20175.2.
(a) (1) A city, with approval of the appropriate city council, may utilize an alternative procedure for bidding on building construction projects in the city in excess of one million dollars ($1,000,000), except as provided in subdivision (p).(2) Cities may award the project using either the lowest responsible bidder or by best value.
(b) (1) It is the intent of the Legislature to enable cities to utilize cost-effective options for building and modernizing public facilities. The Legislature also recognizes the national trend, including authorization in California, to allow
public entities to utilize design-build contracts as a project delivery method. It is not the intent of the Legislature to authorize this procedure for transportation facilities, including, but not limited to, roads and bridges.
(2) The Legislature also finds and declares that utilizing a design-build contract requires a clear understanding of the roles and responsibilities of each participant in the design-build process. The Legislature also finds that the cost-effective benefits to cities are achieved by shifting the liability and risk for cost containment and project completion to the design-build entity.
(3) It is the intent of the Legislature to provide an alternative and optional procedure for bidding and building construction projects for cities.
(4) The design-build approach may be used, but is not limited to
use, when it is anticipated that it will: reduce project cost, expedite project completion, or provide design features not achievable through the design-bid-build method.
(5) (A) For contracts awarded prior to the effective date of either the regulations adopted by the Department of Industrial Relations pursuant to subdivision (b) of Section 1771.55 of the Labor Code or the fees established by the department pursuant to subparagraph (B), if a city council elects to proceed under this section, the city council shall establish and enforce, for design-build projects, a labor compliance program containing the requirements outlined in Section 1771.5 of the Labor Code, or it shall contract with a third party to operate a labor compliance program containing the requirements outlined in Section 1771.5 of the Labor Code. This requirement shall not apply to any project where the city or the design-build entity has entered into any
collective bargaining agreement or agreements that bind all of the contractors performing work on the projects.
(B) For contracts awarded on or after the effective date of both the regulations adopted by the Department of Industrial Relations pursuant to subdivision (b) of Section 1771.55 of the Labor Code and the fees established by the department pursuant to this subparagraph, the city council shall pay a fee to the department, in an amount that the department shall establish, and as it may from time to time amend, sufficient to support the department’s costs in ensuring compliance with and enforcing prevailing wage requirements on the project, and labor compliance enforcement as set forth in subdivision (b) of Section 1771.55. All fees collected pursuant to this paragraph shall be deposited in the State Public Works Enforcement Fund created by Section 1771.3 of the Labor Code, and shall be used only for enforcement of prevailing wage
requirements on those projects.
(C) The Department of Industrial Relations may waive the fee set forth in subparagraph (2) if the city council has previously been granted approval by the director to initiate and operate a labor compliance program on its projects and requests to continue to operate that labor compliance program on its projects in lieu of labor compliance by the department pursuant to subdivision (b) of Section 1771.55. The fee shall not be waived for the city council if it contracts with a third party to initiate and enforce labor compliance programs on its projects.
(c) As used in this section:
(1) “Best value” means a value determined by objectives relative to price, features, functions, and life-cycle costs.
(2) “Design-build” means a
procurement process in which both the design and construction of a project are procured from a single entity.
(3) “Design-build entity” means a partnership, corporation, or other legal entity that is able to provide appropriately licensed contracting, architectural, and engineering services, as needed, pursuant to a design-build contract.
(4) “Project” means the construction of a building and improvements directly related to the construction of a building, but does not include streets and highways, public rail transit, or water resource facilities and infrastructure.
(d) Design-build projects shall progress in a four-step process, as follows:
(1) (A) The city shall prepare a set of documents setting forth the scope of the project.
The documents may include, but are not limited to, the size, type, and desired design character of the buildings and site, performance specifications covering the quality of materials, equipment, and workmanship, preliminary plans or building layouts, or any other information deemed necessary to describe adequately the city’s needs. The performance specifications and any plans shall be prepared by a design professional who is duly licensed and registered in California.
