 4.5 of Title 22 of the California Code of Regulations.
(f)Subdivision (a) does not apply to any of the following:
(1)Any variance issued to a public agency to transport wastes for purposes of operating a household hazardous waste collection facility, or to transport waste from a household hazardous waste collection facility, which receives household hazardous waste or hazardous waste from conditionally exempted small quantity generators pursuant to Article 10.8 (commencing with Section 25218).
(2)A permanent household hazardous waste collection facility.
(3)Any variance issued to a public agency to conduct a collection program for agricultural wastes.
(g)(1)This section applies to applications and requests submitted to the department on or after July 1, 2013, and applications and requests pending before the department as of July 1, 2013.
(2)For purposes of applying the provisions of this subdivision, the Legislature finds and declares all of the following:
(A)The department expends a substantial amount of time and resources in processing permit applications and modifications.
(B)The former flat fee option paid by applicants was most often insufficient to cover the actual costs to the department in reviewing and processing the applications and modifications.
(C)The applicant, being the primary beneficiary of the permit process, in fairness should pay the actual costs of the department in reviewing permit applications and modifications.
(D)The amendment to the act adding this subdivision in the 2013–14 Regular Session eliminating the flat fee option and revising provisions requiring applicants to enter into a written reimbursement agreement with the department is intended to apply both to future and pending applications and modification requests in order to remedy this inequity.
(3)For an application or request that is submitted to the department prior to July 1, 2013, which remains pending as of that date, the reimbursement agreement shall provide credit for any fee previously paid to the department, minus the value of services provided by the department prior to July 1, 2013, in conjunction with that application or request pursuant to this section as it read prior to January 1, 2013.
(4)Only time and resources expended by the department after July 1, 2013, on already pending permit applications and modification requests will be the subject of the written reimbursement agreement with the department.
(a)The owner of a hazardous waste facility authorized to operate pursuant to a permit-by-rule, authorized under a grant of conditional authorization pursuant to Section 25200.3, exempted pursuant to subdivision (a) or (c) of Section 25201.5, or exempted pursuant to Section 25144.6 or 25201.14 is exempt from the fee specified in Section 25205.2 for any activities authorized by the permit-by-rule, under a grant of conditional authorization pursuant to Section 25200.3, exempted pursuant to subdivision (a) or (c) of Section 25201.5, or exempted pursuant to Section 25144.6 or 25201.14 at that facility for any year or reporting period during which the facility is operating.
(b)The operator of a hazardous waste facility authorized by the department to clean and recycle excavated underground storage tanks is exempt from the facility fee specified in Section 25205.2 with regard to those activities conducted before January 1, 1994, and those activities conducted after that date, until the effective date of a regulation adopted by the department governing the statewide requirements for the issuance of a permit for tank cleaning and recycling facilities.
(a)Except as provided in Section 25404.5, the owner or operator of a facility or transportable treatment unit operating pursuant to a permit-by-rule shall pay a fee to the board per facility or transportable treatment unit for each reporting period, or portion of a reporting period. The fee for the 2013 reporting period shall be one thousand four hundred fifty-seven dollars ($1,457).
Thereafter, the fee shall be adjusted annually by the board to reflect increases and decreases in the cost of living, as measured by the Consumer Price Index issued by the Department of Industrial Relations or a successor agency. The reporting period shall begin January 1 of each calendar year. On or before January 31 of each calendar year, the department shall notify the board of all known owners or operators operating pursuant to a permit-by-rule who are not exempted from this fee pursuant to Section 25404.5. The department shall also notify the board of any owner or operator authorized to operate pursuant to a permit-by-rule, who is not exempted from this fee pursuant to Section 25404.5, within 60 days after the owner or operator is authorized.
(b)Except as provided in Section 25404.5, a generator operating under
a grant of conditional authorization pursuant to Section 25200.3 shall pay a fee to the board per facility for each reporting period, or portion thereof, unless the generator is subject to a fee under a permit-by-rule. The fee for the 2013 reporting period shall be one thousand four hundred fifty-seven dollars ($1,457). Thereafter, the fee shall be adjusted annually by the board to reflect increases and decreases in the cost of living, during the prior fiscal year, as measured by the Consumer Price Index issued by the Department of Industrial Relations or a successor agency. The reporting period shall begin January 1 of each calendar year. On or before January 31 of each calendar year, the department shall notify the board of all known generators operating pursuant to a grant of conditional authorization under Section 25200.3 who are not exempted from this fee pursuant to Section 25404.5. The
department shall also notify the board of any generator authorized to operate under a grant of conditional authorization, who is not exempted from this fee pursuant to Section 25404.5, within 60 days of the receipt of notification.
