Code Section Group

Civil Code - CIV

DIVISION 1. PERSONS [38 - 86]

  ( Heading of Division 1 amended by Stats. 1988, Ch. 160, Sec. 12. )

PART 2.52. CONSTRUCTION-RELATED ACCESSIBILITY STANDARDS COMPLIANCE [55.51 - 55.545]
  ( Part 2.52 added by Stats. 2008, Ch. 549, Sec. 3. )

55.51.
  

This part shall be known, and may be cited, as the Construction-Related Accessibility Standards Compliance Act. Notwithstanding any other provision of law, the provisions of this part shall apply to any construction-related accessibility claim, as defined in this part, including, but not limited to, any claim brought under Section 51, 54, 54.1, or 55.

(Added by Stats. 2008, Ch. 549, Sec. 3. Effective January 1, 2009. Became operative on date prescribed by Sec. 12 (subd. (a)) of Ch. 549. Section may become inoperative under conditions prescribed by Stats. 2008, Ch. 549, Sec. 12, subd. (b).)

55.52.
  

(a) For purposes of this part, the following definitions apply:

(1) “Construction-related accessibility claim” means any civil claim in a civil action with respect to a place of public accommodation, including, but not limited to, a claim brought under Section 51, 54, 54.1, or 55, based wholly or in part on an alleged violation of any construction-related accessibility standard, as defined in paragraph (6).

(2) “Application for stay and early evaluation conference” means an application to be filed with the court that meets the requirements of subdivision (c) of Section 55.54.

(3) “Certified access specialist” or “CASp” means any person who has been certified pursuant to Section 4459.5 of the Government Code.

(4) “Meets applicable standards” means the site was inspected by a CASp and determined to meet all applicable construction-related accessibility standards pursuant to paragraph (1) of subdivision (a) of Section 55.53. A site that is “CASp inspected” on or before the effective date of the amendments made to this section by Senate Bill 1186 of the 2011–12 Regular Session of the Legislature means that the site “meets applicable standards.”

(5) “Inspected by a CASp” means the site was inspected by a CASp and is pending a determination by the CASp that the site meets applicable construction-related accessibility standards pursuant to paragraph (2) of subdivision (a) of Section 55.53. A site that is “CASp determination pending” on or before the effective date of the amendments made to this section by Senate Bill 1186 of the 2011–12 Regular Session of the Legislature means that the site was “inspected by a CASp.”

(6) “Construction-related accessibility standard” means a provision, standard, or regulation under state or federal law requiring compliance with standards for making new construction and existing facilities accessible to persons with disabilities, including, but not limited to, any provision, standard, or regulation set forth in Section 51, 54, 54.1, or 55 of this code, Section 19955.5 of the Health and Safety Code, the California Building Standards Code (Title 24 of the California Code of Regulations), the federal Americans with Disabilities Act of 1990 (Public Law 101-336; 42 U.S.C. Sec. 12101 et seq.), and the federal Americans with Disabilities Act Accessibility Guidelines (Appendix A to Part 36 of Title 28 of the Code of Federal Regulations).

(7) “Place of public accommodation” has the same meaning as “public accommodation,” as set forth in Section 12181(7) of Title 42 of the United States Code and the federal regulations adopted pursuant to that section.

(8) “Qualified defendant” means a defendant in an action that includes a construction-related accessibility claim that is asserted against a place of public accommodation that met the requirements of “meets applicable standards” or “inspected by a CASp” prior to the date the defendant was served with the summons and complaint in that action. To be a qualified defendant, the defendant is not required to have been the party who hired any CASp, so long as the basis of the alleged liability of the defendant is a construction-related accessibility claim. To determine whether a defendant is a qualified defendant, the court need not make a finding that the place of public accommodation complies with all applicable construction-related accessibility standards as a matter of law. The court need only determine that the place of public accommodation has a status of “meets applicable standards” or “inspected by a CASp.”

(9) “Site” means a place of public accommodation.

(b) Unless otherwise indicated, terms used in this part relating to civil procedure have the same meanings that those terms have in the Code of Civil Procedure.

(Amended by Stats. 2012, Ch. 383, Sec. 7. (SB 1186) Effective September 19, 2012. Section may become inoperative under conditions prescribed by Stats. 2008, Ch. 549, Sec. 12, subd. (b).)

55.53.
  

(a) For purposes of this part, a certified access specialist shall, upon completion of the inspection of a site, comply with the following:

(1) For a meets applicable standards site, if the CASp determines the site meets all applicable construction-related accessibility standards, the CASp shall provide a written inspection report to the requesting party that includes both of the following:

(A) An identification and description of the inspected structures and areas of the site.

(B) A signed and dated statement that includes both of the following:

(i) A statement that, in the opinion of the CASp, the inspected structures and areas of the site meet construction-related accessibility standards. The statement shall clearly indicate whether the determination of the CASp includes an assessment of readily achievable barrier removal.

(ii) If corrections were made as a result of the CASp inspection, an itemized list of all corrections and dates of completion.

(2) For an inspected by a CASp site, if the CASp determines that corrections are needed to the site in order for the site to meet all applicable construction-related accessibility standards, the CASp shall provide a signed and dated written inspection report to the requesting party that includes all of the following:

(A) An identification and description of the inspected structures and areas of the site.

