8385.
  

(a) For purposes of this chapter, the following shall apply:

(1) “Compliance period” means a period of approximately one year.

(2) “Electrical cooperative” has the same meaning as defined in Section 2776.

(b) The commission shall supervise an electrical corporation’s compliance with the requirements of this chapter pursuant to the Public Utilities Act (Part 1 (commencing with Section 201) of Division 1). Nothing in this chapter affects the commission’s authority or jurisdiction over an electrical cooperative or local publicly owned electrical corporation.

(Added by Stats. 2016, Ch. 598, Sec. 1. (SB 1028) Effective January 1, 2017.)

8386.
  

(a) Each electrical corporation shall construct, maintain, and operate its electrical lines and equipment in a manner that will minimize the risk of catastrophic wildfire posed by those electrical lines and equipment.

(b) Each electrical corporation shall annually prepare and submit a wildfire mitigation plan to the division for review and approval. In calendar year 2020, and thereafter, the plan shall cover at least a three-year period. The division shall establish a schedule for the submission of subsequent comprehensive wildfire mitigation plans, which may allow for the staggering of compliance periods for each electrical corporation. In its discretion, the division may allow the annual submissions to be updates to the last approved comprehensive wildfire mitigation plan; provided, that each electrical corporation shall submit a comprehensive wildfire mitigation plan at least once every three years.

(c) The wildfire mitigation plan shall include all of the following:

(1) An accounting of the responsibilities of persons responsible for executing the plan.

(2) The objectives of the plan.

(3) A description of the preventive strategies and programs to be adopted by the electrical corporation to minimize the risk of its electrical lines and equipment causing catastrophic wildfires, including consideration of dynamic climate change risks.

(4) A description of the metrics the electrical corporation plans to use to evaluate the plan’s performance and the assumptions that underlie the use of those metrics.

(5) A discussion of how the application of previously identified metrics to previous plan performances has informed the plan.

(6) Protocols for disabling reclosers and deenergizing portions of the electrical distribution system that consider the associated impacts on public safety, as well as protocols related to mitigating the public safety impacts of those protocols, including impacts on critical first responders and on health and communication infrastructure.

(7) Appropriate and feasible procedures for notifying a customer who may be impacted by the deenergizing of electrical lines. The procedures shall consider the need to notify, as a priority, critical first responders, health care facilities, and operators of telecommunications infrastructure.

(8) Plans for vegetation management.

(9) Plans for inspections of the electrical corporation’s electrical infrastructure.

(10) A list that identifies, describes, and prioritizes all wildfire risks, and drivers for those risks, throughout the electrical corporation’s service territory, including all relevant wildfire risk and risk mitigation information that is part of Safety Model Assessment Proceeding and Risk Assessment Mitigation Phase filings. The list shall include, but not be limited to, both of the following:

(A) Risks and risk drivers associated with design, construction, operations, and maintenance of the electrical corporation’s equipment and facilities.

(B) Particular risks and risk drivers associated with topographic and climatological risk factors throughout the different parts of the electrical corporation’s service territory.

(11) A description of how the plan accounts for the wildfire risk identified in the electrical corporation’s Risk Assessment Mitigation Phase filing.

(12) A description of the actions the electrical corporation will take to ensure its system will achieve the highest level of safety, reliability, and resiliency, and to ensure that its system is prepared for a major event, including hardening and modernizing its infrastructure with improved engineering, system design, standards, equipment, and facilities, such as undergrounding, insulation of distribution wires, and pole replacement.

(13) A showing that the utility has an adequate sized and trained workforce to promptly restore service after a major event, taking into account employees of other utilities pursuant to mutual aid agreements and employees of entities that have entered into contracts with the utility.

(14) Identification of any geographic area in the electrical corporation’s service territory that is a higher wildfire threat than is currently identified in a commission fire threat map, and where the commission should consider expanding the high fire threat district based on new information or changes in the environment.

(15) A methodology for identifying and presenting enterprise-wide safety risk and wildfire-related risk that is consistent with the methodology used by other electrical corporations unless the commission determines otherwise.

(16) A description of how the plan is consistent with the electrical corporation’s disaster and emergency preparedness plan prepared pursuant to Section 768.6, including both of the following:

(A) Plans to prepare for, and to restore service after, a wildfire, including workforce mobilization and prepositioning equipment and employees.

(B) Plans for community outreach and public awareness before, during, and after a wildfire, including language notification in English, Spanish, and the top three primary languages used in the state other than English or Spanish, as determined by the commission based on the United States Census data.