(c)Except as provided in Section 25404.5, a generator performing treatment conditionally exempted pursuant to Section 25144.6 or subdivision (a) or (c) of Section 25201.5 shall pay thirty-eight dollars ($38) to the board per facility for each reporting period, unless that generator is subject to a fee under a permit-by-rule or a conditional authorization pursuant to Section 25200.3. The reporting period shall begin January 1 of each calendar year. On or before January 31 of each calendar year, the department shall notify the board of all known facilities performing treatment conditionally exempted by Section
25144.6 or subdivision (a) or (c) of Section 25201.5 who are not exempted from this fee pursuant to Section 25404.5. The department shall also notify the board of any generator who notifies the department that the generator is conducting a conditionally exempt treatment operation, and who is not exempted from this fee pursuant to Section 25404.5, within 60 days of the receipt of the notification.
(d)The fees imposed pursuant to this section shall be paid in accordance with Part 22 (commencing with Section 43001) of Division 2 of the Revenue and Taxation Code.
(a)Except for the first four manifests used in a calendar year by a business with less than 100 employees, and except as provided in paragraph (2), in addition to any fees to cover printing and distribution costs, the department shall impose a manifest fee of seven dollars and fifty cents ($7.50) for each California Hazardous Waste Manifest form or electronic equivalent used after June 30, 1998, by any person, in the following manner:
(1)The department shall bill generators for each California Uniform Hazardous Waste Manifest form, manifest number, or electronic equivalent used after June 30, 1998. The billing frequency specified by the department may range from monthly to annually, with the payment by the generator required within 30 days from the date of receipt of the billing, and shall be determined based on consultation with the regulated community. In preparing the bills, the department shall distinguish between manifests used solely for recycled hazardous wastes and those used for nonrecycled hazardous wastes. In determining the billing frequency, the department may take into account each person’s volume of manifest usage.
(2)(A)The manifest fee shall not be collected on the use of California Hazardous Waste Recycling Manifests that are used solely for hazardous wastes that are recycled.
(B)The manifest fee for each California Uniform Hazardous Waste Manifest form used solely for hazardous waste derived from air compliance solvents, shall be three dollars and fifty cents ($3.50) This is in addition to any fees charged to cover printing and distribution costs.
(3)The department shall implement a system for the use of manifests that distinguishes among recycling manifests used solely for hazardous wastes that are to be recycled, manifests used solely to transport hazardous waste derived from air compliance solvents, and general manifests that may be used for transporting waste for any purpose.
(4)(A)If a person erroneously reports on a California Uniform Hazardous Waste Manifest that the manifest is being used for the transport of hazardous wastes that are being shipped for recycling or for the transport of hazardous wastes derived from air compliance solvents rather than the transport of other types of hazardous waste, the person shall pay the seven dollars and fifty cents ($7.50) manifest fee and an additional error correction fee of twenty dollars ($20) per manifest, as required pursuant to Section 25160.5.
(B)Notwithstanding subparagraph (A) the department shall provide the manifest user with a reasonable opportunity to notify the department of any incorrect use of the recycling manifest, as described in subparagraph (A), and to provide the department with the appropriate manifest fee payment without additional fines, penalties, or payment of the error correction fee.
(5)The department may adopt regulations to implement and administer the manifest fee system imposed pursuant to this subdivision.
(b)For purposes of subdivision (a), a California Uniform Hazardous Waste Manifest means either of the following:
(1)A manifest document printed and supplied by the state for a shipment initiated on and before September 4, 2006.
(2)The Uniform Hazardous Waste Manifest printed by a source registered with the United States Environmental Protection Agency for a shipment initiated on and after September 5, 2006, if the manifest originates from a generator located in California, is received by the designated facility located in California where the manifest is signed and terminated, or is imported or exported through a point of entry or exit in California.
(c)On and
after July 1, 1999, commencing with 1999–2000 fiscal year and annually thereafter, the department shall expend, upon appropriation by the Legislature in the annual Budget Act, not less than one million fifty thousand dollars ($1,050,000) from the manifest fees, deposited in the Hazardous Waste Control Account, to establish a program to encourage hazardous waste generators to implement pollution prevention measures. The program shall be administered pursuant to administrative and expenditure criteria to be established by the Legislature.
(d)The manifest fees shall be deposited in the Hazardous Waste Control Account and be available for expenditure, upon appropriation by the Legislature.
(e)For purposes of this section, “air compliance solvent” means a solvent, including aqueous
solutions, that are required or approved for use by regulations adopted by the State Air Resources Board, an air pollution control district, or an air quality management district, to meet air emission standards adopted by that board or district and, pursuant to those regulations, is required to be used instead of another solvent that was used and recycled prior to the adoption of those regulations.
(f)This section shall apply only to fees due for the 2013 and earlier reporting periods.
(g)This section shall remain in effect only until January 1, 2014, and as of that date is repealed, unless a later enacted statute, that is enacted before January 1, 2014, deletes or extends that date.
