8386.
(a) Each electrical corporation shall construct, maintain, and operate its electrical lines and equipment in a manner that will minimize the risk of catastrophic wildfire posed by those electrical lines and equipment.(b) Each electrical corporation shall annually prepare and submit a wildfire mitigation plan for the next compliance period to the commission for review. The wildfire mitigation plan shall include:
(1) An accounting of the responsibilities of persons responsible for executing the plan.
(2) The objectives of the plan.
(3) A description of the preventive strategies and programs to be adopted by the electrical corporation to minimize the risk of its electrical lines and equipment causing catastrophic wildfires.
(4) A description of the metrics the electrical corporation plans to use to evaluate the plan’s performance and the assumptions that underlie the use of those metrics.
(5) A discussion of how the application of previously identified metrics to previous plan performances has informed the plan.
(6) A description of the processes and procedures the electrical corporation will use to do the following:
(A) Monitor and audit the implementation of the plan.
(B) Identify any deficiencies in the plan or the plan’s implementation and correct those deficiencies.
(C) Monitor and audit the effectiveness of electrical line and equipment inspections, including inspections performed by contractors, carried out under the plan and other applicable statutes and commission rules.
(7) Any other information that the commission may require.
(c) The commission shall act expeditiously, but no later than 30 days before the beginning of the compliance period, to review and comment on the electrical corporation’s wildfire mitigation plan.
(d) The commission shall provide the electrical corporation with an opportunity to amend a wildfire mitigation plan in response to commission comments within 30 days.
(e) The commission shall conduct or contract for audits to determine if an electrical corporation is satisfactorily complying with its wildfire mitigation plan.
(f) The commission may contract with an independent third party to evaluate wildfire mitigation plans or to conduct audits and inspections authorized by this section, and may require electrical corporations to reimburse any related expenses.