(B) The date of the inspection.

(C) A statement that, in the opinion of the CASp, the inspected structures and areas of the site need correction to meet construction-related accessibility standards. This statement shall clearly indicate whether the determination of the CASp includes an assessment of readily achievable barrier removal.

(D) An identification and description of the structures or areas of the site that need correction and the correction needed.

(E) A schedule of completion for each of the corrections within a reasonable timeframe.

(3) The CASp shall provide, within 30 days of the date of the inspection of a business that qualifies for the provisions of subparagraph (A) of paragraph (3) of subdivision (g) of Section 55.56, a copy of a report prepared pursuant to that subparagraph to the business.

(4) The CASp shall file, within 10 days of inspecting a business pursuant to subparagraph (A) of paragraph (3) of subdivision (g) of Section 55.56, a notice with the State Architect for listing on the State Architect’s Internet Web site, as provided by subdivision (d) of Section 4459.7 of the Government Code, indicating that the CASp has inspected the business, the name and address of the business, the date of the filing, the date of the inspection of the business, the name and license number of the CASp, and a description of the structure or area inspected by the CASp.

(5) The CASp shall post the notice described in paragraph (4), in a form prescribed by the State Architect, in a conspicuous location within five feet of all public entrances to the building on the date of the inspection and instruct the business to keep it in place until the earlier of either of the following:

(A) One hundred twenty days after the date of the inspection.

(B) The date when all of the construction-related violations in the structure or area inspected by the CASp are corrected.

(b) For purposes of this section, in determining whether the site meets applicable construction-related accessibility standards when there is a conflict or difference between a state and federal provision, standard, or regulation, the state provision, standard, or regulation shall apply unless the federal provision, standard, or regulation is more protective of accessibility rights.

(c) Every CASp who conducts an inspection of a place of public accommodation shall, upon completing the inspection of the site, provide the building owner or tenant who requested the inspection with the following notice, which the State Architect shall make available as a form on the State Architect’s Internet Web site:

NOTICE TO PRIVATE PROPERTY OWNER/TENANT:

YOU ARE ADVISED TO KEEP IN YOUR RECORDS ANY WRITTEN INSPECTION REPORT AND ANY OTHER DOCUMENTATION CONCERNING YOUR PROPERTY SITE THAT IS GIVEN TO YOU BY A CERTIFIED ACCESS SPECIALIST.

IF YOU BECOME A DEFENDANT IN A LAWSUIT THAT INCLUDES A CLAIM CONCERNING A SITE INSPECTED BY A CERTIFIED ACCESS SPECIALIST, YOU MAY BE ENTITLED TO A COURT STAY (AN ORDER TEMPORARILY STOPPING ANY LAWSUIT) OF THE CLAIM AND AN EARLY EVALUATION CONFERENCE.

IN ORDER TO REQUEST THE STAY AND EARLY EVALUATION CONFERENCE, YOU WILL NEED TO VERIFY THAT A CERTIFIED ACCESS SPECIALIST HAS INSPECTED THE SITE THAT IS THE SUBJECT OF THE CLAIM. YOU WILL ALSO BE REQUIRED TO PROVIDE THE COURT AND THE PLAINTIFF WITH THE COPY OF A WRITTEN INSPECTION REPORT BY THE CERTIFIED ACCESS SPECIALIST, AS SET FORTH IN CIVIL CODE SECTION 55.54. THE APPLICATION FORM AND INFORMATION ON HOW TO REQUEST A STAY AND EARLY EVALUATION CONFERENCE MAY BE OBTAINED AT www.courts.ca.gov/selfhelp-start.htm.

YOU ARE ENTITLED TO REQUEST, FROM A CERTIFIED ACCESS SPECIALIST WHO HAS CONDUCTED AN INSPECTION OF YOUR PROPERTY, A WRITTEN INSPECTION REPORT AND OTHER DOCUMENTATION AS SET FORTH IN CIVIL CODE SECTION 55.53. YOU ARE ALSO ENTITLED TO REQUEST THE ISSUANCE OF A DISABILITY ACCESS INSPECTION CERTIFICATE, WHICH YOU MAY POST ON YOUR PROPERTY.


(d) (1) Commencing July 1, 2010, a local agency shall employ or retain at least one building inspector who is a certified access specialist. The certified access specialist shall provide consultation to the local agency, permit applicants, and members of the public on compliance with state construction-related accessibility standards with respect to inspections of a place of public accommodation that relate to permitting, plan checks, or new construction, including, but not limited to, inspections relating to tenant improvements that may impact access. If a local agency employs or retains two or more certified access specialists to comply with this subdivision, at least one-half of the certified access specialists shall be building inspectors who are certified access specialists.

(2) Commencing January 1, 2014, a local agency shall employ or retain a sufficient number of building inspectors who are certified access specialists to conduct permitting and plan check services to review for compliance with state construction-related accessibility standards by a place of public accommodation with respect to new construction, including, but not limited to, projects relating to tenant improvements that may impact access. If a local agency employs or retains two or more certified access specialists to comply with this subdivision, at least one-half of the certified access specialists shall be building inspectors who are certified access specialists.