(17) A statement of how the electrical corporation will restore service after a wildfire.

(18) Protocols for compliance with requirements adopted by the commission regarding activities to support customers during and after a wildfire, outage reporting, support for low-income customers, billing adjustments, deposit waivers, extended payment plans, suspension of disconnection and nonpayment fees, repair processing and timing, access to utility representatives, and emergency communications.

(19) A description of the processes and procedures the electrical corporation will use to do all of the following:

(A) Monitor and audit the implementation of the plan.

(B) Identify any deficiencies in the plan or the plan’s implementation and correct those deficiencies.

(C) Monitor and audit the effectiveness of electrical line and equipment inspections, including inspections performed by contractors, carried out under the plan and other applicable statutes and commission rules.

(20) Any other information that the Wildfire Safety Division may require.

(d) The Wildfire Safety Division shall post all wildfire mitigation plans and annual updates on the commission’s internet website for no less than two months before the Wildfire Safety Division’s decision regarding approval of the plan. The Wildfire Safety Division shall accept comments on each plan from the public, other local and state agencies, and interested parties, and verify that the plan complies with all applicable rules, regulations, and standards, as appropriate.

(Amended by Stats. 2019, Ch. 79, Sec. 17. (AB 1054) Effective July 12, 2019.)

8386.1.
  

The commission shall assess penalties on an electrical corporation that fails to substantially comply with its plan. In determining an appropriate amount of the penalty, the commission shall consider all of the following:

(a) The nature and severity of any noncompliance with the plan, including whether the noncompliance resulted in harm.

(b) The extent to which the commission has found that the electrical corporation complied with its plans in prior years.

(c) Whether the electrical corporation self-reported the circumstances constituting noncompliance.

(d) Whether the electrical corporation implemented corrective actions with respect to the noncompliance.

(e) Whether the electrical corporation knew or in the exercise of reasonable care should have known of the circumstances constituting noncompliance.

(f) Whether the electrical corporation had previously engaged in conduct of a similar nature that caused significant property damage or injury.

(g) Any other factors established by the commission in a rulemaking proceeding, consistent with this section.

(Added by Stats. 2018, Ch. 626, Sec. 39. (SB 901) Effective January 1, 2019.)

8386.2.
  

The commission shall require a safety culture assessment of each electrical corporation to be conducted by an independent third-party evaluator. The commission shall set the schedule for each assessment, including updates to the assessment at least every five years. The electrical corporation shall not seek reimbursement for the costs of the assessment from ratepayers.

(Added by Stats. 2018, Ch. 626, Sec. 40. (SB 901) Effective January 1, 2019.)

8386.3.
  

(a) The Wildfire Safety Division shall approve or deny each wildfire mitigation plan and update submitted by an electrical corporation within three months of its submission, unless the division makes a written determination, including reasons supporting the determination, that the three-month deadline cannot be met. Each electrical corporation’s approved plan shall remain in effect until the division approves the electrical corporation’s subsequent plan. The division shall consult with the Department of Forestry and Fire Protection on the review of each wildfire mitigation plan and update. In rendering its decision, the division shall consider comments submitted pursuant to subdivision (d) of Section 8386. Before approval, the division may require modifications of the plan. After approval by the division, the commission shall ratify the action of the division.

(b) The Wildfire Safety Division’s approval of a plan does not establish a defense to any enforcement action for a violation of a commission decision, order, or rule.

(c) Following approval of a wildfire mitigation plan, the Wildfire Safety Division shall oversee compliance with the plan consistent with the following:

(1) Three months after the end of an electrical corporation’s initial compliance period as established by the Wildfire Safety Division pursuant to subdivision (b) of Section 8386, and annually thereafter, each electrical corporation shall file with the division a report addressing its compliance with the plan during the prior calendar year.

(2) (A) Before March 1, 2021, and before each March 1 thereafter, the Wildfire Safety Division, in consultation with the Department of Forestry and Fire Protection, shall make available a list of qualified independent evaluators with experience in assessing the safe operation of electrical infrastructure.

(B) (i) Each electrical corporation shall engage an independent evaluator listed pursuant to subparagraph (A) to review and assess the electrical corporation’s compliance with its plan. The engaged independent evaluator shall consult with, and operate under the direction of, the Wildfire Safety Division of the commission. The independent evaluator shall issue a report on July 1 of each year in which a report required by paragraph (1) is filed. As a part of the independent evaluator’s report, the independent evaluator shall determine whether the electrical corporation failed to fund any activities included in its plan.

