10791.
(a) A person who extracts or uses water from a groundwater basin within 20 miles of the boundaries of Joshua Tree National Park for purposes of construction and operation of a closed-loop pumped hydroelectric energy storage system shall submit to the board any plans, technical reports, or monitoring data reports related to groundwater required under any license for hydroelectric generation issued by the Federal Energy Regulatory Commission pursuant to subsection (1) of Section 23(b) of the Federal Power Act (16 U.S.C. Sec. 817).(b) Unless otherwise provided by federal law, the materials to be submitted under subdivision (a) shall include all plans, reports, and monitoring data provided to the Federal Energy Regulatory Commission in connection with any of the following:
(1) (A) A site-specific groundwater level monitoring plan that ensures the water supply pumping rate will result in water levels that are at or above maximum allowable change thresholds for the applicable groundwater aquifer. The plan shall include, at a minimum, provisions for all of the following:
(i) Twenty-four months of groundwater level monitoring to establish baseline groundwater levels before the initial use of water for reservoir filling.
(ii) Sampling the monitoring wells at least monthly during the initial fill period, at least quarterly for the first seven years of pumped hydroelectric energy storage system operations, and semiannually thereafter for the term of the license.
(iii) If water levels fall to within one foot of maximum allowable change thresholds or if trends indicate that levels may drop below those thresholds due to pumped hydroelectric energy storage system pumping, management of pumped hydroelectric energy storage system water level drawdowns through either reducing the pumping rate, reducing the pumping duration, or changing the pumping location, provided that the water levels will be maintained at all times at or above the maximum allowable change thresholds.
(B) For purposes of this section, “maximum allowable change thresholds” mean the change, measured in feet, that the water level at a monitoring well may decrease in reference to an elevation above sea level or any other method of water level measurement set forth in an applicable license issued by the Federal Energy Regulatory Commission.
(2) A site-specific groundwater quality monitoring plan to monitor for any adverse effects of seepage from the pumped hydroelectric energy storage facility’s reservoirs and evaporation ponds on groundwater quality. The plan shall provide for, at a minimum, all of the following:
(A) Two years of preproject operation baseline groundwater quality monitoring data for the project’s reservoirs, desalination ponds, seepage recovery wells, and water supply wells, as applicable.
(B) Monitoring groundwater quality for the pumped hydroelectric energy storage system’s reservoirs, desalination ponds, seepage recovery wells, and water supply wells over the term of the license, as applicable.
(C) Identifying specific sampling locations, methods, and frequency.
(D) Specifying constituent features to be analyzed, including salinity, odor, and trace metals.
(E) The applicant to file annual monitoring reports with the board.
(F) An implementation schedule.
(c) The materials to be submitted to the board pursuant to subdivision (a) shall also include any of the following provided to the Federal Energy Regulatory Commission:
(1) A soil erosion and sedimentation control plan or other plans designed to mitigate the effects of soil and vegetation loss, as well as any revegetation plan or other plans designed to revegetate any areas affected by the project.
(2) An inflow design flood and hazard classification study or other plans designed to evaluate and assess potential downstream hazards in the event of a dam failure.
(3) A groundwater level monitoring plan or other plans designed to confirm that the project’s water supply pumping rate will be maintained at levels that are in the historical range.
(4) A groundwater quality monitoring plan or other plans designed to monitor for any adverse effects of seepage into the groundwater.
(5) An aquifer testing plan or other plans designed to model groundwater levels.
(6) A salt management storage and disposal plan or other plans designed to characterize potential waste streams and provide for proper storage and disposal of such streams.
(7) A water and soil pollution prevention plan, air quality monitoring plan, or other plans designed to ensure the safe construction and operation of the plant and mitigate any potential pollution issues.
(d) A person required to submit the materials described in this section to the board shall do so on the same schedule and in the same manner as provided in the license issued pursuant to subsection (1) of Section 23(b) of the Federal Power Act (16 U.S.C. Sec. 817).
(e) A person who fails to timely submit the materials described in this section shall be subject to a penalty of up to ten thousand dollars ($10,000) per day, as assessed by the board, for noncompliance.
(f) The board shall review the materials submitted pursuant to this section. If the board concludes the person is not in compliance with its hydroelectric generating license from the Federal Energy Regulatory Commission, the board may petition the Federal Energy Regulatory Commission to ensure compliance with all of the terms and conditions of the license.
(g) (1) Subject to federal law, the extraction of groundwater in excess of maximum allowable change thresholds by a pumped hydroelectric energy storage facility subject to this section, regardless of whether the groundwater basin is subject to an adjudication under California law, is prohibited unless the extraction is permitted following consideration of an action or project that requires discretionary approval by a state or local governmental entity.
(2) Excess extraction of groundwater in violation of this subdivision shall be subject to enforcement by the board pursuant to the standards and procedures set forth in subdivisions (b), (c), and (e) of Section 13350, provided that any civil penalty imposed pursuant to subdivision (e) of Section 13350 shall be imposed on a per gallon basis so that each gallon of groundwater extracted in excess of the maximum allowable change thresholds shall be subject to a civil penalty not to exceed ten dollars ($10), with the aggregate penalty not to exceed one million dollars ($1,000,000).
(h) (1) The Joshua Tree National Park Environmental Protection Fund is hereby established in the State Treasury. Civil penalties imposed pursuant to this part shall be deposited in the fund.
(2) Moneys in the Joshua Tree National Park Environmental Protection Fund are available, upon appropriation by the Legislature, to mitigate the environmental harms caused by the extraction or use of water from a groundwater basin within 20 miles of the boundaries of Joshua Tree National Park for purposes of construction and operation of a pumped hydroelectric energy storage system.