Code Section Group

Water Code - WAT

DIVISION 12. COUNTY WATER DISTRICTS [30000 - 33901]

  ( Division 12 added by Stats. 1949, Ch. 274. )

PART 5. POWERS AND PURPOSES [31000 - 31182]

  ( Part 5 added by Stats. 1949, Ch. 274. )

CHAPTER 1. Powers and Purposes Generally [31000 - 31149.7]

  ( Chapter 1 added by Stats. 1949, Ch. 274. )

ARTICLE 11. Power Generation [31149.1 - 31149.7]
  ( Article 11 added by Stats. 1981, Ch. 79, Sec. 2. )

31149.1.
  

A district may, by using any water or water supplies furnished to the district or used by the district, construct, maintain, and operate one or more plants for the generation of hydroelectric power from the water, and the transmission lines for the conveyance thereof.

“Plant for the generation of hydroelectric power” includes water driven generators and appurtenant facilities for the generation of electric power and structures for the protection of the generators on appurtenant facilities.

The plant or plants so constructed shall be operated in a manner which is compatible with the proper operation of the district’s water storage, transmission, and distribution system. Construction of the plant or plants and transmission lines may be financed by the issuance of general obligation bonds or revenue bonds or any other method of financing district works authorized in this division.

(Added by Stats. 1981, Ch. 79, Sec. 2.)

31149.2.
  

The hydroelectric power plant or plants and transmission lines constructed pursuant to this article may be leased for operation by, or the power generated may be sold to, a public utility or public agency engaged in the distribution, use, or sale of electricity. The power generated may be used by a district for its own purposes, or for the production or transmission of water, but shall not be offered for sale directly by a district to customers other than such a public utility or public agency. The power to acquire works and facilities shall not include, and nothing in this article shall be interpreted to allow, the acquisition of property already employed in the generation of hydroelectric energy for public utility purposes, except by mutual agreement between the district and the owner of that property.

(Added by Stats. 1981, Ch. 79, Sec. 2.)

31149.3.
  

(a) The North Marin County Water District may construct, maintain, and operate one or more plants for the generation of power from wind or solar radiation, and the transmission lines for the conveyance thereof, and in connection therewith shall have all the powers set forth in this article for the generation of hydroelectric power.

(b) Notwithstanding Section 31149.1, the North Marin County Water District may use any water for the generation of hydroelectric power subject, however, to any limitations or provisions contained in Section 106.7, Part 2 (commencing with Section 1200) of Division 2, or any other provisions of law. The hydroelectric power shall be developed so as to meet the direct and indirect energy requirements of the district for the proper operation of the district’s water storage, transmission, and distribution system.

(c) The authority contained in subdivision (b), in the case of sole projects of the North Marin County Water District, may only be exercised by the district if the project is approved by the board of supervisors of the county in which the project is located or, in the case of joint projects, may only be exercised by the district if the project is approved by contract with the public agency acting as lead agency on the project.

(Amended by Stats. 1984, Ch. 468, Sec. 1.)

31149.4.
  

Notwithstanding Section 31149.1 or any other provision of law, the Sierra Lakes County Water District may construct works for generating hydroelectric power, at Lake Dulzura and Lake Serena and on Serena Creek in Placer County, and may operate and maintain the works, or contract for that operation or maintenance.

Construction of the works authorized by this section may be financed by the issuance of general obligation bonds or revenue bonds or any other method of financing authorized by law for public agencies. The power generated may be used by the district for its own purposes, but shall not be offered for sale directly by the district to customers other than a public utility or public agency engaged in the distribution, use, or sale of electricity.

Any of the powers may be exercised jointly with other public agencies authorized to exercise those powers. The power to acquire works and facilities does not include, and nothing in this section authorizes, the acquisition of property already employed in the generation of hydroelectric energy for public utility purposes, except by mutual agreement between the district and the owner of that property. The authority to construct, maintain, and operate works pursuant to this section applies only to works constructed and maintained after January 1, 1984.

(Added by Stats. 1984, Ch. 795, Sec. 1.)

31149.5.
  

(a) The Marina County Water District may finance, construct, maintain, operate, lease, use, and sell power to any public utility or public agency from one or more plants within the district’s boundaries for the cogeneration of electric power in conjunction with facilities for removing dissolved solids and impurities from seawater, and may finance, construct, maintain, operate, and lease the transmission lines for the conveyance of the power.