(ii) The Wildfire Safety Division shall consider the independent evaluator’s findings, but the independent evaluator’s findings are not binding on the division, except as otherwise specified.

(iii) The independent evaluator’s findings shall be used by the Wildfire Safety Division to carry out its obligations under Article 1 (commencing with Section 451) of Chapter 3 of Part 1 of Division 1.

(iv) The independent evaluator’s findings shall not apply to events that occurred before the initial plan is approved for the electrical corporation.

(3) The commission shall authorize the electrical corporation to recover in rates the costs of the independent evaluator.

(4) The Wildfire Safety Division shall complete its compliance review within 18 months after the submission of the electrical corporation’s compliance report.

(d) An electrical corporation shall not divert revenues authorized to implement the plan to any activities or investments outside of the plan.

(e) The commission shall not allow a large electrical corporation to include in its equity rate base its share, as determined pursuant to the Wildfire Fund allocation metric specified in Section 3280, of the first five billion dollars ($5,000,000,000) expended in aggregate by large electrical corporations on fire risk mitigation capital expenditures included in the electrical corporations’ approved wildfire mitigation plans. An electrical corporation’s share of the fire risk mitigation capital expenditures and the debt financing costs of these fire risk mitigation capital expenditures may be financed through a financing order pursuant to Section 851, subject to the requirements of that financing order.

(Added by Stats. 2019, Ch. 79, Sec. 18. (AB 1054) Effective July 12, 2019.)

8386.4.
  

(a) At the time of approval of an electrical corporation’s wildfire mitigation plan, the commission shall authorize the electrical corporation to establish a memorandum account to track costs incurred to implement the plan.

(b) (1) The commission shall consider whether the cost of implementing each electrical corporation’s plan is just and reasonable in its general rate case application. Each electrical corporation shall establish a memorandum account to track costs incurred for fire risk mitigation that are not otherwise covered in the electrical corporation’s revenue requirements. The commission shall review the costs in the memorandum accounts and disallow recovery of those costs the commission deems unreasonable.

(2) In lieu of paragraph (1), an electrical corporation may elect to file an application for recovery of the cost of implementing its plan as accounted in the memorandum account at the conclusion of the time period covered by the plan. If the electrical corporation files an application for cost recovery pursuant to this paragraph, the commission shall issue a proposed decision within 12 months of the filing date of the application unless the commission issues an order extending the deadline upon a finding of good cause.

(3) The chief executive officer of an electrical corporation shall certify in each general rate case application that the electrical corporation has not received authorization from the commission to recover the costs in a previous proceeding, including wildfire cost recovery applications.

(4) Nothing in this section shall be interpreted as a restriction or limitation on Article 1 (commencing with Section 451) of Chapter 3 of Part 1 of Division 1.

(Added by Stats. 2019, Ch. 79, Sec. 19. (AB 1054) Effective July 12, 2019.)

8386.5.
  

The commission and the Department of Forestry and Fire Protection shall enter into a memorandum of understanding to cooperatively develop consistent approaches and share data related to fire prevention, safety, vegetation management, and energy distribution systems. The commission and the department shall share results from various fire prevention activities, including relevant inspections and fire ignition data.

(Added by Stats. 2018, Ch. 626, Sec. 41. (SB 901) Effective January 1, 2019.)

8387.
  

(a) Each local publicly owned electric utility and electrical cooperative shall construct, maintain, and operate its electrical lines and equipment in a manner that will minimize the risk of wildfire posed by those electrical lines and equipment.

(b) (1) The local publicly owned electric utility or electrical cooperative shall, before January 1, 2020, prepare a wildfire mitigation plan. After January 1, 2020, a local publicly owned electric utility or electrical cooperative shall prepare a wildfire mitigation plan annually and shall submit the plan to the California Wildfire Safety Advisory Board on or before July 1 of that calendar year. Each local publicly owned electric utility and electrical cooperative shall update its plan annually and submit the update to the California Wildfire Safety Advisory Board by July 1 of each year. At least once every three years, the submission shall be a comprehensive revision of the plan.

(2) The wildfire mitigation plan shall consider as necessary, at minimum, all of the following:

(A) An accounting of the responsibilities of persons responsible for executing the plan.

(B) The objectives of the wildfire mitigation plan.

(C) A description of the preventive strategies and programs to be adopted by the local publicly owned electric utility or electrical cooperative to minimize the risk of its electrical lines and equipment causing catastrophic wildfires, including consideration of dynamic climate change risks.