(B) Any architect or engineer retained by the city to assist in the development of the project-specific documents shall not be eligible to participate in the preparation of a bid with any design-build entity for that project.
(2) (A) Based on the documents prepared in paragraph (1), the city shall prepare a request for proposals that invites interested parties to submit competitive sealed
proposals in the manner prescribed by the city. The request for proposals shall include, but is not limited to, the following elements:
(i) Identification of the basic scope and needs of the project or contract, the expected cost range, and other information deemed necessary by the city to inform interested parties of the contracting opportunity, to include the methodology that will be used by the city to evaluate proposals, and specifically if the contract will be awarded to the lowest responsible bidder.
(ii) Significant objective factors which the city reasonably expects to consider in evaluating proposals, including cost or price and all nonprice related factors.
(iii) The relative importance or weight assigned to each of the factors identified in the request for proposals.
(B) With respect to clause (iii) of subparagraph (A), if a nonweighted system is used, the agency shall specifically disclose whether all evaluation factors, other than cost or price, when combined are:
(i) Significantly more important than cost or price.
(ii) Approximately equal in importance to cost or price.
(iii) Significantly less important than cost or price.
(C) If the city chooses to reserve the right to hold discussions or negotiations with responsive bidders, it shall so specify in the request for proposal and shall publish separately, or incorporate into the request for proposal, applicable rules and procedures to be observed by the city to ensure that any discussions or
negotiations are conducted in good faith.
(3) (A) The city shall establish a procedure to prequalify design-build entities using a standard questionnaire developed by the city. In preparing the questionnaire, the city shall consult with the construction industry, including representatives of the building trades and surety industry. This questionnaire shall require information including, but not limited to, all of the following:
(i) If the design-build entity is a partnership, limited partnership, or other association, a listing of all of the partners, general partners, or association members known at the time of bid submission who will participate in the design-build contract, including, but not limited to, mechanical subcontractors.
(ii) Evidence that the members of the design-build entity have
completed, or demonstrated the experience, competency, capability, and capacity to complete projects of similar size, scope, or complexity, and that proposed key personnel have sufficient experience and training to competently manage and complete the design and construction of the project, as well as a financial statement that assures the city that the design-build entity has the capacity to complete the project.
(iii) The licenses, registration, and credentials required to design and construct the project, including information on the revocation or suspension of any license, credential, or registration.
(iv) Evidence that establishes that the design-build entity has the capacity to obtain all required payment and performance bonding, liability insurance, and errors and omissions insurance.
(v) Any prior serious or
willful violation of the California Occupational Safety and Health Act of 1973, contained in Part 1 (commencing with Section 6300) of Division 5 of the Labor Code or the federal Occupational Safety and Health Act of 1970 (Public Law 91-596) settled against any member of the design-build entity, and information concerning workers’ compensation experience history and worker safety program.
(vi) Information concerning any debarment, disqualification, or removal from a federal, state, or local government public works project. Any instance where an entity, its owners, officers, or managing employees submitted a bid on a public works project and were found to be nonresponsive, or were found by an awarding body not to be a responsible bidder.
(vii) Any instance where the entity, its owners, officers, or managing employees defaulted on a construction contract.
(viii) Any violations of the Contractors State License Law (Chapter 9 (commencing with Section 7000) of Division 3 of the Business and Professions Code), excluding alleged violations of federal or state law including the payment of wages, benefits, apprenticeship requirements, or personal income tax withholding, or of Federal Insurance Contribution Act (FICA) withholding requirements settled against any member of the design-build entity.
(ix) Information concerning the bankruptcy or receivership of any member of the design-build entity, including information concerning any work completed by a surety.
(x) Information concerning all settled adverse claims, disputes, or lawsuits between the owner of a public works project and any member of the design-build entity during the five years preceding submission of a bid pursuant
to this section, in which the claim, settlement, or judgment exceeds fifty thousand dollars ($50,000). Information shall also be provided concerning any work completed by a surety during this period.
(xi) In the case of a partnership or an association that is not a legal entity, a copy of the agreement creating the partnership or association and specifying that all partners or association members agree to be fully liable for the performance under the design-build contract.