(3) If a permit applicant or member of the public requests consultation from a certified access specialist, the local agency may charge an amount limited to a reasonable hourly rate, an estimate of which shall be provided upon request in advance of the consultation. A local government may additionally charge or increase permitting, plan check, or inspection fees to the extent necessary to offset the costs of complying with this subdivision. Any revenues generated from an hourly or other charge or fee increase under this subdivision shall be used solely to offset the costs incurred to comply with this subdivision. A CASp inspection pursuant to subdivision (a) by a building inspector who is a certified access specialist shall be treated equally for legal and evidentiary purposes as an inspection conducted by a private CASp. Nothing in this subdivision shall preclude permit applicants or any other person with a legal interest in the property from retaining a private CASp at any time.

(e) (1) Every CASp who completes an inspection of a place of public accommodation shall, upon a determination that the site meets applicable standards pursuant to paragraph (1) of subdivision (a) or is inspected by a CASp pursuant to paragraph (2) of subdivision (a), provide the building owner or tenant requesting the inspection with a numbered disability access inspection certificate indicating that the site has undergone inspection by a certified access specialist. The disability access inspection certificate shall be dated and signed by the CASp inspector, and shall contain the inspector’s name and license number. Upon issuance of a certificate, the CASp shall record the issuance of the numbered certificate, the name and address of the recipient, and the type of report issued pursuant to subdivision (a) in a record book the CASp shall maintain for that purpose.

(2) Beginning March 1, 2009, the State Architect shall make available for purchase by any local building department or CASp sequentially numbered disability access inspection certificates that are printed with a watermark or other feature to deter forgery and that comply with the information requirements specified in subdivision (a).

(3) The disability access inspection certificate may be posted on the premises of the place of public accommodation, unless, following the date of inspection, the inspected site has been modified or construction has commenced to modify the inspected site in a way that may impact compliance with construction-related accessibility standards.

(f) Nothing in this section or any other law is intended to require a property owner or tenant to hire a CASp. A property owner’s or tenant’s election not to hire a CASp shall not be admissible to prove that person’s lack of intent to comply with the law.

(Amended by Stats. 2016, Ch. 13, Sec. 1. (SB 269) Effective May 10, 2016. Subd. (c) may become inoperative under conditions prescribed by Stats. 2008, Ch. 549, Sec. 12, subd. (b).)

55.54.
  

(a) (1) An attorney who causes a summons and complaint to be served in an action that includes a construction-related accessibility claim, including, but not limited to, a claim brought under Section 51, 54, 54.1, or 55, shall, at the same time, cause to be served a copy of the application form specified in subdivision (c) and a copy of the following notice, including, until January 1, 2013, the bracketed text, to the defendant on separate papers that shall be served with the summons and complaint:


ADVISORY NOTICE TO DEFENDANT


YOU MAY BE ENTITLED TO ASK FOR A COURT STAY (AN ORDER TEMPORARILY STOPPING ANY LAWSUIT) AND EARLY EVALUATION CONFERENCE IN THIS LAWSUIT AND MAY BE ASSESSED REDUCED STATUTORY DAMAGES IF YOU MEET CERTAIN CONDITIONS.

If the construction-related accessibility claim pertains to a site that has a Certified Access Specialist (CASp) inspection report for that site, or to a site where new construction or improvement was approved after January 1, 2008, by the local building permit and inspection process, you may make an immediate request for a court stay and early evaluation conference in the construction-related accessibility claim by filing the attached application form with the court. You may be entitled to the court stay and early evaluation conference regarding the accessibility claim only if ALL of the statements in the application form applicable to you are true.

FURTHER, if you are a defendant described above (with a CASp inspection report or with new construction after January 1, 2008), and, to the best of your knowledge, there have been no modifications or alterations completed or commenced since the CASp report or building department approval of the new construction or improvement that impacted compliance with construction-related accessibility standards with respect to the plaintiff’s claim, your liability for minimum statutory damages may be reduced to $1,000 for each offense, unless the violation was intentional, and if all construction-related accessibility violations giving rise to the claim are corrected within 60 days of being served with this complaint.

ALSO, if your business has been served with a complaint filed by a high-frequency litigant, as defined in subdivision (b) of Section 425.55 of the Code of Civil Procedure, asserting a construction-related accessibility claim, including, but not limited to, a claim brought under Section 51, 54, 54.1, or 55 of the Civil Code, you may also be entitled to a court stay and an early evaluation conference. If you choose to request a stay and early evaluation conference, you may also request to meet in person with the plaintiff and counsel for both parties, as well as experts if the parties so elect, at the subject premises no later than 30 days after issuance of the court order to jointly inspect the portions of the subject premises and review any conditions that are claimed to constitute a violation of a construction-related accessibility standard.

IN ADDITION, if your business is a small business that, over the previous three years, or the existence of the business if less than three years, employs 25 or fewer employees on average over that time period and meets specified gross receipts criteria, you may also be entitled to the court stay and early evaluation conference and your minimum statutory damages for each claim may be reduced to $2,000 for each offense, unless the violation was intentional, and if all the alleged construction-related accessibility violations are corrected within 30 days of being served with the complaint.

