85089.
(a) Construction of a new Delta conveyance facility shall not be initiated until the persons or entities that contract to receive water from the State Water Project and the federal Central Valley Project or a joint powers authority representing those entities have made arrangements or entered into contracts to pay for both of the following:(a) (1) The costs of the environmental review, planning, design, construction, and mitigation, including mitigation required pursuant to Division 13 (commencing with Section 21000 21000) of the Public Resources Code), Code, required for the construction, operation, and maintenance of any new Delta water conveyance facility.
(b) (2) Full mitigation of property tax or assessments levied by local governments or special districts for land used in the construction, location, mitigation, or operation of new Delta conveyance facilities.
(b) Before a water contractor enters into a contract to pay for the costs described in subdivision (a), the lead agency shall provide both of the following:
(1) The breakdown of costs for each water contractor entering into a contract.
(2) What benefits each contractor will receive based on the proportion the contractor has financed of the new Delta conveyance facility.