AB-190 Local government: development permits: design review.(2017-2018)

SHARE THIS:share this bill in Facebookshare this bill in Twitter
Date Published: 02/23/2017 09:00 PM
AB190:v98#DOCUMENT

Amended  IN  Assembly  February 23, 2017

CALIFORNIA LEGISLATURE— 2017–2018 REGULAR SESSION

Assembly Bill No. 190


Introduced by Assembly Member Steinorth

January 19, 2017


An act to add Section 65950.3 to the Government Code, relating to local government.


LEGISLATIVE COUNSEL'S DIGEST


AB 190, as amended, Steinorth. Local government: development permits: design review.
The Permit Streamlining Act within the Planning and Zoning Law requires the lead agency that has the principal responsibility for approving a development project, as defined, to approve or disapprove the project within a specified number of days from the date of certification of an environmental impact report, the date of the adoption of a negative declaration, or the determination by the lead agency that the project is exempt from the California Environmental Quality Act.
This bill would require a lead agency, where an ordinance requiring design review applies to a development project, to approve or disapprove the design of the development project within 30 days of the application being determined to be complete, as specified. The bill would provide, that if the lead agency has not approved or disapproved the design of the development project within that 30-day period, the project is deemed to be approved on the 31st day.
Vote: MAJORITY   Appropriation: NO   Fiscal Committee: NO   Local Program: NO  

The people of the State of California do enact as follows:


SECTION 1.

 Section 65950.3 is added to the Government Code, to read:

65950.3.
 (a) If an ordinance requiring design review applies to a development project, the public agency that is the lead agency, as that term is defined in subdivision (d) of Section 65950, for a development project shall approve or disapprove the design of the development project within 30 days of the application being determined to be complete pursuant to Section 65943.
(b) If the public agency that is the lead agency has not approved or disapproved the design of the development project as required pursuant to subdivision (a), the development project shall be deemed approved on the 31st day after the application was determined to be complete pursuant to Section 65943.