If you plan to correct the violations giving rise to the claim, you should take pictures and measurements or similar action to document the condition of the physical barrier asserted to be the basis for a violation before undertaking any corrective action in case a court needs to see the condition of a barrier before it was corrected.

The court will schedule the conference to be held within 70 days after you file the attached application form.

[If you are not a defendant with a CASp inspection report, until a form is adopted by the Judicial Council, you may use the attached form if you modify the form and supplement it with your declaration stating any one of the following:

(1) Until January 1, 2018, that the site’s new construction or improvement on or after January 1, 2008, and before January 1, 2016, was approved pursuant to the local building permit and inspection process; that, to the best of your knowledge, there have been no modifications or alterations completed or commenced since the building department approval that impacted compliance with construction-related accessibility standards with respect to the plaintiff’s claim; and that all violations giving rise to the claim have been corrected, or will be corrected within 60 days of the complaint being served.

(2) That the site’s new construction or improvement passed inspection by a local building department inspector who is a certified access specialist; that, to the best of your knowledge, there have been no modifications or alterations completed or commenced since that inspection approval that impacted compliance with construction-related accessibility standards with respect to the plaintiff’s claim; and that all violations giving rise to the claim have been corrected, or will be corrected within 60 days of the complaint being served.

(3) That your business is a small business with 25 or fewer employees and meets the gross receipts criteria set out in Section 55.56 of the Civil Code, and that all violations giving rise to the claim have been corrected, or will be corrected within 30 days of being served with the complaint.]

The court will also issue an immediate stay of the proceedings unless the plaintiff has obtained a temporary restraining order in the construction-related accessibility claim. You may obtain a copy of the application form, filing instructions, and additional information about the stay and early evaluation conference through the Judicial Council Internet Web site at www.courts.ca.gov/selfhelp-start.htm.

You may file the application after you are served with a summons and complaint, but no later than your first court pleading or appearance in this case, which is due within 30 days after you receive the summons and complaint. If you do not file the application, you will still need to file your reply to the lawsuit within 30 days after you receive the summons and complaint to contest it. You may obtain more information about how to represent yourself and how to file a reply without hiring an attorney at www.courts.ca.gov/selfhelp-start.htm.

You may file the application without the assistance of an attorney, but it may be in your best interest to immediately seek the assistance of an attorney experienced in disability access laws when you receive a summons and complaint. You may make an offer to settle the case, and it may be in your interest to put that offer in writing so that it may be considered under Section 55.55 of the Civil Code.


(2) An attorney who files a Notice of Substitution of Counsel to appear as counsel for a plaintiff who, acting in propria persona, had previously filed a complaint in an action that includes a construction-related accessibility claim, including, but not limited to, a claim brought under Section 51, 54, 54.1, or 55, shall, at the same time, cause to be served a copy of the application form specified in subdivision (c) and a copy of the notice specified in paragraph (1) upon the defendant on separate pages that shall be attached to the Notice of Substitution of Counsel.

(b) (1) Notwithstanding any other law, upon being served with a summons and complaint asserting a construction-related accessibility claim, including, but not limited to, a claim brought under Section 51, 54, 54.1, or 55, a qualified defendant, or other defendant as defined in paragraph (2), may file a request for a court stay and early evaluation conference in the proceedings of that claim prior to or simultaneous with that defendant’s responsive pleading or other initial appearance in the action that includes the claim. If that defendant filed a timely request for stay and early evaluation conference before a responsive pleading was due, the period for filing a responsive pleading shall be tolled until the stay is lifted. Any responsive pleading filed simultaneously with a request for stay and early evaluation conference may be amended without prejudice, and the period for filing that amendment shall be tolled until the stay is lifted.

(2) This subdivision shall also apply to a defendant if any of the following apply:

(A) Until January 1, 2018, the site’s new construction or improvement on or after January 1, 2008, and before January 1, 2016, was approved pursuant to the local building permit and inspection process, and the defendant declares with the application that, to the best of the defendant’s knowledge, there have been no modifications or alterations completed or commenced since that approval that impacted compliance with construction-related accessibility standards with respect to the plaintiff’s claim, and that all violations have been corrected, or will be corrected within 60 days of being served with the complaint.

(B) The site’s new construction or improvement was approved by a local public building department inspector who is a certified access specialist, and the defendant declares with the application that, to the best of the defendant’s knowledge, there have been no modifications or alterations completed or commenced since that approval that impacted compliance with construction-related accessibility standards with respect to the plaintiff’s claim, and that all violations have been corrected, or will be corrected within 60 days of being served with the complaint.

(C) The defendant is a small business described in subdivision (f) of Section 55.56, and the defendant declares with the application that all violations have been corrected, or will be corrected within 30 days of being served with the complaint.

(D) The defendant is a business that has been served with a complaint filed by a high-frequency litigant, as defined in subdivision (b) of Section 425.55 of the Code of Civil Procedure, asserting a construction-related accessibility claim, including, but not limited to, a claim brought under Section 51, 54, 54.1, or 55.