(D) A description of the metrics the local publicly owned electric utility or electrical cooperative plans to use to evaluate the wildfire mitigation plan’s performance and the assumptions that underlie the use of those metrics.

(E) A discussion of how the application of previously identified metrics to previous wildfire mitigation plan performances has informed the wildfire mitigation plan.

(F) Protocols for disabling reclosers and deenergizing portions of the electrical distribution system that consider the associated impacts on public safety, as well as protocols related to mitigating the public safety impacts of those protocols, including impacts on critical first responders and on health and communication infrastructure.

(G) Appropriate and feasible procedures for notifying a customer who may be impacted by the deenergizing of electrical lines. The procedures shall consider the need to notify, as a priority, critical first responders, health care facilities, and operators of telecommunications infrastructure.

(H) Plans for vegetation management.

(I) Plans for inspections of the local publicly owned electric utility’s or electrical cooperative’s electrical infrastructure.

(J) A list that identifies, describes, and prioritizes all wildfire risks, and drivers for those risks, throughout the local publicly owned electric utility’s or electrical cooperative’s service territory. The list shall include, but not be limited to, both of the following:

(i) Risks and risk drivers associated with design, construction, operation, and maintenance of the local publicly owned electric utility’s or electrical cooperative’s equipment and facilities.

(ii) Particular risks and risk drivers associated with topographic and climatological risk factors throughout the different parts of the local publicly owned electric utility’s or electrical cooperative’s service territory.

(K) Identification of any geographic area in the local publicly owned electric utility’s or electrical cooperative’s service territory that is a higher wildfire threat than is identified in a commission fire threat map, and identification of where the commission should expand a high fire-threat district based on new information or changes to the environment.

(L) A methodology for identifying and presenting enterprisewide safety risk and wildfire-related risk.

(M) A statement of how the local publicly owned electric utility or electrical cooperative will restore service after a wildfire.

(N) A description of the processes and procedures the local publicly owned electric utility or electrical cooperative shall use to do all of the following:

(i) Monitor and audit the implementation of the wildfire mitigation plan.

(ii) Identify any deficiencies in the wildfire mitigation plan or its implementation, and correct those deficiencies.

(iii) Monitor and audit the effectiveness of electrical line and equipment inspections, including inspections performed by contractors, that are carried out under the plan, other applicable statutes, or commission rules.

(3) The local publicly owned electric utility or electrical cooperative shall, on or before January 1, 2020, and not less than annually thereafter, present its wildfire mitigation plan in an appropriately noticed public meeting. The local publicly owned electric utility or electrical cooperative shall accept comments on its wildfire mitigation plan from the public, other local and state agencies, and interested parties, and shall verify that the wildfire mitigation plan complies with all applicable rules, regulations, and standards, as appropriate.

(c) The local publicly owned electric utility or electrical cooperative shall contract with a qualified independent evaluator with experience in assessing the safe operation of electrical infrastructure to review and assess the comprehensiveness of its wildfire mitigation plan. The independent evaluator shall issue a report that shall be made available on the internet website of the local publicly owned electric utility or electrical cooperative, and shall present the report at a public meeting of the local publicly owned electric utility’s or electrical cooperative’s governing board.

(Amended by Stats. 2019, Ch. 79, Sec. 20. (AB 1054) Effective July 12, 2019.)

8388.
  

An electrical corporation, local publicly owned electric utility, or community choice aggregator with a contract to procure electricity generated from biomass pursuant to subdivision (b) of Section 399.20.3, commission Resolution E-4770 (March 17, 2016), or commission Resolution E-4805 (October 13, 2016), or with a contract that is operative at any time in 2018, and expires or expired on or before December 31, 2023, shall seek to amend the contract to include, or seek approval for a new contract that includes, an expiration date five years later than the expiration date in the contract that was operative in 2018, so long as the contract extension follows the feedstock requirement of subdivision (b) of Section 399.20.3. This section shall not apply to facilities located in federal severe or extreme nonattainment areas for particulate matter or ozone.

(Added by Stats. 2018, Ch. 626, Sec. 43. (SB 901) Effective January 1, 2019.)

8389.
  

(a) For purposes of this section, the following definitions apply:

(1) “Board” means the California Wildfire Safety Advisory Board established pursuant to Section 326.1.

(2) “Division” means the Wildfire Safety Division established pursuant to Section 326.

(b) By June 30, 2020, and annually thereafter, the board shall make recommendations to the division on all of the following:

(1) Appropriate performance metrics and processes for determining an electrical corporation’s compliance with its approved wildfire mitigation plan.