(xii) (I) Any instance in which the entity, or any of its members, owners, officers, or managing employees was, during the five years preceding submission of a bid pursuant to this section, determined by a court of competent jurisdiction to have submitted, or legally admitted for purposes of a criminal plea to have submitted either of the following:
(ia) Any claim to any public agency or official in violation of the federal False Claims Act (31 U.S.C. Sec. 3729 et seq.).
(ib) Any claim to any public official in violation of the California False Claims Act (Article 9 (commencing with Section 12650) of Chapter 6 of Part 2 of Division 3 of the Government Code).
(II) Information provided pursuant to this subdivision shall include the name and number of any case filed, the court in which it was filed, and the date on which it was filed. The entity may also provide further information regarding any such instance, including any mitigating or extenuating circumstances that the entity wishes the city to consider.
(B) The information required pursuant to this subdivision shall be verified under oath by the
entity and its members in the manner in which civil pleadings in civil actions are verified. Information that is not a public record pursuant to the California Public Records Act (Chapter 3.5 (commencing with Section 6250) of Division 7 of Title 1 of the Government Code) shall not be open to public inspection.
(4) The city shall establish a procedure for final selection of the design-build entity. Selection shall be based on either of the following criteria:
(A) A competitive bidding process resulting in lump-sum bids by the prequalified design-build entities. Awards shall be made to the lowest responsible bidder.
(B) The city may use a design-build competition based upon best value and other criteria set forth in paragraph (2) of subdivision (d). The design-build competition shall include the following elements:
(i) Competitive proposals shall be evaluated by using only the criteria and selection procedures specifically identified in the request for proposal. However, the following minimum factors shall each represent at least 10 percent of the total weight of consideration given to all criteria factors: price, technical design and construction expertise, life-cycle costs over 15 years or more, skilled labor force availability, and acceptable safety record.
(ii) Once the evaluation is complete, the top three responsive bidders shall be ranked sequentially from the most advantageous to the least.
(iii) The award of the contract shall be made to the responsible bidder whose proposal is determined, in writing, to be the most advantageous.
(iv) Notwithstanding any
provision of this code, upon issuance of a contract award, the city shall publicly announce its award, identifying the contractor to whom the award is made, along with a written decision supporting its contract award and stating the basis of the award. The notice of award shall also include the city’s second and third ranked design-build entities.
(v) For purposes of this paragraph, “skilled labor force availability” shall be determined by the existence of an agreement with a registered apprenticeship program, approved by the California Apprenticeship Council, which has graduated apprentices in each of the preceding five years. This graduation requirement shall not apply to programs providing apprenticeship training for any craft that has been deemed by the Department of Labor and the Department of Industrial Relations to be an apprenticeable craft in the five years prior to enactment of this act.
(vi) For purposes of this paragraph, a bidder’s “safety record” shall be deemed “acceptable” if its experience modification rate for the most recent three-year period is an average of 1.00 or less, and its average total recordable injury/illness rate and average lost work rate for the most recent three-year period does not exceed the applicable statistical standards for its business category, or if the bidder is a party to an alternative dispute resolution system, as provided for in Section 3201.5 of the Labor Code.
(e) (1) Any design-build entity that is selected to design and build a project pursuant to this section shall possess or obtain sufficient bonding to cover the contract amount for nondesign services and errors and omissions insurance coverage sufficient to cover all design and architectural services provided in the contract. This section does not
prohibit a general or engineering contractor from being designated the lead entity on a design-build entity for the purposes of purchasing necessary bonding to cover the activities of the design-build entity.
(2) Any payment or performance bond written for the purposes of this section shall be written using a bond form developed by the city.