(3) Notwithstanding any other law, if the plaintiff had acted in propria persona in filing a complaint that includes a construction-related accessibility claim, including, but not limited to, a claim brought under Section 51, 54, 54.1, or 55, a qualified defendant, or a defendant described by paragraph (2), who is served with a Notice of Substitution of Counsel shall have 30 days to file an application for a stay and an early evaluation conference. The application may be filed prior to or after the defendant’s filing of a responsive pleading or other initial appearance in the action that includes the claim, except that an application may not be filed in a claim in which an early evaluation conference or settlement conference has already been held on the claim.

(c) (1) An application for an early evaluation conference and stay by a qualified defendant shall include a signed declaration that states both of the following:

(A) The site identified in the complaint has been CASp-inspected or meets applicable standards, or is CASp determination pending or has been inspected by a CASp, and if the site is CASp-inspected or meets applicable standards, there have been no modifications completed or commenced since the date of inspection that may impact compliance with construction-related accessibility standards to the best of the defendant’s knowledge.

(B) An inspection report pertaining to the site has been issued by a CASp. The inspection report shall be provided to the court and the plaintiff at least 15 days prior to the court date set for the early evaluation conference.

(2) An application for an early evaluation conference and stay by a defendant described by subparagraph (A) of paragraph (2) of subdivision (b), which may be filed until January 1, 2018, shall include a signed declaration that states all of the following:

(A) The site’s new construction or improvement was approved pursuant to the local building permit and inspection process on or after January 1, 2008, and before January 1, 2016.

(B) To the best of the defendant’s knowledge there have been no modifications or alterations completed or commenced since that approval that impacted compliance with construction-related accessibility standards with respect to the plaintiff’s claim.

(C) All construction-related violations giving rise to the claim have been corrected, or will be corrected within 60 days of the complaint being served upon the defendant.

(3) An application for an early evaluation conference and stay by a defendant described in subparagraph (B) of paragraph (2) of subdivision (b) shall include a signed declaration that states all of the following:

(A) The site’s new construction or improvement was approved by a local building department inspector who is a certified access specialist.

(B) To the best of the defendant’s knowledge there have been no modifications or alterations completed or commenced since that approval that impacted compliance with construction-related accessibility standards with respect to the plaintiff’s claim.

(C) All construction related violations giving rise to the claim have been corrected, or will be corrected within 60 days of the complaint being served upon the defendant.

(4) An application for an early evaluation conference and stay by a defendant described by subparagraph (C) of paragraph (2) of subdivision (b) shall include the materials listed in paragraphs (5) and (6) of this subdivision, and shall include a signed declaration that states both of the following:

(A) The defendant is a small business that employs 25 or fewer employees and meets the gross receipts eligibility criteria provided in paragraph (2) of subdivision (f) of Section 55.56.

(B) All construction-related violations giving rise to the claim have been corrected, or will be corrected within 30 days of the complaint being served upon the defendant.

(5) An application for an early evaluation conference and stay by a small business defendant under paragraph (4) shall include evidence showing correction of all violations within 30 days of the service of the complaint and served upon the plaintiff with the reply unless the application is filed prior to completion of the corrections. In that event, the evidence shall be provided to the court and served upon the plaintiff within 10 days of the court order as provided in paragraph (4) of subdivision (d). This paragraph shall not be construed to extend the permissible time under subdivision (f) of Section 55.56 to make the corrections.

(6) An application for an early evaluation conference and stay by a small business defendant under paragraph (4) shall also include both of the following, which shall be confidential documents filed only with the court and not served upon or available to the plaintiff:

(A) Proof of the defendant’s number of employees, as shown by wage report forms filed with the Employment Development Department.

(B) Proof of the defendant’s average gross receipts for the previous three years, or for the existence of the business if less than three years, as shown by a federal or state tax document.

(7) An application for an early evaluation conference and stay by a defendant described by subparagraph (D) of paragraph (2) of subdivision (b) shall include a signed declaration that the defendant was served with a complaint filed by a high-frequency litigant, as defined in subdivision (b) of Section 425.55 of the Code of Civil Procedure, asserting a construction-related accessibility claim, including, but not limited to, a claim brought under Section 51, 54, 54.1, or 55.

(8) The following provisional request and notice forms may be used and filed by a qualified defendant until forms are adopted by the Judicial Council for those purposes pursuant to subdivision (l):


* * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * *


NOTICE OF INCOMPLETE TEXT: Forms relating to
Stay of Proceedings and Early Evaluation Conference
appear in the published chaptered bill.
See Sec. 4, Chapter 755 (pp. 23–25), Statutes of 2015.


* * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * * *

(9) The provisional forms and any replacement Judicial Council forms shall include the defendant’s declaration of proof of service of the application, the notice of the court’s order, and the court’s order pursuant to subdivision (d).

(d) Upon the filing of an application for stay and early evaluation conference by a qualified defendant, or a defendant described by paragraph (2) of subdivision (b), the court shall immediately issue an order that does all of the following:

(1) Grants a 90-day stay of the proceedings with respect to the construction-related accessibility claim, unless the plaintiff has obtained temporary injunctive relief that is still in place for the construction-related accessibility claim.