(2) Appropriate requirements in addition to the requirements set forth in Section 8386 for the wildfire mitigation plan.

(3) The appropriate scope and process for assessing the safety culture of an electrical corporation.

(c) By October 31, 2020, and annually thereafter, the division shall issue an analysis and recommendation to the commission on the recommendations provided by the board pursuant to subdivision (b).

(d) By December 1, 2020, and annually thereafter, the commission, after consultation with the division, shall adopt and approve all of the following:

(1) Performance metrics for electrical corporations.

(2) Additional requirements for wildfire mitigation plans.

(3) A wildfire mitigation plan compliance process.

(4) A process for the division to conduct annual safety culture assessments for each electrical corporation.

(e) The executive director of the commission shall issue a safety certification to an electrical corporation if the electrical corporation provides documentation of the following:

(1) The electrical corporation has an approved wildfire mitigation plan.

(2) The electrical corporation is in good standing, which can be satisfied by the electrical corporation having agreed to implement the findings of its most recent safety culture assessment, if applicable.

(3) The electrical corporation has established a safety committee of its board of directors composed of members with relevant safety experience.

(4) The electrical corporation has established an executive incentive compensation structure approved by the division and structured to promote safety as a priority and to ensure public safety and utility financial stability with performance metrics, including incentive compensation based on meeting performance metrics that are measurable and enforceable, for all executive officers, as defined in Section 451.5. This may include tying 100 percent of incentive compensation to safety performance and denying all incentive compensation in the event the electrical corporation causes a catastrophic wildfire that results in one or more fatalities.

(5) The electrical corporation has established board-of-director-level reporting to the commission on safety issues.

(6) (A) The electrical corporation has established a compensation structure for any new or amended contracts for executive officers, as defined in Section 451.5, that is based on the following principles:

(i) (I) Strict limits on guaranteed cash compensation, with the primary portion of the executive officers’ compensation based on achievement of objective performance metrics.

(II) No guaranteed monetary incentives in the compensation structure.

(ii) It satisfies the compensation principles identified in paragraph (4).

(iii) A long-term structure that provides a significant portion of compensation, which may take the form of grants of the electrical corporation’s stock, based on the electrical corporation’s long-term performance and value. This compensation shall be held or deferred for a period of at least three years.

(iv) Minimization or elimination of indirect or ancillary compensation that is not aligned with shareholder and taxpayer interest in the electrical corporation.

(B) The division shall approve the compensation structure of an electrical corporation if it determines the structure meets the principles set forth in subparagraph (A) and paragraph (4).

(C) It is the intent of the Legislature, in enacting this paragraph and paragraph (4), that any approved bankruptcy reorganization plan of an electrical corporation should, in regards to compensation for executive officers of the electrical corporation, comply with the requirements of those paragraphs.

(7) The electrical corporation is implementing its approved wildfire mitigation plan. The electrical corporation shall file a tier 1 advice letter on a quarterly basis that details the implementation of both its approved wildfire mitigation plan and recommendations of the most recent safety culture assessment, and a statement of the recommendations of the board of directors safety committee meetings that occurred during the quarter. The advice letter shall also summarize the implementation of the safety committee recommendations from the electrical corporation’s previous advice letter filing. If the division has reason to doubt the veracity of the statements contained in the advice letter filing, it shall perform an audit of the issue of concern.

(f) (1) The executive director shall issue an initial safety certification within 30 days of receipt of a request for that certification by an electrical corporation if the electrical corporation provides documentation that it is meeting the requirements set forth in paragraphs (1), (2), (3) and (5) of subdivision (e). A safety certification shall be valid for the 12 consecutive months following the issuance of the certification.

(2) Before the expiration of a certification, an electrical corporation shall submit to the division a request for certification for the following 12 months. The division shall issue a safety certification within 90 days of a request if the electrical corporation has provided documentation that it has satisfied the requirements in subdivision (e).

(3) All documents submitted pursuant to this section shall be publicly available on the commission’s internet website.

(4) Notwithstanding paragraph (1), a safety certification shall remain valid until the division acts on the electrical corporation’s pending request for safety certification.

(g) If the division determines an electrical corporation is not in compliance with its approved wildfire mitigation plan, it may recommend that the commission pursue an enforcement action against the electrical corporation for noncompliance with its approved plan.

(Added by Stats. 2019, Ch. 79, Sec. 21. (AB 1054) Effective July 12, 2019.)