(10) Does not have any significant impacts that have not been publicly disclosed, analyzed, and mitigated.
(c) The proponent of a project described in subdivision (b) shall do both of the following, as applicable:
(1) Certify to the local agency that either of the following is true, as applicable:
(A) The
entirety of the project is a public work for purposes of Chapter 1 (commencing with Section 1720) of Part 7 of Division 2 of the Labor Code.
(B) If the project is not in its entirety a public work, that all construction workers employed in the execution of the project will be paid at least the general prevailing rate of per diem wages for the type of work and geographic area, as determined by the Director of Industrial Relations pursuant to Sections 1773 and 1773.9 of the Labor Code, except that apprentices registered in programs approved by the Chief of the Division of Apprenticeship Standards may be paid at least the applicable apprentice prevailing rate. If the project is subject to this subparagraph, for those portions of the project that are not a public work, all of the following shall apply:
(i) The project proponent shall ensure that the prevailing wage requirement is included in all contracts for the performance of the work.
(ii) All contractors and subcontractors shall pay to all construction workers employed in the execution of the work at least the general prevailing rate of per diem wages, except that apprentices registered in programs approved by the Chief of the Division of Apprenticeship Standards may be paid at least the applicable apprentice prevailing rate.
(iii) Except as provided in clause (v), all contractors and subcontractors shall maintain and verify payroll records pursuant to Section 1776 of the Labor Code and make those records available
for inspection and copying as provided in therein.
(iv) Except as provided in clause (v), the obligation of the contractors and subcontractors to pay prevailing wages may be enforced by the Labor Commissioner through the issuance of a civil wage and penalty assessment pursuant to Section 1741 of the Labor Code, which may be reviewed pursuant to Section 1742 of the Labor Code within 18 months after the completion of the project by an underpaid worker through an administrative complaint or civil action, or by a joint labor-management committee though a civil action under Section 1771.2 of the Labor Code. If a civil wage and penalty assessment is issued, the
contractor, subcontractor, and surety on a bond or bonds issued to secure the payment of wages covered by the assessment shall be liable for liquidated damages pursuant to Section 1742.1 of the Labor Code.
(v) Clauses (iii) and (iv) shall not apply if all contractors and subcontractors performing work on the project are subject to a project labor agreement that requires the payment of prevailing wages to all construction workers employed in the execution of the project and provides for enforcement of that obligation through an arbitration procedure. For purposes of this clause, “project labor agreement” has the same meaning as set forth in paragraph (1) of subdivision (b) of Section 2500 of the Public Contract Code.
(vi) Notwithstanding subdivision (c) of Section 1773.1 of the Labor Code, the requirement that employer payments not reduce the obligation to pay the hourly straight time or overtime wages found to be prevailing shall not apply if otherwise provided in a bona fide collective bargaining agreement covering the worker. The requirement to pay at least the general prevailing rate of per diem wages does not preclude use of an alternative workweek schedule adopted pursuant to Section 511 or 514 of the Labor Code.
(2) (A) Certify to the local agency that a skilled and trained workforce will be used to complete the project.
(B) If the project proponent has certified that a skilled and trained workforce
will be used to complete the project, the following shall apply:
(i) The project proponent shall require in all contracts for the performance of work that every contractor and subcontractor at every tier will individually use a skilled and trained workforce to complete the project.
(ii) Every contractor and subcontractor shall use a skilled and trained workforce to complete the project.
(iii) Except as provided in clause (iv), the project proponent shall provide to the local agency, on a monthly basis while the project or contract is being performed, a report demonstrating compliance with Chapter 2.9 (commencing with Section 2600) of Part
1 of Division 2 of the Public Contract Code. A monthly report provided to the local agency pursuant to this clause shall be a public record under the California Public Records Act (Chapter 3.5 (commencing with Section 6250) of Division 7 of Title 1 of the Government Code) and shall be open to public inspection. A project proponent that fails to provide a monthly report demonstrating compliance with Chapter 2.9 (commencing with Section 2600) of Part 1 of Division 2 of the Public Contract Code shall be subject to a civil penalty of ten thousand dollars ($10,000) per month for each month for which the report has not been provided. Any contractor or subcontractor that fails to use a skilled and trained workforce shall be subject to a civil penalty of two hundred dollars ($200) per day for each worker employed in contravention of the skilled and trained workforce requirement. Penalties may be assessed by
the Labor Commissioner within 18 months of completion of the project using the procedures for issuance of civil wage and penalty assessments set forth in Section 1741 of the Labor Code, and may be reviewed pursuant to the procedures set forth in Section 1742 of the Labor Code. Penalties shall be paid to the State Public Works Enforcement Fund.
(iv) Clause (iii) shall not apply if all contractors and subcontractors performing work on the project are subject to a project labor agreement that requires compliance with the skilled and trained workforce requirement and provides for enforcement of that obligation through an arbitration procedure. For purposes of this clause, “project labor agreement” has the same meaning as set forth in paragraph (1) of subdivision (b) of Section 2500 of the Public Contract Code.
(d) Prior to determining that a project is exempt pursuant to this
section, the lead agency shall do all of the following:
(1) Ensure that the project proponent has met the requirements of subdivision (c).
(2) Issue and publish a draft determination that the project is exempt pursuant to this section.
(3) (A) Hold a noticed public hearing no earlier than 30 days following the publication of the draft determination and at least
30 days prior to the issuance of a final determination in areas affected by the project to hear and respond to public comments.
(B) Publication of the notice shall be no fewer times than required by Section 6061 of the Government Code, by the lead agency in a newspaper of general circulation in the area affected by the proposed project. If more than one area will be affected, the notice shall be published in the newspaper with the largest circulation from among the newspapers of general circulation in those areas.
(e) If the lead agency determines that a project is not subject to this division pursuant to this section and it determines to approve or carry out the project, the lead agency shall file a notice with the Office of Planning and Research in the manner specified