(a)(1)The department may impose an annual verification fee upon all generators, transporters, and facility operators with 50 or more employees that possess a valid identification number issued either by the department or by the Environmental Protection Agency. The fee charged shall be one hundred fifty dollars ($150) for each generator, transporter, and facility operator with 50 or more employees, but less than 75 employees; one hundred seventy-five dollars ($175) for each generator, transporter, and facility operator with 75 or more employees, but less than 100 employees; two hundred dollars ($200) for each generator, transporter, and facility operator with 100 or more employees,
but less than 250 employees; two hundred twenty-five dollars ($225) for each generator, transporter, and facility operator with 250 or more employees, but less than 500 employees; two hundred fifty dollars ($250) for each generator, transporter, and facility operator with 500 or more employees. However, no generator, transporter, or facility operator shall be assessed fees pursuant to this section that exceed, in total, five thousand dollars ($5,000).
(2)The generator, transporter, or facility operator subject to the fee shall submit payment of the fee within 30 days from the date of receiving a notice of assessment from the department. The notice shall be sent once during each fiscal year to each holder of a valid identification number. The fee imposed by this section shall be deposited in the Hazardous Waste Control Account and be available for expenditure, upon appropriation by the Legislature. For purposes of this section, “employee” shall have the same meaning set forth in Section 25205.6.
(b)The department shall establish an identification number certification system to biennially verify the accuracy of information related to generators, transporters, and facilities authorized to treat, store, or dispose of hazardous waste. However, if the number of identification numbers issued since the previous certification exceeds 20 percent of the active identification numbers, the department may implement an annual certification. Each entity issued an identification number shall provide or verify the information specified in paragraphs (1) to (9), inclusive, when requested by the department. The system shall include the provision or verification of all of the following
information:
(1)The name, mailing address, facsimile number, fictitious business name, federal employer number, State Board of Equalization identification number, SIC code, electronic mail address, if available, and telephone number of the firm or organization engaged in hazardous waste activities.
(2)The name, mailing address, facsimile number, and telephone number of the owner of the firm or organization.
(3)The name, title, mailing address, facsimile number, and telephone number of a contact person for the firm or organization.
(4)The identification number assigned to the firm or organization.
(5)The site location address or description associated with the firm or organization’s identification number provided in paragraph (4).
(6)The number of employees of the firm or organization.
(7)If the firm or organization is a generator, a statement of whether the generator produces RCRA hazardous waste or non-RCRA hazardous waste.
(8)An identification of any of the following hazardous waste activities in which the firm or organization is engaged:
(A)Generation.
(B)Transportation.
(C)Onsite treatment, storage, or disposal.
(9)The waste codes associated with the four largest hazardous waste streams, by volume, of the firm or organization. The federal waste code shall be verified for RCRA hazardous waste and the California waste code shall be verified for non-RCRA hazardous waste.
(c)Any generator, transporter, and facility operator who fails to comply with this section, or who fails to provide information required by the department to verify the accuracy of hazardous waste activity data, shall be subject to suspension of any and all identification numbers assigned to the generator, transporter, or facility operator and to any other authorized enforcement action.
(d)This section shall apply only to fees due for the 2013 and earlier
reporting periods.
(e)This section shall remain in effect only until January 1, 2014, and as of that date is repealed, unless a later enacted statute, that is enacted before January 1, 2014, deletes or extends that date.
(a)The department shall establish an identification number certification system to annually verify the accuracy of information related to generators, transporters, and facilities authorized to treat, store, or dispose of hazardous waste. Each entity issued an identification number shall provide or verify the information specified in paragraphs (1) to (9), inclusive, when requested by the department. The system shall include the provision or verification of all of the following information:
(1)The name, mailing address, facsimile number, fictitious business name, federal employer number, State Board of Equalization identification number, SIC code, electronic mail address, if available, and telephone number of the firm or organization engaged in hazardous waste activities.
(2)The name, mailing address, facsimile number, and telephone number of the owner of the firm or organization.
(3)The name, title, mailing address, facsimile number, and telephone number of a contact person for the firm or organization.
(4)The identification number assigned to the firm or organization.
(5)The site location address or description associated with the firm or organization’s identification number provided in paragraph (4).
(6)The number of employees of the firm or organization.
(7)If the firm or organization is a generator, a statement of whether the generator produces RCRA hazardous waste or non-RCRA hazardous waste.
(8)An identification of any of the following hazardous waste activities in which the firm or organization is engaged:
(A)Generation.
(B)Transportation.
(C)Onsite treatment, storage, or disposal.
(9)The waste codes associated with the four largest hazardous waste streams, by volume, of the firm or organization. The federal waste code shall be verified for RCRA hazardous waste and the California waste code shall be verified for non-RCRA hazardous waste.