(2) Schedules a mandatory early evaluation conference for a date as soon as possible from the date of the order, but in no event later than 70 days after issuance of the order, and in no event earlier than 50 days after the filing of the request.

(3) Directs the parties, and any other person whose authority is required to negotiate and enter into settlement, to appear in person at the time set for the conference. Appearance by counsel shall not satisfy the requirement that the parties or those with negotiation and settlement authority personally appear, provided, however, that the court may allow a party who is unable to attend in person due to his or her disability to participate in the hearing by telephone or other alternative means or through a representative authorized to settle the case.

(4) (A) Directs the qualified defendant to file with the court and serve on the plaintiff a copy of any relevant CASp inspection report at least 15 days before the date of the conference. The CASp inspection report is confidential and is available only as set forth in paragraph (5) of this subdivision and in paragraph (4) of subdivision (e).

(B) Directs a defendant described by subparagraph (A) or (B) of paragraph (2) of subdivision (b) who has filed a declaration stating that the violation or violations have been corrected, or will be corrected within 60 days of service of the complaint to file with the court and serve on the plaintiff evidence showing correction of the violation or violations within 10 calendar days after the completion of the corrections.

(C) Directs a defendant described by subparagraph (C) of paragraph (2) of subdivision (b) who has filed a declaration stating that the violation or violations have been corrected, or will be corrected within 30 days of service of the complaint to file with the court and serve on the plaintiff within 10 days after issuance of the court order evidence of correction of the violation or violations, if that evidence showing correction was not filed previously with the application and served on the plaintiff.

(5) Directs the parties that the CASp inspection report may be disclosed only to the court, the parties to the action, the parties’ attorneys, those individuals employed or retained by the attorneys to assist in the litigation, and insurance representatives or others involved in the evaluation and settlement of the case.

(6) If the defendant so requests, directs the parties that no later than 30 days after issuance of the court order the parties and their counsel, accompanied by their experts if the parties so elect, shall meet in person at the subject premises. They shall jointly inspect the portions of the subject premises, and shall review any programmatic or policy issues, that are claimed to constitute a violation of a construction-related accessibility standard. The court may allow a plaintiff who is unable to meet in person at the subject premises to be excused from participating in a site visit or to participate by telephone or other alternative means for good cause. A plaintiff or plaintiff’s counsel is not required, but may agree, to attend more than one in-person site meeting. A site inspection pursuant to this paragraph shall not affect the right of the parties to conduct otherwise appropriate discovery.

(7) Directs the plaintiff to file with the court and serve on the defendant at least 15 days before the date of the conference a statement that includes, to the extent reasonably known, for use solely for the purpose of the early evaluation conference, all of the following:

(A) An itemized list of specific conditions on the subject premises that are the basis of the claimed violations of construction-related accessibility standards in the plaintiff’s complaint.

(B) The amount of damages claimed.

(C) The amount of attorney’s fees and costs incurred to date, if any, that are being claimed.

(D) Any demand for settlement of the case in its entirety.

(e) (1) A party failing to comply with any court order may be subject to court sanction at the court’s discretion.

(2) (A) The court shall lift the stay when the defendant has failed to file and serve the CASp inspection report prior to the early evaluation conference and has failed also to produce the report at the time of the early evaluation conference, unless the defendant shows good cause for that failure.

(B) The court shall lift the stay when a defendant described by paragraph (2) of subdivision (b) has failed to file and serve the evidence showing correction of the violation or violations as required by law.

(3) The court may lift the stay at the conclusion of the early evaluation conference upon a showing of good cause by the plaintiff. Good cause may include the defendant’s failure to make reasonably timely progress toward completion of corrections noted by a CASp.

(4) The CASp inspection report filed and served pursuant to subdivision (d) shall remain confidential throughout the stay and shall continue to be confidential until the conclusion of the claim, whether by dismissal, settlement, or final judgment, unless there is a showing of good cause by any party. Good cause may include the defendant’s failure to make reasonably timely progress toward completion of corrections noted by a CASp. The confidentiality of the inspection report shall terminate upon the conclusion of the claim, unless the owner of the report obtains a court order pursuant to the California Rules of Court to seal the record.

(f) All discussions at the early evaluation conference shall be subject to Section 1152 of the Evidence Code. It is the intent of the Legislature that the purpose of the evaluation conference shall include, but not be limited to, evaluation of all of the following, as applicable:

(1) Whether the defendant is entitled to the 90-day stay for some or all of the identified issues in the case, as a qualified defendant.

(2) The current condition of the site and the status of any plan of corrections, including whether the qualified defendant has corrected or is willing to correct the alleged violations, and the timeline for doing so.

(3) Whether subdivision (f) of Section 55.56 may be applicable to the case, and whether all violations giving rise to the claim have been corrected within the specified time periods.

(4) Whether the case, including any claim for damages or injunctive relief, can be settled in whole or in part.

(5) Whether the parties should share other information that may facilitate early evaluation and resolution of the dispute.

(g) Nothing in this section precludes any party from making an offer to compromise pursuant to Section 998 of the Code of Civil Procedure.

