Code Section

Civil Code - CIV

DIVISION 4. GENERAL PROVISIONS [3274 - 9566]

  ( Heading of Division 4 amended by Stats. 1988, Ch. 160, Sec. 16. )
  

PART 6. WORKS OF IMPROVEMENT [8000 - 9566]

  ( Part 6 added by Stats. 2010, Ch. 697, Sec. 20. )
  

TITLE 3. PUBLIC WORK OF IMPROVEMENT [9000 - 9566]

  ( Title 3 added by Stats. 2010, Ch. 697, Sec. 20. )
  

CHAPTER 5. Payment Bond [9550 - 9566]
  ( Chapter 5 added by Stats. 2010, Ch. 697, Sec. 20. )

  
9566.  

(a) A claimant does not have a right to recover on a payment bond unless the claimant provided work to the direct contractor either directly or through one or more subcontractors pursuant to a public works contract.

(b) Nothing in this section affects the stop payment notice rights of, and relative priorities among, design professionals.

(Added by Stats. 2010, Ch. 697, Sec. 20. (SB 189) Effective January 1, 2011. Operative July 1, 2012, by Sec. 105 of Ch. 697 and by Section 8052.)