(b)Any generator, transporter, and facility operator who fails to comply with this section, or who fails to provide information required by the department to verify the accuracy of hazardous waste activity data, shall be subject to suspension of any and all identification numbers assigned to the generator, transporter, or facility operator and to any other authorized enforcement action.
(c)This section shall become operative on January 1, 2014, and shall apply to the fees due for the 2014 reporting period and thereafter, including the prepayments due following the reporting period and the final reconciliation fee due and payable following the reporting period.
(a)If a facility has a permit or an interim status document that sets forth the facility’s allowable capacity for treatment or storage, the facility’s size for purposes of the annual facility fee pursuant to Section 25205.2 shall be based upon that capacity, except as provided in subdivision (d).
(b)If a facility’s allowable capacity changes or is initially established as a result of a permit modification, or a submission of a certification pursuant to subdivision (d), the fee that is due for the reporting period in which the change occurs shall be
the higher fee.
(c)The department may require the facility to submit an application to modify its permit to provide for an allowable capacity.
(d)A facility may reduce its allowable capacity below the amounts specified in subdivision (a) or (c) by submitting a certification signed by the owner or operator in which the owner or operator pledges that the facility will not handle hazardous waste at a capacity above the amount specified in the certification. In that case, the facility’s size for purposes of the annual facility fee pursuant to Section 25205.2 shall be based upon the capacity specified in the certification, until the certification is withdrawn. Exceeding the capacity limits specified in a certification that has not been withdrawn shall
be a violation of the hazardous waste control law and may subject a facility or its operator to a penalty and corrective action as provided in this chapter, including, but not limited to, an augmentation pursuant to Section 25191.1.
(e)This section shall have no bearing on the imposition of the annual postclosure facility fee.
(a)If a facility has a permit or an interim status document that sets forth the facility’s type, pursuant to Section 25205.1, as either treatment, storage, or disposal, the facility’s type for purposes of the annual facility fee pursuant to Section 25205.2 shall be rebuttably presumed to be what is set forth in that permit or document.
(b)If the facility’s type changes as a result of a permit or interim status modification, any change in the annual fee shall be effective the reporting period following the one in which the modification becomes effective.
(c)If the facility’s
permit or interim status document does not set forth its type, the department may require the facility to submit an application to modify the permit or interim status document to provide for a facility type.
(d)A permit or interim status document may set forth more than one facility type or size. In accordance with subdivision (d) of Section 25205.4, the facility shall be subject only to the highest applicable fee.
(a)Notwithstanding Section 25205.4, a disposal facility operator that is a government agency shall be subject to a maximum facility fee pursuant to Section 25205.2 of ten thousand dollars ($10,000) for any reporting period of 12 months and five thousand dollars ($5,000) for any reporting period of six months, for that disposal facility for any reporting period in which it did not at any time dispose of hazardous waste therein. This section shall apply to all reporting periods since the inception of the facility fee.
(b)This section shall not affect the imposition of the annual postclosure facility fee pursuant to Section
25205.2.
(a)Prior to January 1, 1996, any person transporting, importing, or receiving non-RCRA hazardous waste imported into this state for purposes of treatment, recycling, or disposal shall be considered the generator of that waste and the facility shall be considered the site of generation for purposes of payment of the generator fee pursuant to Section 25205.5, and the facility operator shall pay the applicable generator fee even if the operator has also paid a facility fee, but no generator fee shall be assessed for non-RCRA hazardous waste imported prior to January 1, 1994.
(b)Notwithstanding subdivision (c), any fees due pursuant to this chapter
for calendar year 1995 and which are due and payable in calendar year 1996 shall be paid in 1996 in accordance with Section 43152.7 of the Revenue and Taxation Code.
(c)On and after January 1, 1996, any person transporting, importing, or receiving non-RCRA hazardous waste imported into this state for purposes of treatment, recycling, or disposal shall be exempt from the payment of the generator fee imposed pursuant to Section 25205.5 and the generator surcharge imposed pursuant to Section 25205.9.
(d)This section applies only to fees due for the 2013 and earlier reporting periods, including the prepayments due during each reporting period and the final reconciliation fee due and payable by February 28 of the year following each reporting period.
(e)This section shall remain in effect only until January 1, 2014, and as of that date is repealed, unless a later enacted statute, that is enacted before January 1, 2014, deletes or extends that date.
(a)On and after January 1, 2014, for hazardous waste imported into this state for purposes of treatment, recycling, or disposal, the operator of the facility receiving the imported hazardous waste shall pay the applicable generation and handling fee.
(b)This section shall initially apply to the annual generation and handling fees due for the 2014 reporting period. This includes the prepayments due during the reporting period and the final reconciliation fee due and payable by February 28 of the year following the reporting period.
