AB-2241 State energy policy.(1999-2000)

SHARE THIS: share this bill in Facebook share this bill in Twitter
AB2241:v98#DOCUMENT

Amended  IN  Assembly  April 25, 2000

CALIFORNIA LEGISLATURE— 1999–2000 REGULAR SESSION

Assembly Bill
No. 2241


Introduced  by  Assembly Member Maldonado

February 24, 2000


An act to amend Section 368 25006 of the Public Resources Code, relating to public utilities.


LEGISLATIVE COUNSEL'S DIGEST


AB 2241, as amended, Maldonado. Public utilities: electrical restructuring: cost recovery plans State energy policy.
Existing law states the policy of the state and the intent of the Legislature to establish and consolidate the state’s responsibility for energy resources, for encouraging, developing, and coordinating research and development into energy supply and demand problems, and for regulating electrical generating and related transmission facilities.
This bill would require each state agency that regulates the operation of electrical generating and transmission facilities in the state to evaluate and consider the energy supply and reliability benefits of those facilities in connection with their regulation of those facilities, consistent with the policy of the state and the intent of the Legislature.

Existing law restructuring the electrical industry requires each electrical corporation to propose a cost recovery plan to the Public Utilities Commission for the recovery of the uneconomic costs of an electrical corporation’s generation-related assets and obligations, as prescribed.

This bill would make technical, nonsubstantive changes in those provisions.

Vote: MAJORITY   Appropriation: NO   Fiscal Committee: NO   Local Program: NO  

The people of the State of California do enact as follows:


SECTION 1.

Section 368 of the Public Utilities Code

Section 25006 of the Public Resources Code is amended to read:

25006.
 (a) It is the policy of the state and the intent of the Legislature to establish and consolidate the state’s responsibility for energy resources, for encouraging, developing, and coordinating research and development into energy supply and demand problems, and for regulating electrical generating and related transmission facilities.
(b) In furtherance of the policy stated in subdivision (a), each state agency that regulates the operation of electrical generating and transmission facilities in the state, including, but not limited to, regulation of the ratemaking, environmental, and land use impacts of those facilities, shall evaluate and consider the energy supply and reliability benefits of those facilities in connection with their regulation of those facilities, consistent with the policy of the state and the intent of the Legislature, as stated in subdivision (a) and Section 334 of the Public Utilities Code.

is amended to read:

368.

Each electrical corporation shall propose a cost recovery plan to the commission for the recovery of the uneconomic costs of an electrical corporation’s generation-related assets and obligations identified in Section 367. The commission shall authorize the electrical corporation to recover the costs pursuant to the plan if the plan meets all of the following criteria:

(a)The cost recovery plan shall set rates for each customer class, rate schedule, contract, or tariff option, at levels equal to the level as shown on electric rate schedules as of June 10, 1996, provided that rates for residential and small commercial customers shall be reduced so that these customers shall receive rate reductions of no less than 10 percent for 1998 continuing through 2002. These rate levels for each customer class, rate schedule, contract, or tariff option shall remain in effect until the earlier of March 31, 2002, or the date on which the commission-authorized costs for utility generation-related assets and obligations have been fully recovered. The electrical corporation shall be at risk for those costs not recovered during that time period. Each utility shall amortize its total uneconomic costs, to the extent possible, such that for each year during the transition period its recorded rate of return on the remaining uneconomic assets does not exceed its authorized rate of return for those assets. For purposes of determining the extent to which the costs have been recovered, any over-collections recorded in Energy Costs Adjustment Clause and Electric Revenue Adjustment Mechanism balancing accounts, as of December 31, 1996, shall be credited to the recovery of the costs.

(b)The cost recovery plan shall provide for identification and separation of individual rate components such as charges for energy, transmission, distribution, public benefit programs, and recovery of uneconomic costs. The separation of rate components required by this subdivision shall be used to ensure that customers of the electrical corporation who become eligible to purchase electricity from suppliers other than the electrical corporation pay the same unbundled component charges, other than energy, that a bundled service customer pays. No cost shifting among customer classes, rate schedules, contract, or tariff options shall result from the separation required by this subdivision. Nothing in this provision is intended to affect the rates, terms, and conditions, or to limit the use, of any Federal Energy Regulatory Commission-approved contract entered into by the electrical corporation prior to the effective date of this provision.

(c)In consideration of the risk that the uneconomic costs identified in Section 367 may not be recoverable within the period identified in subdivision (a) of Section 367, an electrical corporation that, as of December 20, 1995, served more than four million customers, and was also a gas corporation that served less than four thousand customers, shall have the flexibility to employ risk management tools, such as forward hedges, to manage the market price volatility associated with unexpected fluctuations in natural gas prices, and the out-of-pocket costs of acquiring the risk management tools shall be considered reasonable and collectible within the transition freeze period. This subdivision applies only to the transaction costs associated with the risk management tools and may not include any losses from changes in market prices.

(d) To ensure implementation of the cost recovery plan, the limitation on the maximum amount of cost recovery for nuclear facilities that may be collected in any year adopted by the commission in Decision 96-01-011 and Decision 96-04-059 shall be eliminated to allow the maximum opportunity to collect the nuclear costs within the transition cap period.

(e)As to an electrical corporation that is also a gas corporation serving more than four million California customers, so long as any cost recovery plan adopted in accordance with this section satisfies subdivision (a), it shall also provide for annual increases in base revenues, effective January 1, 1997, and January 1, 1998, equal to the inflation rate for the prior year plus two percentage points, as measured by the consumer price index. The increase shall do both of the following:

(1)Remain in effect pending the next general rate case review, which shall be filed not later than December 31, 1997, for rates that would become effective in January 1999. For purposes of any commission-approved performance-based ratemaking mechanism or general rate case review, the increases in base revenue authorized by this subdivision shall create no presumption that the level of base revenue reflecting those increases constitute the appropriate starting point for subsequent revenues.

(2)Be used by the utility for the purposes of enhancing its transmission and distribution system safety and reliability, including, but not limited to, vegetation management and emergency response. To the extent the revenues are not expended for system safety and reliability, they shall be credited against subsequent safety and reliability base revenue requirements. Any excess revenues carried over shall not be used to pay any monetary sanctions imposed by the commission.

(f)The cost recovery plan shall provide the electrical corporation with the flexibility to manage the renegotiation, buy-out, or buy-down of the electrical corporation’s power purchase obligations, consistent with review by the commission to assure that the terms provide net benefits to ratepayers and are otherwise reasonable in protecting the interests of both ratepayers and shareholders.

(g)An example of a cost recovery plan authorized by this section is the document entitled “Restructuring Rate Settlement” transmitted to the commission by Pacific Gas and Electric Company on June 12, 1996.