2827.10.
(a) As used in this section, the following terms have the following meanings:(1) “Electrical corporation” means an electrical corporation, as defined in Section 218.
(2) “Eligible fuel cell electrical generating facility” means a facility that includes the following:
(A) Integrated powerplant systems containing a stack, tubular array, or other functionally similar configuration used to electrochemically convert fuel to electric energy.
(B) An inverter and fuel processing system where necessary.
(C) Other plant equipment, including heat recovery equipment, necessary to support the plant’s operation or its energy conversion.
(3) “Eligible fuel cell customer-generator” means a customer of an electrical corporation that meets all the following criteria:
(A) Uses a fuel cell electrical generating facility with a capacity of not more than one megawatt that is located on or adjacent to the customer’s owned, leased, or rented premises, is interconnected and operates in parallel with the electric grid while the grid is operational or in a grid independent mode when the grid is nonoperational, and is sized to offset part or all of the eligible fuel cell customer-generator’s own electrical requirements.
(B) Is the recipient of local, state, or federal
funds, or who self-finances projects designed to encourage the development of eligible fuel cell electrical generating facilities.
(C) Uses technology that meets the definition of an “ultra-clean and low-emission distributed generation” in subdivision (a) of Section 353.2.
(4) “Net energy metering” has the same meaning as that term is defined in Section 2827.9.
(b) Every electrical corporation shall, not later than March 1, 2004, file with the commission a standard tariff providing for net energy metering for eligible fuel cell customer-generators, consistent with this section. Every electrical corporation shall make this tariff available to eligible fuel cell customer-generators upon request, on a first-come-first-served basis, until the total cumulative rated generating capacity used by the eligible fuel cell
customer-generators equals 45 megawatts within the service territory of the electrical corporation for an electrical corporation with a peak demand above 10,000 megawatts, or equals 22.5 megawatts within the service territory of the electrical corporation for an electrical corporation with a peak demand of 10,000 megawatts or below. The combined statewide cumulative rated generating capacity used by the eligible fuel cell customer-generators in the service territories of all electrical corporations in the state may not exceed 112.5 megawatts.
(c) In determining the eligibility for the cumulative rated generating capacity within an electrical service area, preference shall be given to facilities which, at the time of installation, are located in a community with significant exposure to air contaminants or localized air contaminants, or both, including, but not limited to, communities of minority populations or low-income populations, or both,
based on the ambient air quality standards established pursuant to Section 39607 of the Health and Safety Code.
(d) Each net energy metering contract or tariff shall be identical, with respect to rate structure, all retail rate components, and any monthly charges, to the contract or tariff to which the customer would be assigned if the customer was not an eligible fuel cell customer-generator. Any new or additional demand charge, standby charge, customer charge, minimum monthly charge, interconnection charge, or other charge that would increase an eligible fuel cell customer-generator’s costs beyond those of other customers in the rate class to which the eligible fuel cell customer-generator would otherwise be assigned are contrary to the intent of the Legislature in enacting the act adding this section, and may not form a part of net energy metering tariffs.
(e) The net metering
calculation shall be carried out in accordance with Section 2827.9.
(f) A fuel cell electrical generating facility shall not be eligible for participation in the tariff established pursuant to this section unless it commenced operation before January 1, 2010. A fuel cell customer‑generator shall be eligible for the tariff established pursuant to this section only for the operating life of the eligible fuel cell electrical generating facility.