(c)This section shall become operative on January 1, 2014.
(a)Any eligible participant who submits banned, unregistered, or outdated agricultural wastes for collection in a program established pursuant to this article is exempt from the fees and reimbursements required by Sections 25174.1, 25205.2, 25205.5, and 25205.7, with regard to the wastes submitted for collection.
(b)An eligible participant who submits banned, unregistered, or outdated agricultural wastes for collection is exempt from the hazardous waste facilities permit requirements of Section 25201 with regard to the management of the wastes submitted for collection.
(c)A county operating a collection program in compliance with this article shall not be held liable in any cost recovery action brought pursuant to Section 25360 for any hazardous waste which has been properly handled and transported to an authorized hazardous waste treatment or disposal facility, in compliance with this chapter, at a location other than that of the collection program.
(d)This section shall remain in effect only until January 1, 2014, and as of that date is repealed, unless a later enacted statute, that is enacted before January 1, 2014, deletes or extends that date.
(a)Any eligible participant who submits banned, unregistered, or outdated agricultural wastes for collection in a program established pursuant to this article is exempt from the fees and reimbursements required by Sections 25205.2, 25205.5, and 25205.7, with regard to the wastes submitted for collection.
(b)An eligible participant who submits banned, unregistered, or outdated agricultural wastes for collection is exempt from the hazardous waste facilities permit requirements of Section 25201 with regard to the management of the wastes submitted for collection.
(c)A county operating a collection
program in compliance with this article shall not be held liable in any cost recovery action brought pursuant to Section 25360 for any hazardous waste that has been properly handled and transported to an authorized hazardous waste treatment or disposal facility, in compliance with this chapter, at a location other than that of the collection program.
(d)This section shall become operative on January 1, 2014, and shall apply to the fees due for the 2014 reporting period and thereafter, including the prepayments due following the reporting period and the final reconciliation fee due and payable following the reporting period.
(a)The department shall review each plan submitted pursuant to Section 25246 and shall approve the plan if it finds that the plan complies with the regulations adopted by the department and complies with all other applicable state and federal regulations.
(b)The department shall not approve the plan until at least one of the following occurs:
(1)The plan has been approved pursuant to Section 13227 of the Water Code.
(2)Sixty days expire after the owner or operator of an interim status facility submits the plan to the department. If the department denies approval of a plan for an interim status facility, this 60-day period shall not begin until the owner or operator resubmits the plan to the department.
(3)The director finds that immediate approval of the plan is necessary to protect public health, safety, or the environment.
(c)Any action taken by the department pursuant to this section is subject to Section 25204.5.
(d)(1)To the extent consistent with the federal act, the department shall impose the requirements of a hazardous waste facility postclosure plan on the owner or operator of a facility through the issuance of an enforcement order, entering into an enforceable agreement, or issuing a postclosure
permit.
(A)A hazardous waste facility postclosure plan imposed or modified pursuant to an enforcement order, a permit, or an enforceable agreement shall be approved in compliance with the California Environmental Quality Act (Division 13 (commencing with Section 21000) of the Public Resources Code).
(B)Before the department initially approves or significantly modifies a hazardous waste facility postclosure plan pursuant to this subdivision, the department shall provide a meaningful opportunity for public involvement, which, at a minimum, shall include public notice and an opportunity for public comment on the proposed action.
(C)For the purposes of subparagraph (B), a “significant modification” is a modification that the department determines would constitute a class 3 permit modification if the change were being proposed to a hazardous waste facilities permit. In determining whether the proposed modification would constitute a class 3 modification, the department shall consider the similarity of the modification to class 3 modifications codified in Appendix I of Chapter 20 (commencing with Section 66270.1) of Division 4.5 of Title 22 of the California Code of Regulations. In determining whether the proposed modification would constitute a class 3 modification, the department shall also consider whether there is significant public concern about the proposed modification, and whether the proposed change is so substantial or complex in nature that the modification requires the more extensive procedures of a class 3 permit modification.
(2)This subdivision does not limit or delay the authority of the department to order any action necessary at a facility to protect public health or safety.
(3)If the department imposes a hazardous waste facility postclosure plan in the form of an enforcement order or enforceable agreement, in lieu of issuing or renewing a postclosure permit, the owner or operator who submits the plan for approval shall, at the time the plan is submitted, enter into a cost reimbursement agreement pursuant to subdivision (a) of Section 25205.7 and upon commencement of the postclosure period shall pay the fee required by paragraph (9) of subdivision (c) of Section 25205.4. For purposes of this paragraph and paragraph (9) of subdivision (c) of Section 25205.4, the commencement of the postclosure period shall be the effective date of the postclosure permit, enforcement order, or enforceable agreement.