(f) All subcontractors that were not listed by the design-build entity in accordance with clause (i) of subparagraph (A) of paragraph (3) of subdivision (d) shall be awarded by the design-build entity in accordance with the design-build process set forth by the city in the design-build package. All subcontractors bidding on contracts pursuant to this section shall be afforded the protections contained in Chapter 4 (commencing with Section 4100) of Part 1. The design-build entity shall do both of the following:
(1) Provide public notice of the availability of work to be subcontracted in accordance with the publication requirements applicable to the competitive bidding process of the city.
(2) Provide a fixed date and time on which the subcontracted work will be awarded in accordance with the procedure established pursuant to this section.
(g) Lists of subcontractors, bidders, and bid awards relating to the project shall be submitted by the design-build entity to the awarding body within 14 days of the award. These documents are deemed to be public records and shall be available for public inspection pursuant to this chapter and Article 1 (commencing with Section 6250) of Chapter 3.5 of Division 7 of the Government Code.
(h) The minimum performance criteria and
design standards established pursuant to paragraph (1) of subdivision (d) shall be adhered to by the design-build entity. Any deviations from those standards may only be allowed by written consent of the city.
(i) The city may retain the services of a design professional or construction project manager, or both, throughout the course of the project in order to ensure compliance with this section.
(j) Contracts awarded pursuant to this section shall be valid until the project is completed.
(k) Nothing in this section is intended to affect, expand, alter, or limit any rights or remedies otherwise available at law.
(l) (1) If the city elects to award a project pursuant to this section, retention proceeds withheld by the city from the
design-build entity shall not exceed 5 percent if a performance and payment bond, issued by an admitted surety insurer, is required in the solicitation of bids.
(2) In a contract between the design-build entity and the subcontractor, and in a contract between a subcontractor and any subcontractor thereunder, the percentage of the retention proceeds withheld may not exceed the percentage specified in the contract between the city and the design-build entity. If the design-build entity provides written notice to any subcontractor who is not a member of the design-build entity, prior to or at the time the bid is requested, that a bond may be required and the subcontractor subsequently is unable or refuses to furnish a bond to the design-build entity, then the design-build entity may withhold retention proceeds in excess of the percentage specified in the contract between the city and the design-build entity from any payment made by the
design-build entity to the subcontractor.
(m) Each city that elects to proceed under this section and uses the design-build method on a public works project shall submit to the Legislative Analyst’s Office before December 1, 2014, a report containing a description of each public works project procured through the design-build process that is completed after January 1, 2011, and before November 1, 2014. The report shall include, but shall not be limited to, all of the following information:
(1) The type of project.
(2) The gross square footage of the project.
(3) The design-build entity that was awarded the project.
(4) The estimated and actual project costs.
(5) The estimated and actual length of time to complete the project.
(6) A description of any written protests concerning any aspect of the solicitation, bid, proposal, or award of the design-build project, including the resolution of the protests.
(7) An assessment of the prequalification process and criteria.
(8) An assessment of the effect of retaining 5 percent retention on the project.
(9) A description of the Labor Force Compliance Program and an assessment of the project impact, where required.
(10) A description of the method used to award the contract. If the best value method was used, the report shall describe the
factors used to evaluate the bid, including the weighting of each factor and an assessment of the effectiveness of the methodology.
(11) An assessment of the project impact of “skilled labor force availability.”
(12) An assessment of the most appropriate uses for the design-build approach.
(n) Any city that elects not to use the authority granted by this section may submit a report to the Legislative Analyst’s Office explaining why the city elected not to use the design-build method.
(o) On or before January 1, 2015, the Legislative Analyst’s Office shall report to the Legislature on the use of the design-build method by cities pursuant to this section, including the information listed in subdivision
(m). The report may include recommendations for modifying or extending this section.
(p) Except as provided in this section, nothing in this act shall be construed to affect the application of any other law.
(q) Before January 1, 2011, the project limitation of one million dollars ($1,000,000), as set forth in subdivision (a), shall not apply to any city in the Counties of Solano and Yolo, or to the Cities of Stanton and Victorville.
(r) This section shall remain in effect only until January 1, 2016, and as of that date is repealed, unless a later enacted statute, that is enacted before January 1, 2016, deletes or extends that date.