(b) Prior to January 1, 1996, the district may not exercise the authority set forth in subdivision (a) to provide water that is a substitute for water from the Monterey County Water Resources Agency’s seawater intrusion project.

(Added by Stats. 1992, Ch. 456, Sec. 1. Effective January 1, 1993.)

31149.7.
  

(a) A district may provide, generate, and deliver electric power, and may construct, operate, and maintain any and all works, facilities, improvements, and property, or portion thereof, necessary or convenient for that generation and delivery.

(b) The electric powerplant or plants and transmission lines constructed pursuant to this section may be leased for operation. The power generated shall be used by a district for its own purposes. A district may sell surplus power to a public or private entity that is engaged in the distribution or sale of electricity. For purposes of this section, “for its own purposes” means a district performing only functions in its capacity as a water district, including, but not be limited to, any of the following:

(1) Pumping operations.

(2) Water treatment operations.

(3) Barrier intrusion operations.

(4) Desalination operations.

(c) Nothing in this section grants to a district the authority to provide, sell, or deliver electric power at retail.

(d) A district may not acquire property employed in the generation or delivery of electric power for public or private utility purposes, except by mutual agreement between the district and the owner of that property.

(e) (1) It is the intent of the Legislature, that each district that has purchased electricity from an electrical corporation on or after February 1, 2001, regardless of whether the district thereafter generates its own electricity, bear a pro rata share of the Department of Water Resources’ electricity purchase costs, that are recoverable from electrical corporation customers in commission-approved rates. It is the further intent of the Legislature to prevent any shifting of recoverable costs from districts that generate their own electricity pursuant to this section, to electrical corporation bundled customers.

(2) To the extent that any shifting of recoverable costs would occur, in the determination of the commission, those costs shall be recovered from districts that generate their own electricity, pursuant to this section.

(3) The Legislature finds and declares that the revisions of this subdivision are consistent with the requirements of Chapter 4 of the Statutes of 2001, First Extraordinary Session, and do not constitute a change in, but are declaratory of existing law.

(f) A district that generates its own electricity pursuant to this section shall be responsible for paying the following:

(1) A charge equivalent to the charges that would otherwise be imposed on the district by the commission to recover bond related costs pursuant to any agreement between the commission and the Department of Water Resources pursuant to Section 80110 of the Water Code, which charges shall be payable until all obligations of the Department of Water Resources pursuant to Division 27 (commencing with Section 80000) of the Water Code are fully paid or otherwise discharged. All bond charges are the property of the Department of Water Resources.

(2) If a district generates new offsite power, it shall be responsible for the additional costs of the Department of Water Resources, equal to the share of the Department of Water Resources’ estimated net unavoidable electricity purchase contract costs attributable to the district as determined by the commission, for the period commencing with the district’s initial generation of its offsite electricity, through the expiration of all then existing electricity purchase contracts entered into by the Department of Water Resources.

(g) A district generating its own electricity pursuant to this section shall reimburse the electrical corporation that previously served the district for all of the following:

(1) The electrical corporation’s unrecovered past undercollections for electricity purchases, including any financing costs, attributable to that district, that the commission lawfully determines may be recovered in rates.

(2) Any additional costs of the electrical corporation recoverable in commission approved rates, equal to the share of the electrical corporation’s estimated net unavoidable electricity purchase contract costs attributable to the district, as determined by the commission, for the period commencing with the district’s initial generation of electricity pursuant to this section, through the expiration of all then existing electricity purchase contracts entered into by the electrical corporation.

(h) (1) Any charges imposed pursuant to subdivision (f) shall be the property of the Department of Water Resources. Any charges imposed pursuant to subdivision (g) shall be the property of the particular electrical corporation. The commission shall establish sufficient mechanisms, including agreements with, or orders with respect to, electrical corporations as are necessary to ensure that charges payable pursuant to this section shall be promptly remitted to the party entitled to the payment.

(2) Charges imposed pursuant to this section shall be nonbypassable.

(i) Prior to implementing this section, the commission shall submit a report certifying its satisfaction of the provisions of this section to the Senate Energy, Utilities and Communications Committee, or its successor, and the Assembly Committee on Utilities and Commerce, or its successor.

(Added by Stats. 2002, Ch. 848, Sec. 1. Effective January 1, 2003.)

WATWater Code - WAT11.