(4)In addition to any other remedy available under state law to enforce a postclosure plan imposed in the form of an enforcement order or enforcement agreement, the department may take any of the following actions:
(A)File an action to enjoin a threatened or continuing violation of a requirement of the enforcement order or agreement.
(B)Require compliance with requirements for corrective action or other emergency response measures that the department deems necessary to protect human health and the environment.
(C)Assess or file an action to recover civil penalties and fines for a violation of a requirement of an enforcement order or agreement.
(e)Subdivision (d) does not apply to a postclosure plan for which a final or draft permit has been issued by the department on or before December 31, 2003, unless the department and the facility mutually agree to replace the permit with an enforcement order or enforceable agreement pursuant to the provisions of subdivision (d).
(f)(1)Except as provided in paragraphs (2) and (3), the department may only impose postclosure plan requirements through an enforcement order or an enforceable agreement pursuant to subdivision (d) until January 1, 2009.
(2)This subdivision does not apply to an enforcement order or enforceable agreement issued prior to January 1, 2009, or an order or agreement for which a public notice is issued on or before January 1, 2009.
(3)This subdivision does not apply to the modification on or after January 1, 2009, of an enforcement order or enforceable agreement that meets the conditions in paragraph (2).
(g)If the department determines that a postclosure permit is necessary to enforce a postclosure plan, the department may, at any time, rescind and replace an enforcement order or an enforceable agreement issued pursuant to this section by issuing a postclosure permit for the hazardous waste facility, in accordance with the procedures specified in the department’s regulations for the issuance of postclosure permits.
(h)Nothing in this section may be construed to limit or delay the authority of the department to order any action necessary at a facility to protect public health or safety, or the environment.
(a)Except as provided in subdivision (b), any person who generates, receives, stores, transfers, transports, treats, or recycles used oil, unless specifically exempted or unless the used oil is not regulated by the department pursuant to subdivision (b) of Section 25250.1, shall comply with all provisions of this chapter.
(b)Used oil which is removed from a motor vehicle and which is subsequently recycled, by a recycler who is permitted pursuant to this article, shall not be included in the calculation of the amount of hazardous waste generated for purposes of the generator fee imposed pursuant to Section 25205.5.
(c)This section shall remain in effect only until January 1, 2014, and as of that date is repealed, unless a later enacted statute, that is enacted before January 1, 2014, deletes or extends that date.
(a)A person who generates, receives, stores, transfers, transports, treats, or recycles used oil, unless specifically exempted or unless the used oil is not regulated by the department pursuant to subdivision (b) of Section 25250.1, shall comply with all provisions of this chapter.
(b)This section shall become operative on January 1, 2014, and shall apply to the fees due for the 2014 reporting period and thereafter, including the prepayments due following the reporting period and the final reconciliation fee due and payable following the reporting period.
(1) | To the State Coastal Conservancy
........................
| $200,000,000 |
(2) | To the California Tahoe Conservancy
........................
| $ 40,000,000 |
(3) | To the Santa Monica Mountains Conservancy
........................
| $ 40,000,000 |
(4) | To the Coachella Valley Mountains Conservancy
........................
| $ 20,000,000 |
(5) | To the San Joaquin River Conservancy
........................
| $ 25,000,000 |
(6) | To the San Gabriel and Lower Los Angeles Rivers and Mountains Conservancy
........................
| $ 40,000,000 |
(7) | To the Baldwin Hills Conservancy
........................
| $ 40,000,000 |
(8) | To the San Francisco Bay Area Conservancy Program
........................
| $ 40,000,000 |
(a)For purposes of the collection of the fees specified in subdivision (a) of Section 25174 and the fee imposed pursuant to Section 25174.1 of the Health and Safety Code, a determination by the Department of Toxic Substances Control that a waste is nonhazardous shall be effective only for wastes disposed of, or submitted for disposal, commencing with the month during which the Department of Toxic Substances Control receives a completed application for that determination.
(b)This section applies only to fees due for the 2013 and earlier reporting periods.
(c)This
section shall remain in effect only until January 1, 2014, and as of that date is repealed, unless a later enacted statute, that is enacted before January 1, 2014, deletes or extends that date.
(a)For purposes of this part, “taxpayer” means any person liable for the payment of a fee or a tax specified in paragraph (1) of subdivision (a) of Section 25173.6 of the Health and Safety Code or subdivision (a) of Section 25174 of the Health and Safety Code, or imposed by Section 105310 or 25174.1 of the Health and Safety Code.
(b)This section shall remain in effect only until January 1, 2014, and as of that date is repealed, unless a later enacted statute, that is enacted before January 1, 2014, deletes or extends that date.
(a)For purposes of this part, “taxpayer” means any person liable for the payment of a fee or a tax specified in paragraph (1) of subdivision (a) of Section 25173.6 of the Health and Safety Code or subdivision (a) of Section 25174 of the Health and Safety Code, or imposed by Section 105310 of the Health and Safety Code.
