Civil Code - CIV
DIVISION 4. GENERAL PROVISIONS [3274 - 9566]
( Heading of Division 4 amended by Stats. 1988, Ch. 160, Sec. 16. ) PART 6. WORKS OF IMPROVEMENT [8000 - 9566]
( Part 6 added by Stats. 2010, Ch. 697, Sec. 20. ) TITLE 2. PRIVATE WORKS OF IMPROVEMENT [8160 - 8848]
( Title 2 added by Stats. 2010, Ch. 697, Sec. 20. ) CHAPTER 5. Stop Payment Notice [8500 - 8560]
( Chapter 5 added by Stats. 2010, Ch. 697, Sec. 20. ) ARTICLE 3. Stop Payment Notice to Construction Lender [8530 - 8538]
( Article 3 added by Stats. 2010, Ch. 697, Sec. 20. ) 8536.
(a) Except as provided in subdivision (b), on receipt of a stop payment notice a construction lender shall withhold from the borrower or other person to whom the lender or the owner is obligated to make payments or advancement out of the construction fund sufficient funds to pay the claim stated in the notice.
(b) The construction lender
may, at its option, elect not to withhold funds in any of the following circumstances:
(1) The stop payment notice is unbonded.
(2) The stop payment notice is given by a claimant other than a direct contractor, and a payment bond is recorded before the lender is given any stop payment notice.
(Added by Stats. 2010, Ch. 697, Sec. 20. (SB 189) Effective January 1, 2011. Operative July 1, 2012, by Sec. 105 of Ch. 697 and by Section 8052.)