(h) For a claim involving a qualified defendant, as provided in paragraph (1) of subdivision (b), the court may schedule additional conferences and may extend the 90-day stay for good cause shown, but not to exceed one additional 90-day extension.

(i) Early evaluation conferences shall be conducted by a superior court judge or commissioner, or a court early evaluation conference officer. A commissioner shall not be qualified to conduct early evaluation conferences pursuant to this subdivision unless he or she has received training regarding disability access requirements imposed by the federal Americans with Disabilities Act of 1990 (Public Law 101-336; 42 U.S.C. Sec. 12101 et seq.), state laws that govern access to public facilities, and federal and state regulations adopted pursuant to those laws. For purposes of this subdivision, a “court early evaluation conference officer” means an attorney employed by the court who has received training regarding disability access requirements imposed by the federal Americans with Disabilities Act of 1990, state laws that govern access to public facilities, and federal and state regulations adopted pursuant to those laws. Attorneys serving in this capacity may also be utilized by the court for other purposes not related to these proceedings.

(j) Nothing in this part shall be deemed to make any inspection report, opinion, statement, or other finding or conclusion of a CASp binding on the court, or to abrogate in any manner the ultimate authority of the court to make all appropriate findings of fact and law. The CASp inspection report and any opinion, statement, finding, or conclusion therein shall be given the weight the trier of fact finds that it deserves.

(k) Nothing in this part shall be construed to invalidate or limit any California construction-related accessibility standard that provides greater or equal protection for the rights of individuals with disabilities than is afforded by the federal Americans with Disabilities Act (Public Law 101-336; 42 U.S.C. Sec. 12101 et seq.) and the federal regulations adopted pursuant to that act.

(l) (1) The Judicial Council shall, by January 1, 2013, prepare and post on its Internet Web site instructions and a form for use by a qualified defendant, or other defendant described by paragraph (2) of subdivision (b), to file an application for stay and early evaluation conference as provided in subdivisions (b) and (c), a form for the court’s notice of stay and early evaluation conference, and any other forms appropriate to implement the provisions relating to early evaluation conferences. Until those forms are adopted, the Judicial Council shall post on its Internet Web site the provisional forms set forth in subdivision (c).

(2) Until the adoption of the forms as provided in paragraph (1), the provisional application form may be used by a defendant described by paragraph (2) of subdivision (b).

(3) In lieu of the provisions specified in number 3 of page 1 of the application form set forth in paragraph (7) of subdivision (c), the application shall include one of the following declarations of the defendant as to the basis for the application, as follows:

(A) That all of the following apply to a defendant described by subparagraph (A) of paragraph (2) of subdivision (b):

(i) The site’s new construction or improvement was approved pursuant to the local building permit and inspection process on or after January 1, 2008, and before January 1, 2016.

(ii) To the best of the defendant’s knowledge there have been no modifications or alterations completed or commenced since that approval that impacted compliance with construction-related accessibility standards with respect to the plaintiff’s claim.

(iii) All the violations giving rise to the claim have been corrected, or will be corrected within 60 days of the complaint being served.

(B) That all of the following apply to a defendant described by subparagraph (B) of paragraph (2) of subdivision (b):

(i) The site’s new construction or improvement was approved by a local public building department inspector who is a certified access specialist.

(ii) To the best of the defendant’s knowledge there have been no modifications or alterations completed or commenced since that approval that impacted compliance with construction-related accessibility standards with respect to the plaintiff’s claim.

(iii) All the violations giving rise to the claim have been corrected, or will be corrected within 60 days of the complaint being served.

(C) That both of the following apply to a defendant described by subparagraph (C) of paragraph (2) of subdivision (b):

(i) The defendant is a small business described in paragraph (2) of subdivision (f) of Section 55.56.

(ii) The violation or violations giving rise to the claim have been corrected, or will be corrected within 30 days of the complaint being served.

(4) In lieu of the provision specified in number 4(c) of page 1 of the application form set forth in paragraph (7) of subdivision (c), the application shall include a request that the court order the defendant to do either of the following:

(A) For a defendant who has filed a declaration stating that all violations have been corrected, or will be corrected within 60 days of service of the complaint, file with the court and serve on the plaintiff evidence showing correction of the violation or violations within 10 calendar days of the completion of the corrections.

(B) For a defendant who is a small business that has filed a declaration stating that all the violations have been corrected, or will be corrected within 30 days of the service of the complaint, file with the court and serve on the plaintiff evidence showing correction of the violation or violations within 10 calendar days after issuance of the court order, if that evidence showing correction was not filed previously with the application and served on the plaintiff.

(5) The Judicial Council shall also prepare and post on its Internet Web site instructions and cover pages to assist plaintiffs and defendants, respectively, to comply with their filing responsibilities under subdivision (d). The cover pages shall also provide for the party’s declaration of proof of service of the pertinent document served under the court order.

(m) The stay provisions shall not apply to any construction-related accessibility claim in which the plaintiff has been granted temporary injunctive relief that remains in place.

(n) This section shall not apply to any action brought by the Attorney General, or by any district attorney, city attorney, or county counsel.

(o) The amendments to this section made by Senate Bill 1186 of the 2011–12 Regular Session of the Legislature shall apply only to claims filed on or after the operative date of that act. Nothing in this part is intended to affect any complaint filed before that date.