(b)This section shall become operative on January 1, 2014, and shall apply to the fees due for the 2014 reporting period and thereafter, including the prepayments due following the reporting period and the final reconciliation fee due and payable following the reporting period.
(a)The fee imposed pursuant to Section 25174.1 of the Health and Safety Code shall be administered and collected by the board in accordance with this part.
(b)This section applies only to fees due for the 2013 and earlier reporting periods.
(c)This section shall remain in effect only until January 1, 2014, and as of that date is repealed, unless a later enacted statute, that is enacted before January 1, 2014, deletes or extends that date.
The fees imposed pursuant to Sections 25205.2, 25205.5, and 25205.14 of the Health and Safety Code shall be administered and collected by the board in accordance with this part.
Every person, as defined in Section 25118 of the Health and Safety Code, who is subject to the fees specified in Section 105190 of the Health and Safety Code, and imposed pursuant to Sections 25205.2, 25205.5, 25205.6, and 25205.14 of the Health and Safety Code, shall register with the board on forms provided by the board.
(a)The fee imposed pursuant to Section 25174.1 of the Health and Safety Code, which is a tax collected and administered under Section 43051, is due and payable to the board monthly on or before the last day of the third calendar month following the end of the calendar month for which the fee is due. Each taxpayer shall, on or before the last day of the third calendar month following the end of the calendar month for which the fee is due, make out a tax return for the calendar month, in the form as prescribed by the board, which may include, but not be limited to, electronic media in accordance with subdivision (c). The taxpayer shall deliver the return, together with a remittance of the amount of fee
due, to the office of the board on or before the last day of the third calendar month following the end of the calendar month for which the fee is due. Returns shall be authenticated in a form or pursuant to methods as may be prescribed by the board.
(b)With the approval of the board, a taxpayer who has more than one facility subject to the taxes collected and administered under this chapter, may file a combined tax return covering operations at more than one, or all, of those facilities.
(c)The form required to be submitted by the taxpayer pursuant to this section shall show, for the taxpayer and for each person from whom the taxpayer accepted hazardous waste for disposal, all of the following:
(1)The total amount of hazardous waste subject to the tax and the amount of the tax for the period covered by the return.
(2)The amount of hazardous waste disposed during the tax period that is in each of the fee categories described in Section 25174.6 of the Health and Safety Code, and the amount of disposal fees paid for each of those categories.
(3)The amount of hazardous waste received for disposal by the taxpayer’s facility or facilities that is exempt from the payment of disposal fees pursuant to Section 25174.7 of the Health and Safety Code, including a copy of any written documentation provided for any shipment or shipments of hazardous waste received by a facility.
(4)The amount of RCRA hazardous waste which is treated by the taxpayer so that the waste is considered to be non-RCRA hazardous waste for purposes of the disposal fee, pursuant to paragraph (2) of subdivision (b) of Section 25174.6.
(d)(1)Each taxpayer shall maintain records documenting all of the following information for each person who has submitted hazardous waste for disposal by the taxpayer during each calendar month and shall make those records available for review and inspection at the request of the board or the department:
(A)The tonnage of hazardous waste submitted for disposal.
(B)The type of hazardous waste disposed as specified by Section 25174.6 of the Health and Safety Code, including both of the following:
(i)Any characterization of the hazardous waste made by the person submitting the hazardous waste for disposal.
(ii)Any other documentation which the taxpayer maintains regarding the type of hazardous waste disposed to land.
(C)Any representation made by the person submitting the hazardous waste regarding any exemptions that may be applicable to the payment of disposal fees.
(D)For any RCRA hazardous waste which is treated by the taxpayer so that the waste is considered to be non-RCRA hazardous waste for purposes of the disposal fee, pursuant to paragraph (2) of subdivision (b) of Section 25174.6, all of the following information:
(i)The tonnage and type of hazardous waste.
(ii)The method or methods used to treat the hazardous waste.
(iii)Operating records documenting the treatment activity.
(iv)Representative and statistical waste sampling and analysis data demonstrating that the waste is no longer RCRA hazardous waste at the time of disposal.
(2)If the hazardous wastes submitted for disposal were accompanied by a manifest, the information specified in paragraph (1) shall be maintained by manifest number for each calendar month.
(e)This section applies only to
fees due for the 2013 and earlier reporting periods.
(f)This section shall remain in effect only until January 1, 2014, and as of that date is repealed, unless a later enacted statute, that is enacted before January 1, 2014, deletes or extends that date.
(a)The board shall establish and annually submit to each generator of hazardous waste a consolidated statement of fees required to be paid by the generator to the board pursuant to Sections 25205.2, 25205.5, 25205.6, and 25205.14 of the Health and Safety Code.
