Code Section

Public Utilities Code - PUC

DIVISION 1. REGULATION OF PUBLIC UTILITIES [201 - 3297]

  ( Division 1 enacted by Stats. 1951, Ch. 764. )
  

PART 1. PUBLIC UTILITIES ACT [201 - 2120]

  ( Part 1 enacted by Stats. 1951, Ch. 764. )
  

CHAPTER 5. Certificates of Public Convenience and Necessity [1001 - 1103]

  ( Chapter 5 enacted by Stats. 1951, Ch. 764. )
  

ARTICLE 5. Electrical and Gas Corporations [1091 - 1103]
  ( Article 5 added by Stats. 1982, Ch. 1253, Sec. 5. )

  
1097.  

(a) For purposes of assisting the construction project board of consultants in monitoring project construction, the corporation shall submit the current design, estimate of project costs, implementation schedule, and draft construction contracts to the commission and the construction project board of consultants before awarding any major construction contract. The corporation shall inform the commission and the board of all bid quotations and any significant exceptions which the bidders may have taken to the corporation’s engineering designs, specifications, and draft contracts.

(b) The examination by the commission and the construction project board of consultants of documents furnished pursuant to this section shall be conducted so as not to unreasonably delay the contracts, bidding, and awards process.

(Added by Stats. 1982, Ch. 1253, Sec. 5.)