(p) Nothing in this part is intended to affect existing law regarding class action requirements.

(Amended by Stats. 2015, Ch. 755, Sec. 4. (AB 1521) Effective October 10, 2015. Subd. (a) may become inoperative, and other provisions may have limited operation, under conditions prescribed by Stats. 2008, Ch. 549, Sec. 12, subd. (b). Note: See published chaptered bill for complete section text. Forms relating to Stay of Proceedings and Early Evaluation Conference appear on pages 17 to 19 of Ch. 755.)

55.545.
  

(a) A defendant who does not qualify for an early evaluation conference pursuant Section 55.54, or who forgoes the provisions of Section 55.54, may request a mandatory evaluation conference. A plaintiff may, if the defendant does not make the request with the filing of the responsive pleadings, request a mandatory evaluation conference by filing an application within 15 days of the defendant’s filing of responsive pleadings.

(b) Upon being served with a summons and complaint asserting a construction-related accessibility claim, including, but not limited to, a claim brought under Section 51, 54, 54.1, or 55, a defendant may file an application for a mandatory evaluation conference in the proceedings of that claim simultaneous with the defendant’s responsive pleading or other initial appearance in the action that includes the claim. Until the application form for the mandatory evaluation conference is developed by the Judicial Council and posted on its Internet Web site pursuant to subdivision (j), a defendant may request the calendaring of the mandatory evaluation conference in a separate application filed with the defendant’s responsive pleadings.

(c) Upon the filing of a request or application for a mandatory evaluation conference by a defendant or plaintiff, the court shall schedule a mandatory evaluation conference for a date as soon as possible from the date of the request or application, but in no event later than 180 days after the date of request or application, or earlier than 120 days after the filing of the request or application. Upon mutual stipulation for an extension of the conference date, the mandatory evaluation conference may be extended for up to 30 days. The court’s notice of conference shall also do all of the following:

(1) Direct the parties, and any other person whose authority is required to negotiate and enter into settlement, to appear in person at the time set for the conference. Appearance by counsel shall not satisfy the requirement that the parties, or those with negotiation and settlement authority, personally appear. However, the court may allow a party who is unable to attend in person due to his or her disability to participate in the hearing by telephone or other alternative means, or through a representative authorized to settle the case.

(2) Direct the plaintiff to file with the court and serve on the defendant, at least 30 days before the date of mandatory evaluation conference, a statement that includes, to the extent reasonably known, for use solely for the purpose of the mandatory evaluation conference, all of the following:

(A) An itemized list of specific conditions on the site that are the basis of the claimed violations of construction-related accessibility standards in the plaintiff’s complaint.

(B) The amount of damages claimed.

(C) The amount of attorney’s fees and costs incurred to date, if any, that are being claimed.

(D) Any demand for settlement of the case in its entirety.

(3) Direct the defendant to file with the court and serve on the plaintiff, at least 30 days before the date of the mandatory evaluation conference, a statement of the defendant detailing any remedial action or remedial correction plan undertaken, or to be undertaken, by the defendant to correct the alleged violations.

(d) A party failing to comply with any court order is subject to court sanction at the court’s discretion.

(e) All discussions at the mandatory evaluation conference shall be subject to Section 1152 of the Evidence Code. It is the intent of the Legislature that the purpose of the evaluation conference shall include, but not be limited to, evaluation of all of the following:

(1) The current condition of the site and the status of any plan of correction, including whether the defendant has corrected, or is willing to correct, the alleged violations, and the timeline for doing so.

(2) Whether the case, including any claim for damages or injunctive relief, can be settled in whole or in part.

(3) Whether the parties should share other information that may facilitate evaluation and resolution of the dispute.

(f) Nothing in this section precludes any party from making an offer to compromise pursuant to Section 998 of the Code of Civil Procedure.

(g) The court may schedule additional conferences.

(h) Mandatory evaluation conferences shall be conducted by a superior court judge or commissioner, or by a court early evaluation conference officer as provided in subdivision (i) of Section 55.54.

(i) If an inspection report by a certified access specialist is offered by the defendant, the provisions of Section 55.54 relating to the use and confidentiality of that report shall apply.

(j) (1) The Judicial Council shall prepare and post on its Internet Web site instructions and a form for a party to use to file an application for a mandatory evaluation conference and a form for the court’s notice of the mandatory evaluation conference. Until those forms are adopted, a party and the court may use an ad hoc form that complies with the requirements of this section.

(2) The Judicial Council shall also prepare and post on its Internet Web site instructions and cover pages to assist plaintiffs and defendants, respectively, to comply with their filing responsibilities under subdivision (c).

(k) The mandatory evaluation conference may, at the court’s discretion, be scheduled or combined with the case management conference within the time period specified in subdivision (c).

(l) This section shall not apply to any action brought by the Attorney General, or by any district attorney, city attorney, or county counsel.

(m) This section shall apply only to claims filed on or after January 1, 2013. Nothing in this section is intended to affect any complaint filed before that date.

(Added by Stats. 2012, Ch. 383, Sec. 10. (SB 1186) Effective September 19, 2012.)