(b)Notwithstanding any other provision of law, any return or other document that is required to be submitted by a generator of hazardous waste to the board in connection with the payment of any fee specified in subdivision (a) shall instead be submitted together with the consolidated statement made pursuant to subdivision (a).
(a)The fee imposed pursuant to Section 25205.5 of the Health and Safety Code that is collected and administered under Section 43053 is due and payable on the last day of the second month following the end of the calendar year.
(b)Every generator subject to the fee imposed pursuant to Section 25205.5 of the Health and Safety Code shall file an annual return in the form as prescribed by the board, which may include, but not be limited to, electronic media and pay the proper amount of fee due. The board shall credit the prepayment made pursuant to Section 43152.15 against the amount due with the annual return. Returns shall be authenticated in a form
or pursuant to methods as may be prescribed by the board.
The fees collected and administered under Sections 43053 and 43054, are due and payable within 30 days after the date of assessment and the feepayer shall deliver a remittance of the amount of the assessed fee to the office of the board within that 30-day period.
(a)In addition to the requirements imposed pursuant to Section 43152.7, every generator subject to the fees specified in Sections 25205.5 and 25205.9 of the Health and Safety Code shall make a prepayment of the fee by site to the board which is due and payable on or before the last day of August of each calendar year. The prepayment shall be accompanied by a prepayment return in a form prescribed by the board.
(b)For purposes of subdivision (a), the amount of the prepayment shall be not less than either of the following:
(1)One hundred percent of the applicable fee imposed on the generator, based on the generator’s fee category as specified in Section 25205.5 of the Health and Safety Code for the total volume of hazardous waste generated by site during the period January 1 to June 30, inclusive, of the current calendar year in which the prepayment is due. The prepayment may be offset by fees paid by the generator for a local hazardous waste management program conducted by a local agency pursuant to a memorandum of understanding with the department which includes the following:
(A)The local fees are paid for the current calendar year for which the prepayment is due or the local fees are paid for the preceding calendar year, if fees have not been paid for the current year.
(B)The offset is subject to the limitations and requirements specified in subdivision (c) of Section 43152.7.
(2)Fifty percent of the generator fee liability paid to the board by site for the preceding calendar year provided the generator paid a generator fee liability to the board for the preceding calendar year for that site.
(c)The board shall credit the amount of the prepayment against the amount of the fee due and payable for the calendar year in which the prepayment is due.
(d)Notwithstanding any other provision in this section, the prepayment of a generator fee shall not be required for any amount due that is less than five hundred dollars ($500), or for any other amount due if the board determines that prepayment is not in the best economic interest of the program.
(e)Any person required to make a prepayment pursuant to this section who fails to make a prepayment by the due date specified in subdivision (a) shall also pay penalties and interest in accordance with Section 43155.
(f)This section applies only to fees due for the 2013 and earlier reporting periods.
(g)This section shall remain in effect only until January 1, 2014, and as of that date is repealed, unless a later enacted statute, that is enacted before January 1, 2014, deletes or extends that date.
(a)In addition to the requirements imposed pursuant to Section 43152.7, every generator subject to the fees specified in Section 25205.5 of the Health and Safety Code shall make a prepayment of the fee by site to the board which is due and payable on or before the last day of August of each calendar year. The prepayment shall be accompanied by a prepayment return in a form prescribed by the board.
(b)For purposes of subdivision (a), the amount of the prepayment shall be not less than either of the following:
(1)One hundred percent of the applicable fee imposed on the generator, based on the generation and handling fee specified in Section 25205.5 of the Health and Safety Code for the total volume of hazardous waste generated by site during the period January 1 to June 30, inclusive, of the current calendar year in which the prepayment is due. The prepayment may be offset by fees paid by the generator for a local hazardous waste management program conducted by a local agency pursuant to a memorandum of understanding with the department which includes the following:
(A)The local fees are paid for the current calendar year for which the prepayment is due or the local fees are paid for the preceding calendar year, if fees have not been paid for the current year.
(B)The offset is subject to the limitations and requirements specified in subdivision (c) of Section 43152.7.
(2)Fifty percent of the generation and handling fee liability paid to the board by site for the preceding calendar year provided the generator paid a generation and handling fee liability to the board for the preceding calendar year for that site.
(c)The board shall credit the amount of the prepayment against the amount of the fee due and payable for the calendar year in which the prepayment is due.
(d)Notwithstanding any other provision in this section, the prepayment of a generation and handling fee shall not be required for any amount due that is less than five hundred dollars ($500), or for any other amount due if the board determines that prepayment is not in the best economic interest of the program.
(e)Any person required to make a prepayment pursuant to this section who fails to make a prepayment by the due date specified in subdivision (a) shall also pay penalties and interest in accordance with Section 43155.